CALDWELL CR (0914-22-076)

Items: 50

County: CALDWELL
Length: N/A
Highway: CR
District: AUSTIN
Control Number: 0914-22-076
DBE Goal: N/A
Project: BR 2021(666)
Guaranty: N/A
Time: 45 WORKING DAYS
Engineer's Estimate: $741,610.00
Date: 02/01/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$741,610.00
$777,849.43
Over/Under Est: 4.89% $36,239.43
Over/Under Est: 4.92% $36,478.90
Amt Left: 0.03% $239.47
Over/Under Est: 6.15% $45,619.45
Amt Left: 1.21% $9,380.02
Delta: -1.17% -$9,140.55
Over/Under Est: 19.67% $145,838.58
Amt Left: 14.09% $109,599.15
Delta: -12.73% -$100,219.13
Over/Under Est: 19.71% $146,185.50
Amt Left: 14.13% $109,946.07
Delta: -0.04% -$346.92

Bid Items & Bid Tabulations

50 Total 0 of 50
CALDWELL  |  CR  |  AUSTIN  |  0914-22-076  |  02/01/2023  |  $741,610.00  |  BR 2021(666)  |  BRIDGE REPL  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SB CONTRACTORS LLC
ACME BRIDGE COMPANY, INC.
A GREATER AUSTIN DEVELOPMENT COMPANY, LLC
DAN WILLIAMS COMPANY
DELGADO'S CONTRACTORS, LLC
PREPARING ROW
STA 3.650 $5,000.000 $8,000.000 $6,000.000 $5,100.000 $18,000.000 $6,250.000
EXCAVATION (ROADWAY)
CY 257.000 $25.000 $9.420 $34.200 $55.000 $35.000 $20.000
EXCAVATION (CHANNEL)
CY 117.000 $25.000 $10.340 $33.400 $55.000 $38.000 $20.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 420.000 $25.000 $22.080 $28.000 $35.000 $35.000 $40.000
FURNISHING AND PLACING TOPSOIL (4")
SY 459.000 $4.000 $4.520 $8.500 $16.500 $2.500 $8.000
BROADCAST SEED (TEMP) (WARM)
SY 459.000 $0.500 $3.140 $2.900 $3.000 $0.310 $3.000
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 459.000 $4.500 $3.140 $2.900 $3.000 $0.810 $5.000
VEGETATIVE WATERING
MG 2.000 $75.000 $69.000 $202.000 $600.000 $10.000 $60.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 459.000 $2.000 $3.680 $3.400 $3.500 $2.500 $4.000
FL BS(CMP IN PLC)(TY D GR 5)(FNAL POS)
CY 290.000 $95.000 $109.260 $115.000 $125.000 $100.000 $150.000
PRIME COAT (MULTI OPTION)
GAL 315.000 $7.000 $9.770 $9.400 $7.250 $6.500 $7.000
CEM STABIL BKFL
CY 83.000 $175.000 $331.670 $200.000 $255.000 $270.000 $200.000
DRILL SHAFT (36 IN)
LF 210.000 $370.000 $348.620 $363.000 $385.000 $550.000 $550.000
CL C CONC (ABUT)
CY 39.700 $1,400.000 $1,352.860 $1,400.000 $1,035.000 $1,450.000 $1,400.000
REINF CONC SLAB
SF 1,950.000 $30.000 $46.660 $41.700 $31.650 $35.000 $42.000
APPROACH SLAB
CY 44.900 $780.000 $735.960 $855.000 $725.000 $750.000 $1,000.000
PRESTR CONC GIRDER (TX28)
LF 258.000 $250.000 $287.660 $279.000 $305.000 $295.000 $300.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 184.000 $300.000 $247.550 $177.000 $255.000 $165.000 $180.000
RIPRAP (MOW STRIP)(4 IN)
CY 30.000 $600.000 $767.250 $800.000 $765.000 $725.000 $600.000
RAIL (TY T223)
LF 178.000 $150.000 $226.130 $144.000 $150.000 $125.000 $155.000
ARMOR JOINT (SEALED)
LF 52.000 $130.000 $180.920 $195.000 $100.000 $125.000 $200.000
RC PIPE (CL III)(18 IN)
LF 50.000 $70.000 $105.910 $80.600 $115.000 $115.000 $200.000
SET (TY II) (18 IN) (RCP) (3: 1) (P)
EA 2.000 $1,550.000 $1,830.490 $1,940.000 $2,025.000 $1,500.000 $3,000.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $25,000.000 $26,000.000 $22,100.000 $27,500.000 $28,000.000 $35,000.000
REMOV STR (SMALL FENCE)
LF 400.000 $5.000 $3.190 $2.250 $6.000 $1.550 $5.000
MOBILIZATION
LS 1.000 $60,000.000 $75,000.000 $68,000.000 $77,800.000 $85,000.000 $95,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $6,000.000 $4,000.000 $5,000.000 $3,500.000 $20,000.000 $4,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 92.000 $35.000 $41.170 $38.000 $40.000 $40.000 $40.000
ROCK FILTER DAMS (REMOVE)
LF 92.000 $10.000 $8.050 $7.400 $8.000 $39.000 $10.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 20.000 $35.000 $56.360 $52.000 $55.000 $30.000 $50.000
CONSTRUCTION EXITS (REMOVE)
SY 20.000 $10.000 $23.010 $21.200 $22.000 $9.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 592.000 $4.000 $4.600 $4.250 $4.500 $4.000 $7.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 592.000 $1.000 $1.140 $1.050 $1.100 $1.250 $2.000
DRIVEWAYS AND TURNOUTS (ACP)
SY 105.000 $125.000 $76.020 $86.600 $58.000 $95.000 $100.000
MTL W-BEAM GD FEN (TIM POST)
LF 250.000 $35.000 $27.200 $25.600 $31.000 $34.000 $30.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $2,100.000 $1,190.390 $1,050.000 $1,458.000 $1,400.000 $1,500.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $3,700.000 $1,983.990 $1,410.000 $1,900.000 $1,800.000 $2,000.000
REMOVE METAL BEAM GUARD FENCE
LF 100.000 $4.000 $2.880 $3.200 $11.000 $5.000 $5.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $3,700.000 $3,312.400 $3,420.000 $3,170.000 $4,000.000 $3,750.000
WIRE FENCE (TY C)
LF 400.000 $25.000 $13.790 $15.900 $25.000 $20.000 $22.000
RELOCATE EXISTING MAILBOX
EA 1.000 $550.000 $402.550 $1,050.000 $825.000 $450.000 $250.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $700.000 $901.700 $231.000 $1,100.000 $1,000.000 $1,000.000
REMOVE SM RD SN SUP&AM
EA 7.000 $150.000 $102.360 $231.000 $150.000 $225.000 $150.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $30.000 $28.750 $30.900 $31.000 $30.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 13.000 $40.000 $28.750 $45.700 $50.000 $45.000 $90.000
REFL PAV MRKR TY II-A-A
EA 36.000 $4.000 $28.750 $133.000 $55.000 $30.000 $120.000
D-GR HMA TY-D PG 76-22 SAC-B (EXEMPT)
TON 158.000 $300.000 $172.520 $361.000 $331.000 $260.000 $280.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $8,000.000 $10,100.000 $5,500.000 $8,500.000 $10,000.000
TMA (STATIONARY)
DAY 20.000 $250.000 $200.000 $158.000 $355.000 $75.000 $450.000
TMA (MOBILE OPERATION)
DAY 10.000 $475.000 $150.000 $463.000 $710.000 $1.000 $450.000
Totals: $741,610.000 $777,849.436 $778,088.900 $787,229.450 $887,448.580 $887,795.500