CALDWELL FM 713 (0805-03-021)
Items: 29
County: CALDWELL
Length: 11.0950 MILES
Highway: FM 713
District: AUSTIN
Control Number: 0805-03-021
DBE Goal: 0.0%
Project: C 805-3-21
Guaranty: $43,000.00
Time: 43 WORKING DAYS
Engineer's Estimate: $2,141,975.10
Date: 09/05/2024 (1 year ago)
Contract Number: 9243027
Type: SEAL COAT
Project ID: A00135282
Project Description: FDR, LEVEL-UP AND SEAL COAT
Mail/Deliver Bids To: N/A
DIANA SCHULZE
CALDWELL FM 713 (0805-03-021)
Project Name: N/A
Project: C 805-3-21
Length: 11.0950 MILES
Project Type: SEAL COAT
Limits From: FM 86
Limits To: BASTROP COUNTY LINE
Project Description: FDR, LEVEL-UP AND SEAL COAT
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,141,975.10 | |||
| $2,033,352.21 |
-5.07%
-$108,622.89
|
|||
| $2,053,330.41 |
-4.14%
-$88,644.69
|
0.98%
$19,978.20
|
||
| $2,068,246.14 |
-3.44%
-$73,728.96
|
1.72%
$34,893.93
|
-0.73%
-$14,915.73
|
|
| $2,175,898.04 |
1.58%
$33,922.94
|
7.01%
$142,545.83
|
-5.20%
-$107,651.90
|
|
| $2,209,659.24 |
3.16%
$67,684.14
|
8.67%
$176,307.03
|
-1.55%
-$33,761.20
|
|
| $2,373,290.93 |
10.8%
$231,315.83
|
16.72%
$339,938.72
|
-7.41%
-$163,631.69
|
|
| $2,598,455.80 |
21.31%
$456,480.70
|
27.79%
$565,103.59
|
-9.49%
-$225,164.87
|
|
| $4,627,491.20 |
116.04%
$2,485,516.10
|
127.58%
$2,594,138.99
|
-78.09%
-$2,029,035.40
|
E
Engineer's Estimate
$2,141,975.10
1
Awarded
$2,033,352.21
Over/Under Est:
-5.07%
-$108,622.89
$2,053,330.41
Over/Under Est:
-4.14%
-$88,644.69
Amt Left:
0.98%
$19,978.20
$2,068,246.14
Over/Under Est:
-3.44%
-$73,728.96
Amt Left:
1.72%
$34,893.93
Delta:
-0.73%
-$14,915.73
$2,175,898.04
Over/Under Est:
1.58%
$33,922.94
Amt Left:
7.01%
$142,545.83
Delta:
-5.20%
-$107,651.90
$2,209,659.24
Over/Under Est:
3.16%
$67,684.14
Amt Left:
8.67%
$176,307.03
Delta:
-1.55%
-$33,761.20
$2,373,290.93
Over/Under Est:
10.8%
$231,315.83
Amt Left:
16.72%
$339,938.72
Delta:
-7.41%
-$163,631.69
$2,598,455.80
Over/Under Est:
21.31%
$456,480.70
Amt Left:
27.79%
$565,103.59
Delta:
-9.49%
-$225,164.87
$4,627,491.20
Over/Under Est:
116.04%
$2,485,516.10
Amt Left:
127.58%
$2,594,138.99
Delta:
-78.09%
-$2,029,035.40
| Subcontractor | Percentage | Amount |
|---|---|---|
| CK NEWBERRY, LLC | 16.97% | $345,059.87 |
| TRP CONSTRUCTION GROUP, LLC | 10.05% | $204,351.90 |
| ENVIRONMENTAL SAFETY SERVICES, INC. | 0.71% | $14,436.80 |
| PROFESSIONAL TRAFFIC CONTROL LLC | 0.40% | $8,133.41 |
| CHEROKEE SERVICES | 0.37% | $7,523.40 |
| Total: | 28.50% | $579,505.38 |
Bid Items & Bid Tabulations
29
Total
0 of 29