County: BURNET Highway: RM 690 Date: 07/10/2018 (6 years ago) Engineer's Estimate: $2,430,395 Control Number: 3005-02-006
Project: STP 2013(635) District: AUSTIN Time: 160 WORKING DAYS Type: PROVIDE ADDITIONAL PAVED SURFACE

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,430,395.25
AARON CONCRETE CONTRACTORS, L.P.   $2,692,128.55 1
10.77% | $261,733.30
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.   $3,083,196.99 2
26.86% | $652,801.74
14.53% | $391,068.44
ANGEL BROTHERS HOLDINGS CORP.   $3,302,955.86 3
35.9% | $872,560.61
22.69% | $610,827.31
7.13% | $219,758.87
DENBOW COMPANY INC.   $3,357,788.27 4
38.16% | $927,393.02
24.73% | $665,659.72
1.66% | $54,832.41
ALLEN KELLER COMPANY   $3,887,732.08 5
59.96% | $1,457,336.83
44.41% | $1,195,603.53
15.78% | $529,943.81
RAY FARIS, INC.   $4,067,860.96 6
67.37% | $1,637,465.71
51.1% | $1,375,732.41
4.63% | $180,128.88

Bid Items

Items: 67, 0 filtered
BURNET RM 690  |  AUSTIN  |  3005-02-006  |  07/10/2018  |  $2,430,395  |  STP 2013(635)  |  PROVIDE ADDITIONAL PAVED SURF  |  160 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate AARON CONCRETE CONTRACTORS, L.P. CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. ANGEL BROTHERS HOLDINGS CORP. DENBOW COMPANY INC. ALLEN KELLER COMPANY RAY FARIS, INC.
100 6002 PREPARING ROW STA 244.300 $500.000 $250.000 $650.000 $520.000 $882.000 $1,000.000 $1,292.310
110 6001 EXCAVATION (ROADWAY) CY 20,512.000 $10.000 $15.000 $25.000 $25.000 $15.840 $30.000 $31.890
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 7,208.000 $12.000 $15.000 $18.000 $10.000 $11.840 $23.750 $25.420
150 6002 BLADING HR 50.000 $115.000 $160.000 $100.000 $100.000 $104.520 $132.000 $71.830
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 88,278.000 $1.750 $1.000 $2.750 $1.510 $3.690 $2.500 $4.310
164 6003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY 88,278.000 $0.200 $0.180 $0.140 $0.230 $0.180 $0.140 $0.140
164 6009 BROADCAST SEED (TEMP) (WARM) SY 44,139.000 $0.130 $0.140 $0.090 $0.230 $0.140 $0.100 $0.090
168 6001 VEGETATIVE WATERING MG 2,207.000 $22.000 $35.000 $25.000 $15.000 $27.500 $10.000 $19.840
169 6002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY 88,278.000 $1.000 $1.400 $0.850 $1.390 $1.530 $0.900 $0.850
216 6001 PROOF ROLLING HR 50.000 $120.000 $75.000 $60.000 $95.000 $165.050 $200.000 $55.250
247 6366 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) CY 6,036.000 $42.000 $53.000 $52.500 $62.000 $59.970 $80.000 $71.940
310 6027 PRIME COAT(MC-30 OR AE-P) GAL 4,343.000 $5.500 $5.000 $3.750 $4.500 $5.100 $5.500 $4.410
316 6005 ASPH (TIER II) GAL 41,260.000 $3.250 $4.500 $3.400 $3.500 $4.530 $4.000 $3.770
316 6240 AGGR(TY-PD GR-4 SAC-B) CY 897.000 $100.000 $110.000 $81.000 $130.000 $113.320 $115.000 $90.940
340 6246 D-GR HMA (SQ) TY-D PG64_22(LEVEL-UP) TON 578.000 $95.000 $165.000 $101.260 $115.000 $169.980 $125.000 $98.150
351 6004 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 2,000.000 $45.000 $63.000 $38.910 $43.500 $62.330 $74.000 $54.600
354 6020 PLANE ASPH CONC PAV(0" TO 1") SY 4,611.000 $4.000 $2.000 $3.500 $3.000 $2.550 $5.500 $4.420
432 6002 RIPRAP (CONC)(5 IN) CY 332.000 $435.000 $500.000 $450.000 $575.000 $430.620 $525.000 $500.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 177.000 $475.000 $520.000 $390.000 $523.000 $441.950 $445.000 $550.000
460 6001 CMP (GAL STL 12 IN) LF 106.000 $54.000 $115.000 $56.670 $69.750 $45.240 $64.000 $45.000
460 6003 CMP (GAL STL 24 IN) LF 19.900 $70.000 $190.000 $168.800 $104.000 $83.490 $95.000 $90.000
460 6004 CMP (GAL STL 30 IN) LF 12.600 $70.000 $280.000 $262.700 $146.000 $131.400 $133.000 $120.000
460 6009 CMP AR (GAL STL DES 2) LF 45.000 $59.000 $235.000 $82.350 $119.000 $94.160 $106.000 $80.000
460 6031 CMP (GAL STL 96 IN) LF 24.000 $150.000 $400.000 $375.000 $640.000 $312.760 $584.000 $400.000
466 6099 HEADWALL (CH - PW - 0) (DIA= 30 IN) EA 2.000 $7,500.000 $7,800.000 $9,000.000 $5,250.000 $7,932.420 $4,780.000 $9,000.000
467 6319 SET (TY II) (12 IN) (CMP) (6: 1) (P) EA 6.000 $1,000.000 $1,500.000 $840.000 $1,400.000 $785.870 $1,275.000 $750.000
467 6377 SET (TY II) (24 IN) (CMP) (4: 1) (C) EA 6.000 $1,400.000 $1,550.000 $930.000 $1,740.000 $1,295.040 $1,590.000 $900.000
467 6523 SET (TY II) (DES 2) (CMP) (4: 1) (C) EA 2.000 $700.000 $1,800.000 $1,200.000 $1,740.000 $1,497.580 $1,590.000 $900.000
480 6001 CLEAN EXIST CULVERTS EA 13.000 $2,500.000 $3,000.000 $1,000.000 $1,740.000 $1,200.850 $1,590.000 $1,200.000
496 6050 REMOV STR (DRIVEWAY CULVERT) EA 3.000 $228.000 $500.000 $1,750.000 $580.000 $863.870 $530.000 $750.000
500 6001 MOBILIZATION LS 1.000 $222,900.000 $140,000.000 $289,000.000 $325,000.000 $330,321.420 $281,000.000 $447,473.450
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 10.000 $3,500.000 $800.000 $700.000 $10,000.000 $11,468.020 $17,000.000 $18,149.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 1,872.000 $22.500 $30.000 $32.550 $40.000 $31.460 $29.000 $27.760
506 6011 ROCK FILTER DAMS (REMOVE) LF 1,872.000 $8.000 $6.400 $7.250 $20.000 $11.690 $6.250 $6.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 156.000 $13.000 $23.000 $19.450 $15.000 $24.530 $23.000 $21.650
506 6024 CONSTRUCTION EXITS (REMOVE) SY 156.000 $7.000 $6.400 $6.600 $12.000 $6.800 $6.370 $6.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 13,840.000 $2.000 $2.500 $2.150 $3.200 $2.660 $2.500 $2.350
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 13,840.000 $0.500 $0.400 $0.250 $0.900 $0.400 $0.370 $0.350
530 6004 DRIVEWAYS (CONC) SY 63.000 $75.000 $22.000 $100.000 $99.000 $133.160 $248.000 $121.050
530 6006 DRIVEWAYS (SURF TREAT) SY 4,629.000 $23.250 $30.000 $40.500 $31.000 $23.100 $51.000 $34.100
530 6009 TURNOUTS (SURF TREAT) SY 400.000 $14.000 $37.000 $32.500 $31.000 $33.080 $111.000 $36.100
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 2,525.000 $20.000 $22.000 $24.500 $27.000 $23.170 $20.190 $20.450
540 6017 MTL BM GD FEN (LONG SPAN SYSTEM) LF 250.000 $25.000 $22.000 $24.500 $27.000 $23.170 $21.250 $20.450
542 6001 REMOVE METAL BEAM GUARD FENCE LF 3,225.000 $1.250 $1.100 $2.500 $2.900 $1.130 $2.120 $1.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 14.000 $255.000 $160.000 $230.000 $260.000 $169.980 $212.490 $150.000
544 6006 GDRAIL END TRT(INST)(WOOD POST)(TY III) EA 22.000 $2,900.000 $2,800.000 $3,050.000 $3,400.000 $3,002.990 $2,762.430 $2,650.000
560 6011 MAILBOX INSTALL-S (TWW-POST) TY 4 EA 12.000 $200.000 $190.000 $185.000 $210.000 $201.090 $188.540 $212.000
560 6012 MAILBOX INSTALL-D (TWW-POST) TY 4 EA 3.000 $240.000 $290.000 $195.000 $220.000 $311.350 $291.910 $255.000
560 6013 MAILBOX INSTALL-M (TWW-POST) TY 4 EA 7.000 $483.000 $640.000 $498.000 $570.000 $685.590 $642.800 $491.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 3.000 $458.000 $480.000 $475.000 $550.000 $509.030 $477.260 $432.000
644 6068 RELOCATE SM RD SN SUP&AM TY 10BWG EA 30.000 $350.000 $470.000 $400.000 $460.000 $497.480 $466.430 $375.000
644 6076 REMOVE SM RD SN SUP&AM EA 35.000 $80.000 $80.000 $115.000 $125.000 $121.390 $79.690 $95.000
658 6011 INSTL DEL ASSM (D-SW)SZ 2(WC)GND(BI) EA 135.000 $12.000 $45.000 $46.000 $53.000 $48.090 $45.090 $47.000
658 6015 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 EA 49.000 $14.000 $12.000 $13.000 $15.000 $12.300 $11.530 $18.000
658 6046 INSTL OM ASSM (OM-2X)(WC)GND EA 21.000 $56.000 $35.000 $51.000 $59.000 $37.100 $34.790 $47.000
662 6004 WK ZN PAV MRK NON-REMOV (W)4"(SLD) LF 47,916.000 $0.250 $0.200 $0.190 $0.300 $0.220 $0.200 $0.190
662 6032 WK ZN PAV MRK NON-REMOV (Y)4"(BRK) LF 554.000 $0.200 $0.200 $0.190 $0.350 $0.220 $0.200 $0.190
662 6034 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) LF 44,879.000 $0.250 $0.200 $0.190 $0.300 $0.220 $0.200 $0.190
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 2,443.000 $0.950 $1.650 $1.000 $0.850 $0.570 $1.780 $1.380
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 149.000 $6.000 $7.700 $7.250 $6.900 $8.220 $7.700 $7.250
666 6224 PAVEMENT SEALER 4" LF 93,498.000 $0.120 $0.100 $0.100 $0.140 $0.110 $0.110 $0.100
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 47,916.000 $0.320 $0.300 $0.270 $0.400 $0.310 $0.290 $0.270
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 554.000 $0.380 $0.300 $0.280 $0.450 $0.320 $0.300 $0.280
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 44,879.000 $0.320 $0.300 $0.280 $0.420 $0.320 $0.300 $0.280
672 6009 REFL PAV MRKR TY II-A-A EA 588.000 $3.000 $3.700 $3.500 $5.800 $3.970 $3.720 $3.500
6185 6001 TMA (STATIONARY) EA 2.000 $10,000.000 $8,500.000 $20,000.000 $10,000.000 $17,338.010 $30,000.000 $28,000.000
6185 6003 TMA (MOBILE OPERATION) HR 30.000 $200.000 $65.000 $65.000 $60.000 $84.990 $155.400 $120.000
Totals: $2,430,395.25 $2,692,128.55 $3,083,196.99 $3,302,955.86 $3,357,788.27 $3,887,732.08 $4,067,860.96