BURNET RM 1174 (1349-03-013)

Items: 120

County: BURNET
Length: N/A
Highway: RM 1174
District: AUSTIN
Control Number: 1349-03-013
DBE Goal: N/A
Project: C 1349-3-13
Guaranty: N/A
Time: 247 WORKING DAYS
Engineer's Estimate: $5,695,841.35
Date: 08/08/2018 (7 years ago)
Contract Number: N/A
Type: PROVIDE ADDITIONAL PAVED SURFACE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$5,695,841.35
Over/Under Est: 8.49% $483,627.71
Over/Under Est: 11.06% $629,777.76
Amt Left: 2.37% $146,150.05
Over/Under Est: 11.61% $661,459.79
Amt Left: 2.88% $177,832.08
Delta: -0.50% -$31,682.03
Over/Under Est: 29.77% $1,695,710.75
Amt Left: 19.61% $1,212,083.04
Delta: -16.27% -$1,034,250.96
$7,667,346.13
Over/Under Est: 34.61% $1,971,504.78
Amt Left: 24.08% $1,487,877.07
Delta: -3.73% -$275,794.03
Over/Under Est: 44.25% $2,520,612.30
Amt Left: 32.96% $2,036,984.59
Delta: -7.16% -$549,107.52

Bid Items & Bid Tabulations

120 Total 0 of 120
BURNET  |  RM 1174  |  AUSTIN  |  1349-03-013  |  08/08/2018  |  $5,695,841.35  |  C 1349-3-13  |  PROVIDE ADDITIONAL PAVED SURF  |  247 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
CAPITAL EXCAVATION COMPANY
ANGEL BROTHERS HOLDINGS CORP.
JORDAN FOSTER CONSTRUCTION, LLC
ALLEN KELLER COMPANY
AARON CONCRETE CONTRACTORS, L.P.
PREPARING ROW
STA 320.000 $500.000 $400.000 $1,000.000 $350.000 $935.000 $500.000 $300.000
REMOVING CONC (RIPRAP)
SY 720.000 $15.500 $75.000 $9.860 $9.000 $16.000 $23.000 $35.000
REMOVING CONC (DRIVEWAYS)
SY 327.000 $20.000 $15.000 $39.690 $10.000 $12.000 $30.500 $34.000
REMOVING STAB BASE AND ASPH PAV (2"-6")
SY 19,240.000 $2.600 $3.750 $4.160 $6.000 $4.000 $2.150 $4.500
EXCAVATION (ROADWAY)
CY 19,241.000 $12.000 $12.750 $13.000 $25.000 $22.000 $22.750 $40.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 11,552.000 $11.000 $7.500 $9.000 $5.500 $22.000 $14.500 $7.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 565.000 $25.000 $20.000 $47.620 $5.500 $10.000 $68.000 $80.000
FURNISHING AND PLACING TOPSOIL (4")
SY 59,511.000 $1.500 $1.900 $1.750 $0.900 $2.750 $3.500 $5.000
BROADCAST SEED (TEMP) (WARM)
SY 14,878.000 $0.200 $0.100 $0.100 $0.190 $0.170 $0.170 $0.300
BROADCAST SEED (TEMP) (COOL)
SY 14,878.000 $0.200 $0.100 $0.100 $0.190 $0.170 $0.170 $0.300
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 59,511.000 $0.300 $0.350 $0.100 $0.290 $0.270 $0.250 $0.400
VEGETATIVE WATERING
MG 1,252.000 $27.500 $20.000 $35.220 $15.000 $22.000 $14.000 $43.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 11,902.000 $1.250 $1.350 $1.380 $2.650 $1.800 $1.500 $1.400
PROOF ROLLING
HR 8.000 $120.000 $100.000 $88.470 $100.000 $100.000 $150.000 $100.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 11,724.000 $42.000 $60.300 $44.000 $42.000 $53.000 $64.000 $75.000
PRIME COAT(MC-30 OR AE-P)
GAL 10,552.000 $3.400 $4.500 $3.250 $3.000 $3.750 $5.000 $3.500
ASPH (TIER II)
GAL 43,790.000 $3.500 $3.200 $3.600 $3.500 $3.100 $4.000 $3.600
AGGR(TY-PD GR-4 SAC-B)
CY 960.000 $100.000 $77.000 $76.000 $130.590 $110.000 $129.000 $78.000
D-GR HMA(SQ) TY-B PG64-22
TON 852.000 $90.000 $79.750 $86.000 $76.000 $72.000 $108.000 $88.000
D-GR HMA TY-C PG64-22
TON 6,017.000 $75.000 $73.800 $82.000 $73.000 $76.000 $94.000 $84.000
D-GR HMA TY-D PG70-22
TON 6,559.000 $80.000 $76.600 $80.000 $73.000 $72.000 $100.000 $82.000
D-GR HMA TY-D PG 70-22 (LEVEL-UP)
TON 666.000 $90.000 $78.000 $93.000 $120.000 $125.000 $130.000 $95.000
CEM STABIL BKFL
CY 212.000 $145.000 $150.000 $168.030 $165.000 $115.000 $150.000 $130.000
CUT & RESTORING PAV
SY 84.000 $110.000 $100.000 $114.510 $110.000 $90.000 $100.000 $280.000
FLOWABLE BACKFILL
CY 166.000 $160.000 $160.000 $149.800 $175.000 $135.000 $160.000 $130.000
TRENCH EXCAVATION PROTECTION
LF 100.000 $10.000 $10.000 $14.390 $45.000 $3.000 $10.000 $65.000
TEMPORARY SPL SHORING
SF 3,926.000 $18.000 $40.000 $21.940 $45.000 $45.000 $40.000 $41.000
CL C CONC (HEADWALL)
CY 15.100 $1,450.000 $1,500.000 $792.170 $1,650.000 $1,350.000 $1,515.000 $2,900.000
RETAINING WALL (MSE)
SF 2,115.000 $52.500 $110.000 $58.270 $45.000 $70.000 $100.000 $125.000
RIPRAP (CONC)(5 IN)
CY 934.000 $380.000 $425.000 $425.420 $465.000 $500.000 $429.000 $520.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 24.000 $425.000 $650.000 $620.850 $1,650.000 $550.000 $850.000 $620.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 23.000 $155.000 $151.400 $144.560 $165.000 $235.000 $340.000 $220.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 363.000 $126.000 $183.650 $151.380 $140.000 $165.000 $155.000 $220.000
RIPRAP (MOW STRIP)(4 IN)
CY 310.000 $400.000 $450.000 $557.250 $500.000 $525.000 $455.000 $540.000
RIPRAP (MOW STRIP)(5 IN)
CY 10.800 $500.000 $500.000 $557.280 $550.000 $675.000 $500.000 $540.000
RETROFIT RAIL (TY T223)
LF 240.000 $125.000 $180.000 $155.350 $145.000 $210.000 $415.000 $500.000
CONC BOX CULV (5 FT X 2 FT)(EXTEND)
LF 32.000 $525.000 $360.000 $907.110 $395.000 $550.000 $360.000 $910.000
CONC BOX CULV (5 FT X 4 FT)(EXTEND)
LF 32.000 $650.000 $435.000 $879.920 $480.000 $800.000 $440.000 $1,140.000
CONC BOX CULV (6 FT X 3 FT)(EXTEND)
LF 84.000 $725.000 $450.000 $903.890 $495.000 $625.000 $455.000 $1,200.000
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
LF 12.000 $800.000 $600.000 $941.960 $660.000 $1,300.000 $606.000 $1,700.000
CONC BOX CULV (6 FT X 6 FT)(EXTEND)
LF 8.000 $900.000 $800.000 $1,990.070 $880.000 $1,900.000 $810.000 $2,100.000
RC PIPE (CL III)(18 IN)
LF 2,046.000 $52.500 $50.000 $60.000 $55.000 $65.000 $50.000 $92.000
RC PIPE (CL III)(24 IN)
LF 718.000 $75.000 $78.000 $112.470 $85.000 $90.000 $79.000 $110.000
RC PIPE (CL III)(30 IN)
LF 244.000 $95.000 $100.000 $151.770 $110.000 $135.000 $100.000 $130.000
RC PIPE (CL III)(36 IN)
LF 224.000 $150.000 $130.000 $228.730 $145.000 $180.000 $130.000 $145.000
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 16.000 $3,000.000 $3,000.000 $2,838.700 $3,300.000 $4,200.000 $3,030.000 $9,000.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 4.000 $6,000.000 $4,000.000 $2,838.700 $4,500.000 $6,400.000 $4,040.000 $11,000.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 6.000 $6,250.000 $6,000.000 $3,545.180 $6,600.000 $7,200.000 $6,060.000 $26,000.000
WINGWALL (PW - 1) (HW=11 FT)
EA 2.000 $25,000.000 $32,000.000 $25,272.260 $35,000.000 $37,000.000 $32,300.000 $75,000.000
WINGWALL (PW - 1) (HW=3 FT)
EA 2.000 $4,000.000 $3,500.000 $4,095.210 $3,850.000 $8,000.000 $3,540.000 $9,800.000
WINGWALL (PW - 1) (HW=4 FT)
EA 3.000 $6,500.000 $5,200.000 $5,702.460 $5,700.000 $9,200.000 $5,260.000 $20,000.000
WINGWALL (PW - 1) (HW=5 FT)
EA 3.000 $8,000.000 $7,000.000 $6,739.270 $7,700.000 $10,500.000 $7,080.000 $24,000.000
WINGWALL (PW - 1) (HW=6 FT)
EA 1.000 $12,000.000 $10,000.000 $6,220.840 $11,000.000 $17,000.000 $10,100.000 $35,000.000
WINGWALL (PW - 1) (HW=8 FT)
EA 1.000 $17,000.000 $16,000.000 $13,219.350 $17,500.000 $23,000.000 $16,180.000 $41,000.000
WINGWALL (PW - 2) (HW=5 FT)
EA 1.000 $10,000.000 $6,500.000 $6,742.270 $7,000.000 $13,000.000 $6,550.000 $17,000.000
WINGWALL (PW - 2) (HW=6 FT)
EA 1.000 $12,000.000 $8,000.000 $6,220.840 $8,800.000 $17,500.000 $8,100.000 $21,000.000
WINGWALL (SW - 0) (HW=5 FT)
EA 1.000 $9,000.000 $5,500.000 $6,742.270 $6,000.000 $20,000.000 $5,560.000 $13,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 106.000 $900.000 $750.000 $920.000 $825.000 $1,100.000 $750.000 $1,300.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 24.000 $1,100.000 $850.000 $1,558.180 $950.000 $1,450.000 $850.000 $1,400.000
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 4.000 $1,450.000 $2,000.000 $1,400.690 $2,200.000 $2,300.000 $2,020.000 $1,700.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 4.000 $1,800.000 $3,000.000 $1,851.660 $3,300.000 $2,350.000 $3,030.000 $1,800.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 4.000 $2,800.000 $3,500.000 $1,943.480 $3,850.000 $3,700.000 $3,540.000 $2,200.000
REMOV STR (SET)
EA 132.000 $180.000 $450.000 $326.610 $500.000 $150.000 $455.000 $530.000
REMOV STR (WINGWALL)
EA 34.000 $1,000.000 $850.000 $160.200 $1,000.000 $1,200.000 $860.000 $1,100.000
REMOV STR (HEADWALL)
EA 6.000 $1,125.000 $850.000 $907.830 $1,000.000 $1,500.000 $860.000 $1,100.000
REMOV STR (PIPE)
LF 212.000 $20.000 $20.000 $10.890 $25.000 $9.000 $20.000 $50.000
REMOV STR (DRIVEWAY CULVERT)
EA 66.000 $425.000 $750.000 $1,416.000 $825.000 $400.000 $750.000 $550.000
MOBILIZATION
LS 1.000 $517,800.000 $485,000.000 $630,000.000 $625,000.000 $720,000.000 $500,000.000 $400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $3,000.000 $4,000.000 $2,500.000 $2,000.000 $20,000.000 $16,360.000 $1,200.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 765.000 $25.000 $26.700 $27.380 $30.000 $28.000 $27.000 $31.000
ROCK FILTER DAMS (REMOVE)
LF 765.000 $8.000 $6.000 $6.150 $6.000 $7.000 $6.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 9,400.000 $2.000 $2.450 $2.510 $2.750 $2.500 $2.500 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 9,400.000 $0.350 $0.350 $0.360 $0.400 $0.400 $0.350 $1.100
CONSTRUCTING DETOURS
SY 2,590.000 $45.000 $58.000 $35.000 $38.000 $20.000 $30.500 $11.000
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 400.000 $30.000 $88.000 $14.150 $75.000 $20.000 $95.000 $78.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 800.000 $7.500 $25.000 $5.750 $8.000 $15.000 $32.750 $20.000
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 400.000 $11.500 $45.000 $14.150 $20.000 $20.000 $32.750 $25.000
INTERSECTIONS (CONC)
SY 168.000 $100.000 $90.000 $126.350 $100.000 $100.000 $245.000 $84.000
INTERSECTIONS (ACP)
SY 1,939.000 $30.000 $18.000 $40.460 $60.000 $50.000 $110.000 $26.000
DRIVEWAYS (CONC)
SY 93.000 $100.000 $90.000 $141.390 $100.000 $115.000 $255.000 $80.000
DRIVEWAYS (ACP)
SY 2,219.000 $30.000 $17.700 $34.960 $41.500 $40.000 $117.000 $32.000
DRIVEWAYS (SURF TREAT)
SY 2,106.000 $30.000 $17.850 $3.630 $31.000 $30.000 $45.000 $26.000
MTL W-BEAM GD FEN (TIM POST)
LF 5,588.000 $19.000 $21.450 $22.000 $23.000 $20.000 $20.000 $28.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,500.000 $1,460.000 $1,497.440 $1,600.000 $1,600.000 $1,720.000 $2,000.000
SHORT RADIUS
LF 54.000 $32.000 $30.000 $31.080 $33.000 $24.000 $26.000 $34.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 2.000 $700.000 $620.000 $635.900 $680.000 $550.000 $1,520.000 $650.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 150.000 $22.500 $20.450 $20.970 $25.000 $23.000 $23.250 $26.000
REMOVE METAL BEAM GUARD FENCE
LF 648.000 $1.500 $1.250 $1.280 $1.500 $2.000 $1.250 $3.300
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $150.000 $125.000 $128.210 $150.000 $165.000 $200.000 $150.000
GUARDRAIL END TREATMENT (INSTALL)
EA 19.000 $2,300.000 $2,735.000 $2,805.130 $3,000.000 $2,600.000 $2,425.000 $3,200.000
GUARDRAIL END TREATMENT (REMOVE)
EA 5.000 $220.000 $125.000 $128.210 $150.000 $225.000 $200.000 $270.000
CRASH CUSH ATTEN (INSTL)
EA 2.000 $9,600.000 $6,750.000 $6,923.080 $7,500.000 $7,800.000 $10,200.000 $9,600.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 4.000 $1,700.000 $1,000.000 $1,025.640 $1,100.000 $1,100.000 $1,550.000 $2,200.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,000.000 $750.000 $769.230 $850.000 $800.000 $770.000 $980.000
PIPE UNDERDRAINS (TY 6) (6")
LF 415.000 $27.500 $25.000 $35.330 $20.000 $32.000 $45.000 $85.000
MAILBOX INSTALL-S (TWG-POST) TY 1
EA 22.000 $165.000 $150.250 $184.850 $200.000 $200.000 $185.000 $212.000
MAILBOX INSTALL-D (TWG-POST) TY 1
EA 5.000 $180.000 $188.250 $220.200 $225.000 $245.000 $220.000 $245.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 3.000 $320.000 $325.000 $310.100 $375.000 $350.000 $310.000 $520.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 51.000 $425.000 $448.350 $423.230 $500.000 $475.000 $420.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 9.000 $700.000 $566.500 $527.270 $650.000 $600.000 $525.000 $680.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $700.000 $554.600 $555.560 $600.000 $600.000 $550.000 $540.000
IN SM RD SN SUP&AM TYFRP(1)UA(P)
EA 2.000 $610.000 $513.800 $500.000 $565.000 $575.000 $500.000 $15.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 2.000 $400.000 $444.000 $378.790 $500.000 $425.000 $375.000 $440.000
REMOVE SM RD SN SUP&AM
EA 57.000 $75.000 $75.000 $90.910 $85.000 $98.000 $90.000 $110.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 3.000 $20.000 $12.850 $15.150 $15.000 $16.000 $15.000 $15.000
INSTL OM ASSM (OM-2Z)(FLX)SRF
EA 35.000 $75.000 $74.500 $62.630 $80.000 $70.000 $63.000 $95.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 76.000 $30.000 $13.250 $17.170 $15.000 $19.000 $17.000 $20.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 508.000 $1.050 $1.000 $1.010 $1.000 $2.000 $1.750 $1.600
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 77.000 $7.500 $10.000 $10.100 $13.500 $7.000 $12.400 $14.000
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
EA 7.000 $45.000 $55.000 $55.560 $35.000 $30.000 $30.300 $33.000
REFL PAV MRK TY II (Y) 4" (BRK)
LF 1,830.000 $0.100 $0.250 $0.250 $0.120 $0.180 $0.110 $0.100
REFL PAV MRK TY II (Y) 4" (SLD)
LF 51,717.000 $0.150 $0.250 $0.250 $0.120 $0.180 $0.110 $0.100
REF PROF PAV MRK TY I(W)4"(SLD)(090MIL)
LF 63,137.000 $0.600 $0.750 $0.760 $0.660 $0.800 $0.610 $0.700
REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL)
LF 51,717.000 $0.600 $0.750 $0.760 $0.670 $0.820 $0.620 $0.700
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 1,830.000 $0.300 $0.500 $0.510 $1.200 $0.650 $1.110 $1.200
REFL PAV MRKR TY II-A-A
EA 740.000 $3.500 $4.000 $4.040 $4.000 $5.000 $3.690 $4.000
ELIM EXT PAV MRK & MRKS (4")
LF 53,273.000 $0.400 $0.470 $0.470 $0.120 $0.620 $0.110 $0.150
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $7,000.000 $12,000.000 $9,042.830 $8,500.000 $7,500.000 $13,400.000 $10,000.000
TMA (STATIONARY)
DAY 50.000 $250.000 $250.000 $300.280 $225.000 $225.000 $215.000 $230.000
TMA (MOBILE OPERATION)
HR 100.000 $50.000 $52.000 $62.460 $100.000 $60.000 $150.000 $58.000
Totals: $5,695,841.350 $6,179,469.060 $6,325,619.121 $6,357,301.140 $7,391,552.100 $7,667,346.130 $8,216,453.650