BURLESON CR (0917-30-054)

Items: 50

County: BURLESON
Length: N/A
Highway: CR
District: BRYAN
Control Number: 0917-30-054
DBE Goal: N/A
Project: BR 1702(413)
Guaranty: N/A
Time: 84 WORKING DAYS
Engineer's Estimate: $835,430.25
Date: 03/07/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
JAMES KREAMER
JOHN MCCALL
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$835,430.25
$946,424.73
Over/Under Est: 13.29% $110,994.48
Over/Under Est: 22.92% $191,455.11
Amt Left: 8.5% $80,460.63
Over/Under Est: 24.19% $202,073.75
Amt Left: 9.62% $91,079.27
Delta: -1.03% -$10,618.64
Over/Under Est: 32.44% $271,005.75
Amt Left: 16.91% $160,011.27
Delta: -6.64% -$68,932.00

Bid Items & Bid Tabulations

50 Total 0 of 50
BURLESON  |  CR  |  BRYAN  |  0917-30-054  |  03/07/2023  |  $835,430.25  |  BR 1702(413)  |  BRIDGE REPL  |  84 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
FUQUA CONSTRUCTION CO., INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
TEXAS MATERIALS GROUP, INC.
PREPARING ROW
STA 4.000 $2,000.000 $2,480.000 $7,116.020 $5,000.000 $17,800.000
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 45.000 $370.000 $220.000 $840.990 $500.000 $200.000
PREPARING ROW(TREE)(24" TO 36" DIA.)
EA 4.000 $1,500.000 $2,250.000 $1,628.630 $2,500.000 $2,000.000
REMOVING STAB BASE AND ASPH PAV (2"-6")
SY 341.000 $15.000 $6.300 $7.990 $20.000 $18.000
EXCAVATION (ROADWAY)
CY 466.000 $15.000 $8.000 $12.000 $20.000 $43.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 399.000 $20.000 $4.000 $15.000 $30.000 $51.000
FURNISHING AND PLACING TOPSOIL (4")
SY 2,929.000 $2.500 $1.800 $4.000 $4.000 $4.000
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 2,929.000 $2.000 $0.950 $4.000 $2.000 $0.850
CELL FBR MLCH SEED(TEMP)(WARM)
SY 1,465.000 $0.500 $0.850 $4.000 $2.000 $0.750
CELL FBR MLCH SEED(TEMP)(COOL)
SY 1,465.000 $0.500 $0.850 $4.000 $2.000 $0.750
VEGETATIVE WATERING
MG 15.000 $35.000 $39.000 $50.000 $1.000 $50.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
SY 896.000 $19.000 $20.150 $20.000 $45.000 $39.000
ASPH (AC-10-2TR)
GAL 267.000 $12.000 $11.250 $12.000 $30.000 $18.000
ASPH (RC-250)
GAL 171.000 $14.000 $15.500 $12.000 $20.000 $28.000
AGGR(TY-PB GR-4 SAC-B)
CY 5.000 $200.000 $683.000 $600.000 $2,000.000 $1,500.000
AGGR(TY-PB GR-5 SAC-B)
CY 5.000 $250.000 $683.000 $600.000 $2,000.000 $1,500.000
CEM STABIL BKFL
CY 55.000 $140.000 $160.000 $79.450 $250.000 $275.000
TEMPORARY SPL SHORING
SF 524.000 $20.000 $108.000 $19.340 $40.000 $30.000
DRILL SHAFT (30 IN)
LF 282.000 $240.000 $392.000 $220.000 $280.000 $320.000
CL C CONC (ABUT)
CY 27.200 $1,000.000 $1,446.000 $1,123.140 $1,500.000 $2,000.000
REINF CONC SLAB (BOX BEAM)
SF 1,701.000 $25.000 $41.380 $25.000 $30.000 $46.000
SHEAR KEY
CY 8.600 $370.000 $435.000 $600.000 $800.000 $700.000
PRESTR CONC BOX BEAM (4B20)
LF 258.700 $280.000 $258.300 $250.420 $340.000 $287.000
PRESTR CONC BOX BEAM (5B20)
LF 129.350 $290.000 $290.700 $250.420 $340.000 $287.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 295.000 $200.000 $177.000 $210.000 $150.000 $173.000
RAIL (TY T223)
LF 162.000 $130.000 $185.000 $120.000 $120.000 $200.000
ARMOR JOINT (SEALED)
LF 52.000 $145.000 $10.000 $112.580 $120.000 $75.000
CONC BOX CULV (10 FT X 6 FT)
LF 72.000 $790.000 $1,682.000 $1,800.000 $2,360.000 $1,500.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $25,000.000 $13,200.000 $40,000.000 $25,000.000 $15,000.000
MOBILIZATION
LS 1.000 $60,000.000 $109,900.000 $141,000.000 $95,000.000 $110,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $7,500.000 $1,260.000 $8,838.770 $2,500.000 $2,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 131.000 $36.000 $42.200 $32.370 $20.000 $38.000
ROCK FILTER DAMS (REMOVE)
LF 131.000 $10.000 $16.600 $10.370 $10.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 78.000 $20.000 $38.900 $24.460 $1.000 $30.000
CONSTRUCTION EXITS (REMOVE)
SY 78.000 $15.000 $16.600 $7.230 $1.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 891.000 $3.500 $4.400 $6.000 $1.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 891.000 $1.250 $1.600 $3.000 $1.000 $1.500
CONSTRUCTING DETOURS
SY 1,014.000 $95.000 $66.850 $100.000 $50.000 $100.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 540.000 $82.000 $18.000 $45.000 $75.000 $50.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 80.000 $82.000 $18.000 $60.000 $75.000 $50.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 540.000 $15.000 $16.000 $8.000 $15.000 $24.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 80.000 $15.000 $16.000 $8.000 $15.000 $24.000
MTL W-BEAM GD FEN (TIM POST)
LF 100.000 $32.000 $32.350 $29.130 $30.000 $28.000
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,500.000 $1,150.000 $1,036.380 $1,500.000 $1,200.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,000.000 $3,832.000 $3,448.680 $3,200.000 $3,300.000
WIRE FENCE (TY A)
LF 400.000 $40.000 $22.250 $15.430 $15.000 $20.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $700.000 $1,025.000 $629.470 $1,000.000 $860.000
REMOVE SM RD SN SUP&AM
EA 5.000 $100.000 $150.000 $112.810 $500.000 $100.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 4.000 $30.000 $22.000 $19.690 $30.000 $25.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 8.000 $35.000 $30.000 $26.760 $30.000 $25.000
Totals: $835,430.250 $946,424.735 $1,026,885.379 $1,037,504.000 $1,106,436.000