Job Info for 0923-00-060

County: BROWN Highway: VA Date: 02/06/2019 (5 years ago) Engineer's Estimate: $888,556 Control Number: 0923-00-060
Project: C 923-00-60 District: BROWNWOOD Time: 50 WORKING DAYS Type: THERMOPLASTIC STRIPING

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $888,556.12
L&L COMPANY   $978,221.46 1
10.09% | $89,665.34
MIJELUM   $1,028,342.17 2
15.73% | $139,786.05
5.12% | $50,120.71
STRIPING TECHNOLOGY, L.P.   $1,077,025.64 3
21.21% | $188,469.52
10.1% | $98,804.18
4.73% | $48,683.47
D. I. J. CONSTRUCTION, INC.   $1,129,217.14 4
27.08% | $240,661.02
15.44% | $150,995.68
4.85% | $52,191.50
INTERSTATE BARRICADES & MARKINGS, INC.   $1,187,923.72 5
33.69% | $299,367.60
21.44% | $209,702.26
5.20% | $58,706.58
TRP CONSTRUCTION GROUP, LLC   $1,342,263.29 6
51.06% | $453,707.17
37.21% | $364,041.83
12.99% | $154,339.57
STRIPE-A-ZONE, INC.   $1,387,959.38 7
56.2% | $499,403.26
41.89% | $409,737.92
3.40% | $45,696.09
TOTAL HIGHWAY MAINTENANCE, LLC   $1,459,733.11 8
64.28% | $571,176.99
49.22% | $481,511.65
5.17% | $71,773.73

Bid Items

Items: 18, 0 filtered
BROWN VA  |  BROWNWOOD  |  0923-00-060  |  02/06/2019  |  $888,556  |  C 923-00-60  |  THERMOPLASTIC STRIPING  |  50 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate L&L COMPANY MIJELUM STRIPING TECHNOLOGY, L.P. D. I. J. CONSTRUCTION, INC. INTERSTATE BARRICADES & MARKINGS, INC. TRP CONSTRUCTION GROUP, LLC STRIPE-A-ZONE, INC. TOTAL HIGHWAY MAINTENANCE, LLC
500 6001 MOBILIZATION LS 1.000 $80,096.010 $1.000 $1.000 $35,000.000 $85,000.000 $50,000.000 $80,000.000 $63,400.000 $65,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 $2,500.000 $1.000 $1,000.000 $6,500.000 $1,200.000 $1.000 $4,300.000 $11,200.000 $4,500.000
666 6009 REFL PAV MRK TY I (W)4"(LNDP)(100MIL) LF 1,090.000 $2.000 $1.000 $1.200 $1.000 $1.000 $1.000 $1.500 $1.500 $1.600
666 6033 REFL PAV MRK TY I (W)8"(LNDP)(100MIL) LF 880.000 $1.000 $1.000 $1.100 $1.000 $1.500 $1.000 $1.400 $2.000 $1.900
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 25,490.000 $0.600 $0.600 $0.650 $0.680 $0.680 $0.680 $0.820 $0.855 $0.880
666 6042 REFL PAV MRK TY I (W)12"(SLD)(100MIL) LF 670.000 $3.000 $4.000 $4.000 $3.000 $5.250 $3.000 $3.750 $4.000 $4.000
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 109,580.000 $0.190 $0.250 $0.240 $0.280 $0.260 $0.270 $0.390 $0.320 $0.440
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 1,875,090.000 $0.190 $0.240 $0.240 $0.245 $0.260 $0.270 $0.305 $0.320 $0.340
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 160,610.000 $0.190 $0.250 $0.240 $0.280 $0.260 $0.270 $0.370 $0.320 $0.440
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 1,333,389.000 $0.190 $0.240 $0.230 $0.255 $0.260 $0.280 $0.305 $0.320 $0.340
668 6076 PREFAB PAV MRK TY C (W) (24") (SLD) LF 5,721.000 $9.000 $11.000 $20.000 $12.750 $11.500 $14.000 $14.000 $14.350 $11.450
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 64.000 $200.000 $250.000 $200.000 $185.000 $200.000 $210.000 $240.000 $245.000 $225.000
668 6078 PREFAB PAV MRK TY C (W) (DBL ARROW) EA 1.000 $250.000 $400.000 $350.000 $350.000 $290.000 $365.000 $1,000.000 $400.000 $325.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 63.000 $250.000 $250.000 $250.000 $235.000 $250.000 $300.000 $320.000 $365.000 $310.000
668 6089 PREFAB PAV MRK TY C (W) (RR XING) EA 12.000 $350.000 $400.000 $550.000 $550.000 $600.000 $650.000 $800.000 $900.000 $856.000
668 6092 PREFAB PAV MRK TY C (W) (36")(YLD TRI) EA 187.000 $30.000 $30.000 $50.000 $35.750 $33.000 $32.000 $60.000 $45.000 $91.000
668 6101 PREFAB PAV MRK TY C (Y) (4") (SLD) LF 1,300.000 $3.500 $4.000 $10.000 $2.250 $3.000 $11.500 $3.000 $3.100 $2.300
6185 6005 TMA (MOBILE OPERATION) DAY 100.000 $250.000 $100.000 $100.000 $100.000 $10.000 $225.000 $10.000 $55.000 $129.000
Totals: $888,556.12 $978,221.46 $1,028,342.17 $1,077,025.65 $1,129,217.14 $1,187,923.72 $1,342,263.30 $1,387,959.38 $1,459,733.11