Job Info for 0255-04-099

County: BROOKS Highway: US 281 Date: 07/08/2020 (4 years ago) Engineer's Estimate: $8,073,768 Control Number: 0255-04-099
Project: NH 2B20(153) District: PHARR Time: 240 WORKING DAYS Type: INSTALL CABLE BARRIER

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $8,073,768.10
MASSANA, INC.   $6,056,599.75 1
-24.98% | -$2,017,168.35
SCR CIVIL CONSTRUCTION, LLC   $7,143,493.47 2
-11.52% | -$930,274.63
17.95% | $1,086,893.72
GRATIOT CONSTRUCTION, LTD.   $7,499,010.20 3
-7.12% | -$574,757.90
23.82% | $1,442,410.45
4.98% | $355,516.73
FNH CONSTRUCTION, LLC   $8,054,690.75 4
-0.24% | -$19,077.35
32.99% | $1,998,091.00
7.41% | $555,680.55
ALTUS CONSTRUCTION LLC   $8,751,930.10 5
8.4% | $678,162.00
44.5% | $2,695,330.35
8.66% | $697,239.35

Bid Items

Items: 12, 0 filtered
BROOKS US 281  |  PHARR  |  0255-04-099  |  07/08/2020  |  $8,073,768  |  NH 2B20(153)  |  INSTL CABLE BARRIER  |  240 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate MASSANA, INC. SCR CIVIL CONSTRUCTION, LLC GRATIOT CONSTRUCTION, LTD. FNH CONSTRUCTION, LLC ALTUS CONSTRUCTION LLC
100 6009 PREPARING ROW (TREE) (6" TO 24" DIA) EA 40.000 $1,000.000 $550.000 $1,470.000 $1,900.000 $5,000.000 $3,423.600
100 6028 PREP ROW (TREE PRUNING) EA 40.000 $2,000.000 $300.000 $570.000 $700.000 $2,500.000 $3,423.600
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 300.000 $1.150 $6.000 $15.000 $70.000 $20.000 $13.690
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 7,728.000 $465.000 $330.000 $536.000 $550.000 $550.000 $578.530
500 6001 MOBILIZATION LS 1.000 $672,450.000 $638,518.500 $414,000.000 $850,000.000 $800,000.000 $869,595.470
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 16.000 $5,000.000 $25,000.000 $5,500.000 $3,700.000 $8,500.000 $13,694.420
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 31,770.000 $5.000 $5.000 $4.250 $8.000 $9.000 $8.220
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 31,770.000 $1.150 $1.000 $1.000 $1.000 $5.000 $2.740
543 6002 CABLE BARRIER SYSTEM (TL-4) LF 202,589.500 $14.000 $7.500 $8.860 $7.600 $8.500 $10.570
543 6020 CABLE BARRIER TERMINAL SECTION (TL-4) EA 118.000 $4,336.200 $5,500.000 $3,175.000 $2,400.000 $2,500.000 $2,648.180
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 1.000 $12,135.000 $25,000.000 $18,000.000 $21,600.000 $16,500.000 $13,694.420
6185 6002 TMA (STATIONARY) DAY 240.000 $216.700 $200.000 $245.000 $350.000 $350.000 $410.830
Totals: $8,073,768.10 $6,056,599.75 $7,143,493.47 $7,499,010.20 $8,054,690.75 $8,751,930.11