Job Info for 6424-04-001

County: BRAZOS Highway: SH0006 Date: 11/15/2022 (2 years ago) Engineer's Estimate: $147,875 Control Number: 6424-04-001
Project: RMC - 642404001 District: BRYAN Time: 365 CALENDAR DAYS Type: TREE REMOVAL
HCS
Pay Estimates: 1 | 2 | 3 | 4
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $147,875.00
GV LANDSCAPE AND CONSTRUCTION LLC   $269,400.00 1
82.18% | $121,525.00
CROSS PLUS CONSTRUCTION, LLC   $313,925.00 2
112.29% | $166,050.00
16.53% | $44,525.00

Bid Items

Items: 12, 0 filtered
BRAZOS SH0006  |  BRYAN  |  6424-04-001  |  11/15/2022  |  $147,875  |  RMC - 642404001  |  TREE RMVL  |  365 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate GV LANDSCAPE AND CONSTRUCTION LLC CROSS PLUS CONSTRUCTION, LLC
500 6033 MOBILIZATION (CALLOUT) EA 10.000 $500.000 $2,900.000 $4,000.000
752 6005 TREE REMOVAL (4" - 12" DIA) EA 400.000 $60.000 $140.000 $100.000
752 6006 TREE REMOVAL (12" - 18" DIA) EA 300.000 $80.000 $150.000 $125.000
752 6007 TREE REMOVAL (18" - 24" DIA) EA 200.000 $120.000 $200.000 $200.000
752 6008 TREE REMOVAL (24" - 30" DIA) EA 100.000 $175.000 $240.000 $400.000
752 6009 TREE REMOVAL (30" - 36" DIA) EA 75.000 $225.000 $290.000 $500.000
752 6010 TREE REMOVAL (36" - 42" DIA) EA 25.000 $350.000 $300.000 $600.000
752 6011 TREE REMOVAL (42" - 48" DIA) EA 10.000 $475.000 $390.000 $900.000
752 6012 TREE REMOVAL (48" - 60" DIA) EA 10.000 $550.000 $700.000 $900.000
752 6013 TREE REMOVAL (60" - 72" DIA) EA 10.000 $700.000 $1,900.000 $900.000
752 6014 STUMP REMOVAL EA 25.000 $60.000 $200.000 $100.000
6185 6002 TMA (STATIONARY) DAY 75.000 $120.000 $150.000 $459.000
Totals: $147,875.00 $269,400.00 $313,925.00