BRAZOS FM 159 (0540-05-048)

Items: 93

County: BRAZOS
Length: N/A
Highway: FM 159
District: BRYAN
Control Number: 0540-05-048
DBE Goal: N/A
Project: C 540-5-48
Guaranty: N/A
Time: 105 WORKING DAYS
Engineer's Estimate: $4,143,104.95
Date: 08/07/2018 (7 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROAD
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (8)
E
Engineer's Estimate
$4,143,104.95
$2,816,987.76
Over/Under Est: -32.01% -$1,326,117.19
Over/Under Est: -30.26% -$1,253,868.17
Amt Left: 2.56% $72,249.02
Over/Under Est: -26.19% -$1,085,079.70
Amt Left: 8.56% $241,037.49
Delta: -5.84% -$168,788.47
Over/Under Est: -25.49% -$1,056,099.76
Amt Left: 9.59% $270,017.43
Delta: -0.95% -$28,979.94
Over/Under Est: -17.31% -$717,134.81
Amt Left: 21.62% $608,982.38
Delta: -10.98% -$338,964.95
$3,589,086.50
Over/Under Est: -13.37% -$554,018.45
Amt Left: 27.41% $772,098.74
Delta: -4.76% -$163,116.36
Over/Under Est: 5.63% $233,444.55
Amt Left: 55.36% $1,559,561.74
Delta: -21.94% -$787,463.00
Over/Under Est: 27.2% $1,127,006.17
Amt Left: 87.08% $2,453,123.36
Delta: -20.42% -$893,561.62

Bid Items & Bid Tabulations

93 Total 0 of 93
BRAZOS  |  FM 159  |  BRYAN  |  0540-05-048  |  08/07/2018  |  $4,143,104.95  |  C 540-5-48  |  REHAB EXIST ROAD  |  105 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GLENN FUQUA, INC.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
ANGEL BROTHERS HOLDINGS CORP.
BIG CREEK CONSTRUCTION, LTD.
KNIFE RIVER CORPORATION - SOUTH
A. L. HELMCAMP, INC.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
TEXCON GENERAL CONTRACTORS
PREPARING ROW
STA 301.700 $520.000 $300.000 $300.000 $950.000 $500.000 $350.000 $300.000 $639.300 $2,000.000
PREPARING ROW(TREE)(5" TO 12" DIA)
EA 12.000 $450.000 $250.000 $250.000 $150.000 $500.000 $500.000 $250.000 $1,466.840 $1,500.000
PREPARING ROW (TREE) (0" TO 6" DIA)
EA 10.000 $220.000 $250.000 $200.000 $150.000 $250.000 $450.000 $175.000 $1,173.470 $850.000
REMOVING CONC (DRIVEWAYS)
SY 205.000 $13.570 $15.000 $10.000 $12.000 $15.000 $18.000 $15.000 $24.660 $35.000
EXCAVATION (ROADWAY)
CY 6,251.000 $8.800 $5.000 $6.000 $8.000 $10.000 $18.000 $6.000 $13.500 $8.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 6,223.000 $17.000 $5.000 $4.500 $6.000 $10.000 $25.000 $8.000 $8.200 $12.000
FURNISHING AND PLACING TOPSOIL (4")
SY 56,959.000 $0.500 $0.500 $0.500 $0.500 $0.750 $0.380 $1.000 $1.030 $3.000
BLOCK SODDING
SY 222.000 $3.410 $5.500 $4.500 $4.500 $5.000 $5.000 $5.000 $11.620 $5.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 56,959.000 $0.100 $0.100 $0.090 $0.090 $0.100 $0.100 $0.090 $0.210 $0.100
BROADCAST SEED (TEMP) (WARM)
SY 13,304.000 $0.130 $0.100 $0.080 $0.080 $0.080 $0.090 $0.080 $0.220 $0.090
BROADCAST SEED (TEMP) (COOL)
SY 13,304.000 $0.130 $0.100 $0.080 $0.080 $0.080 $0.090 $0.080 $0.220 $0.090
VEGETATIVE WATERING
MG 866.000 $19.590 $14.000 $5.000 $12.000 $10.000 $20.000 $16.000 $13.720 $65.000
FL BS (CMP IN PLC)(TY D)(GR1-2)(1")
SY 45,277.000 $8.000 $1.750 $3.600 $1.650 $3.000 $1.500 $2.000 $2.770 $3.000
FL BS (CMP IN PLC)(TY D)(GR1-2)(3")
SY 37,542.000 $8.000 $1.500 $7.500 $4.700 $5.000 $4.400 $6.000 $8.300 $8.500
REWORK BS MTL (TY B) (6") (DENS CONT)
SY 82,819.000 $10.600 $5.500 $2.500 $4.200 $3.500 $4.650 $5.500 $4.320 $4.500
CEMENT
TON 1,261.000 $149.000 $145.000 $150.000 $143.000 $150.000 $152.000 $150.000 $162.410 $185.000
CEMENT TREAT(EXIST MATL)(8")
SY 95,543.000 $2.000 $1.250 $1.250 $1.300 $2.000 $2.550 $2.600 $1.860 $2.500
ASPH (RC-250)
GAL 23,886.000 $3.910 $3.900 $4.000 $3.700 $3.500 $3.830 $4.250 $4.430 $7.800
AGGR (TY-B GR-5 OR TY-L GR-5)
CY 708.000 $95.310 $85.000 $111.000 $100.000 $85.000 $138.000 $150.000 $105.050 $235.000
AGGR (TY-PB GR-4 OR TY-PL GR-4 SAC-A)
CY 1,326.000 $83.650 $110.000 $119.000 $110.000 $115.000 $143.000 $150.000 $133.860 $225.000
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 66,256.000 $2.850 $3.700 $3.300 $3.200 $3.500 $3.140 $5.500 $4.050 $5.900
SUPERPAVE MIXTURES SP-D SAC-A PG64-22
TON 1,548.000 $90.000 $90.000 $96.000 $84.000 $85.000 $91.000 $82.000 $116.220 $132.000
PLANE ASPH CONC PAV (2")
SY 12,451.000 $3.500 $1.750 $4.180 $2.000 $2.000 $1.600 $1.600 $3.550 $2.000
TRENCH EXCAVATION PROTECTION
LF 4.000 $4.000 $20.000 $20.000 $20.000 $100.000 $22.200 $21.000 $114.530 $250.000
TEMPORARY SPL SHORING
SF 424.000 $25.000 $40.000 $40.000 $40.000 $50.000 $44.400 $41.000 $45.180 $135.000
CL C CONC (WINGWALLS)
CY 3.000 $1,451.000 $3,000.000 $2,500.000 $1,700.000 $2,500.000 $2,770.000 $2,800.000 $4,829.750 $1,500.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 15.000 $180.000 $105.000 $105.000 $170.000 $200.000 $116.000 $125.000 $446.840 $200.000
RIPRAP (MOW STRIP)(4 IN)
CY 102.000 $500.000 $650.000 $600.000 $500.000 $500.000 $650.000 $650.000 $594.140 $450.000
CONC BOX CULV (5 FT X 4 FT)
LF 16.000 $269.290 $500.000 $500.000 $1,000.000 $650.000 $550.000 $560.000 $2,043.210 $1,125.000
CONC BOX CULV (6 FT X 4 FT)
LF 23.000 $327.550 $525.000 $525.000 $500.000 $675.000 $600.000 $580.000 $1,465.350 $1,370.000
CONC BOX CULV (6 FT X 6 FT)
LF 24.000 $372.640 $550.000 $550.000 $890.000 $700.000 $600.000 $600.000 $1,668.380 $1,600.000
CONC BOX CULV (8 FT X 6 FT)(EXTEND)
LF 20.000 $650.000 $900.000 $900.000 $1,100.000 $750.000 $1,000.000 $1,000.000 $1,678.390 $2,000.000
RC PIPE (CL III)(18 IN)
LF 2,400.000 $50.000 $48.000 $48.000 $54.000 $55.000 $53.000 $52.000 $73.240 $96.000
RC PIPE (CL III)(24 IN)
LF 135.000 $71.620 $90.000 $94.000 $85.000 $70.000 $104.000 $100.000 $113.120 $110.000
INLET (COMPL)(TY H)(MOD)
EA 1.000 $4,500.000 $4,000.000 $4,000.000 $2,400.000 $4,500.000 $4,440.000 $4,200.000 $5,871.160 $4,500.000
WINGWALL (PW - 1) (HW=10 FT)
EA 1.000 $25,000.000 $27,000.000 $27,000.000 $21,000.000 $35,000.000 $30,000.000 $30,000.000 $29,155.850 $30,000.000
WINGWALL (PW - 1) (HW=6 FT)
EA 1.000 $10,000.000 $9,500.000 $9,500.000 $8,000.000 $12,000.000 $10,500.000 $11,000.000 $20,531.260 $10,000.000
WINGWALL (PW - 1) (HW=7 FT)
EA 1.000 $15,293.000 $14,000.000 $14,000.000 $10,000.000 $16,000.000 $15,500.000 $16,000.000 $21,614.610 $15,000.000
WINGWALL (PW - 1) (HW=8 FT)
EA 1.000 $20,672.830 $18,000.000 $18,000.000 $14,000.000 $25,000.000 $20,000.000 $20,000.000 $22,460.860 $20,000.000
SET (TY I)(S= 6 FT)(HW= 5 FT)(6:1) (P)
EA 2.000 $10,200.000 $12,500.000 $12,500.000 $11,000.000 $10,000.000 $13,900.000 $14,000.000 $8,403.460 $16,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 16.000 $788.950 $750.000 $750.000 $1,500.000 $1,000.000 $830.000 $850.000 $991.490 $1,200.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 2.000 $800.000 $800.000 $800.000 $1,500.000 $1,250.000 $900.000 $950.000 $1,022.740 $1,250.000
SET (REMOV & REINSTALL)
EA 1.000 $510.840 $550.000 $550.000 $1,500.000 $600.000 $600.000 $600.000 $2,144.950 $750.000
REMOV STR (SMALL)
EA 3.000 $920.000 $750.000 $750.000 $650.000 $1,250.000 $830.000 $900.000 $1,550.290 $1,000.000
MOBILIZATION
LS 1.000 $460,000.000 $225,000.000 $150,000.000 $240,000.000 $240,000.000 $295,500.000 $290,000.000 $744,643.100 $350,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $5,700.000 $1,900.000 $4,000.000 $3,500.000 $2,000.000 $1,680.000 $9,000.000 $2,669.190 $8,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 360.000 $31.000 $25.000 $24.000 $24.000 $27.000 $26.600 $26.000 $50.290 $27.000
ROCK FILTER DAMS (REMOVE)
LF 360.000 $11.080 $8.500 $8.000 $8.000 $5.000 $8.000 $7.000 $11.670 $9.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 78.000 $34.370 $18.000 $16.000 $16.000 $25.000 $18.000 $10.000 $28.730 $18.000
CONSTRUCTION EXITS (REMOVE)
SY 78.000 $8.800 $8.500 $7.000 $7.000 $5.000 $7.000 $2.000 $5.390 $8.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,470.000 $3.240 $2.750 $2.500 $2.500 $3.000 $2.780 $3.000 $3.260 $2.800
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,470.000 $0.770 $1.250 $1.000 $1.000 $0.500 $1.000 $1.000 $1.170 $1.120
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 3,262.000 $3.750 $3.750 $3.500 $3.500 $4.000 $3.890 $4.000 $8.610 $3.900
BIODEG EROSN CONT LOGS (REMOVE)
LF 3,262.000 $0.670 $1.250 $1.000 $1.000 $1.000 $1.000 $1.000 $2.120 $1.120
DRIVEWAYS (CONC)
SY 205.000 $78.180 $110.000 $100.000 $77.000 $90.000 $110.000 $110.000 $89.200 $90.000
DRIVEWAYS (ACP)
SY 146.000 $30.000 $25.000 $55.000 $29.000 $30.000 $38.800 $40.000 $83.260 $37.000
DRIVEWAYS (SURF TREAT)
SY 4,351.000 $20.000 $15.000 $22.700 $28.000 $18.000 $34.500 $20.000 $26.530 $35.000
TURNOUTS (SURF TREAT)
SY 583.000 $20.000 $15.000 $22.000 $25.000 $20.000 $42.000 $27.000 $35.110 $40.000
MTL W-BEAM GD FEN (TIM POST)
LF 600.000 $19.500 $25.000 $18.500 $21.000 $35.000 $24.440 $22.000 $29.030 $25.000
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 175.000 $19.500 $26.500 $21.500 $21.000 $40.000 $25.600 $23.000 $29.280 $25.600
REMOVE METAL BEAM GUARD FENCE
LF 775.000 $1.830 $6.000 $3.000 $1.500 $5.000 $5.500 $2.000 $5.650 $2.200
REMOVE TERMINAL ANCHOR SECTION
EA 8.000 $358.000 $275.000 $75.000 $130.000 $150.000 $450.000 $150.000 $289.790 $190.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,232.320 $2,500.000 $2,350.000 $2,800.000 $2,700.000 $2,900.000 $3,000.000 $2,842.910 $3,000.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 21.000 $160.000 $190.000 $110.000 $110.000 $175.000 $122.000 $210.000 $218.200 $175.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 4.000 $196.000 $232.000 $145.000 $150.000 $190.000 $161.000 $270.000 $257.130 $215.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 3.000 $569.060 $600.000 $420.000 $420.000 $500.000 $467.000 $610.000 $655.330 $625.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 17.000 $509.190 $475.000 $385.000 $390.000 $425.000 $428.000 $570.000 $536.420 $565.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 9.000 $717.600 $560.000 $445.000 $450.000 $500.000 $495.000 $610.000 $629.150 $612.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $817.140 $685.000 $550.000 $550.000 $625.000 $611.000 $780.000 $765.330 $856.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $878.570 $795.000 $595.000 $600.000 $660.000 $561.000 $830.000 $886.330 $940.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 4.000 $1,100.000 $887.000 $675.000 $680.000 $760.000 $750.000 $970.000 $987.530 $1,040.000
IN SM RD SN SUP&AM TYTWT(1)UA(P)
EA 35.000 $337.000 $390.000 $270.000 $280.000 $300.000 $300.000 $440.000 $442.520 $480.000
IN SM RD SN SUP&AM TYTWT(1)UA(T)
EA 3.000 $416.000 $420.000 $345.000 $350.000 $360.000 $383.000 $550.000 $473.830 $600.000
REMOVE SM RD SN SUP&AM
EA 68.000 $122.700 $80.000 $45.000 $80.000 $75.000 $50.000 $75.000 $105.400 $95.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
EA 56.000 $50.000 $60.000 $50.000 $50.000 $50.000 $56.000 $35.000 $95.930 $56.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 12.000 $19.750 $28.000 $18.000 $18.000 $40.000 $54.000 $25.000 $29.660 $34.000
INSTL OM ASSM (OM-2X)(WC)GND
EA 29.000 $86.000 $65.000 $52.000 $52.000 $50.000 $58.000 $45.000 $63.940 $60.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 23.000 $24.000 $45.000 $20.000 $20.000 $40.000 $58.000 $35.000 $30.090 $36.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 47,769.000 $0.170 $0.550 $0.200 $0.100 $0.550 $0.240 $0.230 $0.270 $0.230
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 76.000 $0.890 $0.470 $1.400 $1.000 $1.000 $1.000 $0.650 $1.230 $1.750
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 9,897.000 $0.620 $0.470 $1.400 $1.000 $1.000 $1.000 $0.650 $1.210 $1.750
REF PROF PAV MRK TY I(W)4"(SLD)(060MIL)
LF 62,495.000 $0.270 $0.550 $0.600 $0.550 $0.550 $0.760 $0.720 $0.770 $0.670
REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL)
LF 47,769.000 $0.270 $0.700 $0.600 $0.550 $0.700 $0.760 $0.720 $0.770 $0.670
REF PROF PAV MRK TY I(Y)4"(BRK)(090MIL)
LF 3,323.000 $0.260 $0.800 $0.600 $0.550 $0.800 $0.780 $0.750 $0.810 $0.670
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 338.000 $21.000 $11.500 $20.000 $15.000 $12.000 $6.670 $6.500 $6.950 $23.000
PREFAB PAV MRK TY C (W) (WORD)
EA 2.000 $218.050 $325.000 $300.000 $300.000 $315.000 $333.000 $310.000 $389.170 $335.000
PREFAB PAV MRK TY C (W) (RR XING)
EA 2.000 $500.000 $880.000 $600.000 $650.000 $800.000 $723.000 $710.000 $774.170 $667.000
REFL PAV MRKR TY I-C
EA 13.000 $2.810 $11.000 $10.000 $3.000 $10.000 $5.560 $5.300 $14.600 $11.150
REFL PAV MRKR TY II-A-A
EA 752.000 $2.540 $5.000 $5.000 $3.000 $5.000 $5.560 $5.300 $5.660 $5.600
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $5,500.000 $15,000.000 $7,500.000 $5,000.000 $200.000 $6,000.000 $22,388.320 $20,000.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 228.000 $4.000 $11.000 $15.000 $15.000 $10.000 $16.000 $15.000 $15.920 $16.700
TMA (STATIONARY)
EA 2.000 $10,000.000 $10,000.000 $12,000.000 $9,000.000 $5,000.000 $1,000.000 $15,000.000 $17,768.320 $30,000.000
TMA (MOBILE OPERATION)
DAY 18.000 $250.000 $65.000 $350.000 $100.000 $150.000 $400.000 $500.000 $391.130 $6,000.000
Totals: $4,143,105.160 $2,816,987.760 $2,889,236.780 $3,058,025.250 $3,087,005.190 $3,425,970.140 $3,589,086.500 $4,376,549.500 $5,270,111.120