Job Info for 0050-02-113

County: BRAZOS Highway: SH 6 Date: 09/03/2020 (4 years ago) Engineer's Estimate: $3,658,238 Control Number: 0050-02-113
Project: NH 2021(060) District: BRYAN Time: 64 WORKING DAYS Type: PROFILE MARKINGS

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $3,658,237.53
STRIPE-A-ZONE, INC.   $2,655,543.38 1
-27.41% | -$1,002,694.15
D. I. J. CONSTRUCTION, INC.   $2,679,734.20 2
-26.75% | -$978,503.33
0.91% | $24,190.82
TRP CONSTRUCTION GROUP, LLC   $2,875,833.60 3
-21.39% | -$782,403.93
8.3% | $220,290.22
7.32% | $196,099.40
PMI PAVEMENT MARKING, LLC   $2,899,141.08 4
-20.75% | -$759,096.45
9.17% | $243,597.70
0.81% | $23,307.48
TOTAL HIGHWAY MAINTENANCE, LLC   $3,367,134.58 5
-7.96% | -$291,102.95
26.8% | $711,591.20
16.14% | $467,993.50
INTERSTATE BARRICADES & MARKINGS, INC.   $3,698,282.32 6
1.09% | $40,044.79
39.27% | $1,042,738.94
9.83% | $331,147.74
STRIPING TECHNOLOGY, L.P.   $3,859,234.20 7
5.49% | $200,996.67
45.33% | $1,203,690.82
4.35% | $160,951.88

Bid Items

Items: 18, 0 filtered
BRAZOS SH 6  |  BRYAN  |  0050-02-113  |  09/03/2020  |  $3,658,238  |  NH 2021(060)  |  PROFILE MRK  |  64 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate STRIPE-A-ZONE, INC. D. I. J. CONSTRUCTION, INC. TRP CONSTRUCTION GROUP, LLC PMI PAVEMENT MARKING, LLC TOTAL HIGHWAY MAINTENANCE, LLC INTERSTATE BARRICADES & MARKINGS, INC. STRIPING TECHNOLOGY, L.P.
500 6001 MOBILIZATION LS 1.000 $200,000.000 $65,000.000 $26,000.000 $40,000.000 $66,000.000 $200,000.000 $350,000.000 $350,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $10,000.000 $1.000 $2,000.000 $500.000 $12,250.000 $25,000.000 $10,000.000 $65,000.000
666 6282 REF PROF PAV MRK TY I(W)4"(SLD)(060MIL) LF 3,063,527.000 $0.550 $0.410 $0.420 $0.450 $0.340 $0.470 $0.520 $0.500
666 6287 REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL) LF 1,807,933.000 $0.600 $0.460 $0.480 $0.500 $0.560 $0.510 $0.520 $0.550
666 6291 REF PROF PAV MRK TY I(Y)4"(BRK)(090MIL) LF 213,511.000 $0.700 $0.460 $0.520 $0.550 $0.560 $0.510 $0.520 $0.650
666 6300 RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) LF 73,582.000 $0.320 $0.290 $0.250 $0.300 $0.410 $0.330 $0.300 $0.400
666 6303 RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) LF 270,337.000 $0.320 $0.290 $0.240 $0.300 $0.410 $0.310 $0.300 $0.340
666 6312 RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) LF 89,017.000 $0.320 $0.300 $0.250 $0.300 $0.420 $0.330 $0.300 $0.400
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 340,908.000 $0.320 $0.300 $0.240 $0.300 $0.410 $0.310 $0.300 $0.340
666 6343 REF PROF PAV MRK TY I(W)6"(SLD)(100MIL) LF 82,113.000 $0.800 $0.660 $0.680 $0.700 $0.950 $0.610 $0.700 $1.000
666 6346 REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL) LF 4,818.000 $0.800 $0.660 $0.720 $0.700 $1.050 $0.700 $0.700 $1.000
666 6347 REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL) LF 62,280.000 $0.750 $0.630 $0.680 $0.700 $0.980 $0.610 $0.700 $1.000
672 6007 REFL PAV MRKR TY I-C EA 1,361.000 $3.500 $4.000 $4.000 $3.000 $3.600 $4.000 $3.000 $3.500
672 6009 REFL PAV MRKR TY II-A-A EA 6,561.000 $3.000 $4.000 $4.000 $3.000 $3.600 $4.000 $3.000 $3.500
672 6010 REFL PAV MRKR TY II-C-R EA 350.000 $3.400 $4.000 $4.000 $3.000 $3.600 $4.500 $3.000 $4.000
6056 6002 PREFORMED CENTERLINE RUMBLE STRIP LF 10,433.000 $3.600 $4.400 $5.350 $4.000 $8.400 $5.500 $8.500 $6.500
6185 6002 TMA (STATIONARY) DAY 114.000 $200.000 $1.000 $1.000 $50.000 $60.000 $250.000 $500.000 $1.000
6185 6005 TMA (MOBILE OPERATION) DAY 196.000 $200.000 $1.000 $1.000 $125.000 $60.000 $600.000 $750.000 $1.000
Totals: $3,658,237.53 $2,655,543.38 $2,679,734.20 $2,875,833.60 $2,899,141.08 $3,367,134.58 $3,698,282.32 $3,859,234.20