Job Info for 0049-12-150

County: BRAZOS Highway: US 190 Date: 08/02/2024 (3 months ago) Engineer's Estimate: $2,189,450 Control Number: 0049-12-150
Project: STP 2B24(359)HES District: BRYAN Time: 44 WORKING DAYS Type: INSTALL CABLE MEDIAN BARRIER
Bidder's List
Informational:

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,189,450.10
MASSANA CONSTRUCTION INC.   $1,348,041.00 1
-38.43% | -$841,409.10
SCR CIVIL CONSTRUCTION, LLC   $1,901,841.83 2
-13.14% | -$287,608.27
41.08% | $553,800.83
ROADWAY SPECIALTIES, INC.   $1,928,134.50 3
-11.94% | -$261,315.60
43.03% | $580,093.50
1.38% | $26,292.67
BK FIELD OPERATIONS LLC   $2,104,118.22 4
-3.9% | -$85,331.88
56.09% | $756,077.22
9.13% | $175,983.72
MB WESTERN INDUSTRIAL CONTRACTING CO.   $2,125,031.26 5
-2.94% | -$64,418.84
57.64% | $776,990.26
0.99% | $20,913.04

Bid Items

Items: 26, 0 filtered
BRAZOS US 190  |  BRYAN  |  0049-12-150  |  08/02/2024  |  $2,189,450  |  STP 2B24(359)HES  |  INSTL CABLE MEDIAN BARRIER  |  44 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate MASSANA CONSTRUCTION INC. SCR CIVIL CONSTRUCTION, LLC ROADWAY SPECIALTIES, INC. BK FIELD OPERATIONS LLC MB WESTERN INDUSTRIAL CONTRACTING CO.
105 6165 RMV TRT & UNTRT BASE & ASPH PV(18"-36") SY 265.000 $23.000 $40.000 $77.000 $17.550 $112.050 $5.000
110 6001 EXCAVATION (ROADWAY) CY 184.000 $60.000 $55.000 $35.000 $22.880 $95.380 $40.000
150 6001 BLADING STA 405.000 $93.000 $35.000 $50.000 $30.160 $135.000 $200.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 70,720.000 $2.000 $0.010 $3.000 $5.480 $2.500 $1.000
164 6003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY 70,720.000 $0.500 $0.010 $0.300 $0.300 $0.410 $0.260
164 6009 BROADCAST SEED (TEMP) (WARM) SY 35,361.000 $0.550 $0.010 $0.230 $0.300 $0.300 $0.260
164 6011 BROADCAST SEED (TEMP) (COOL) SY 35,361.000 $0.550 $0.010 $0.200 $0.300 $0.350 $0.260
168 6001 VEGETATIVE WATERING MG 708.000 $42.000 $0.010 $75.000 $60.380 $95.000 $96.200
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 1,218.000 $600.000 $370.000 $616.000 $483.720 $537.000 $650.000
496 6004 REMOV STR (SET) EA 2.000 $800.000 $1,100.000 $500.000 $1,912.670 $1,200.000 $950.000
496 6016 REMOV STR (PIPE) EA 1.000 $1,500.000 $600.000 $1,500.000 $2,405.050 $2,500.000 $2,750.000
500 6001 MOBILIZATION LS 1.000 $199,732.000 $235,804.300 $161,150.000 $206,418.750 $250,700.000 $200,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 $7,500.000 $16,000.000 $8,000.000 $2,636.100 $10,000.000 $2,250.000
506 6002 ROCK FILTER DAMS (INSTALL) (TY 2) LF 220.000 $40.000 $85.000 $97.000 $68.180 $150.000 $58.500
506 6011 ROCK FILTER DAMS (REMOVE) LF 220.000 $12.000 $35.000 $40.000 $22.730 $50.000 $19.500
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 600.000 $6.500 $16.200 $18.450 $6.820 $10.000 $5.850
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 600.000 $1.500 $3.000 $3.350 $1.520 $5.000 $1.300
543 6002 CABLE BARRIER SYSTEM (TL-4) LF 32,354.000 $20.000 $12.000 $13.150 $13.810 $16.170 $19.680
543 6020 CABLE BARRIER TERMINAL SECTION (TL-4) EA 40.000 $5,000.000 $2,500.000 $2,100.000 $2,348.060 $3,847.000 $3,360.000
666 6178 REFL PAV MRK TY II (W) 8" (SLD) LF 110.000 $0.900 $1.800 $5.450 $6.060 $4.750 $6.175
666 6207 REFL PAV MRK TY II (Y) 4" (SLD) LF 248.000 $1.500 $2.000 $2.750 $4.550 $2.380 $3.094
672 6007 REFL PAV MRKR TY I-C EA 7.000 $7.000 $13.000 $86.000 $30.300 $75.000 $97.500
677 6008 ELIM EXT PAV MRK & MRKS (ARROW) EA 2.000 $100.000 $120.000 $261.000 $227.250 $228.070 $296.490
677 6012 ELIM EXT PAV MRK & MRKS (WORD) EA 2.000 $85.000 $120.000 $261.000 $227.250 $228.070 $296.490
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 4.000 $9,000.000 $1,500.000 $3,000.000 $7,500.000 $225.000 $10,000.000
6185 6002 TMA (STATIONARY) DAY 65.000 $275.000 $128.000 $485.000 $318.150 $200.000 $250.000
Totals: $2,189,450.10 $1,348,041.00 $1,901,841.83 $1,928,134.50 $2,104,118.22 $2,125,031.26