BRAZORIA SH0288 (6364-37-001)

Items: 15

County: BRAZORIA
Length: N/A
Highway: SH0288
District: HOUSTON
Control Number: 6364-37-001
DBE Goal: N/A
Project: RMC - 636437001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $268,957.28
Date: 08/11/2020 (5 years ago)
Contract Number: N/A
Type: REPAIR CONCRETE PAVEMENT AND SPALL REPAI
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$268,957.28
$320,160.00
Over/Under Est: 19.04% $51,202.72
Over/Under Est: 23.84% $64,119.07
Amt Left: 4.03% $12,916.35
Over/Under Est: 50.96% $137,067.72
Amt Left: 26.82% $85,865.00
Delta: -21.90% -$72,948.65
$488,230.00
Over/Under Est: 81.53% $219,272.72
Amt Left: 52.5% $168,070.00
Delta: -20.25% -$82,205.00

Bid Items & Bid Tabulations

15 Total 0 of 15
BRAZORIA  |  SH0288  |  HOUSTON  |  6364-37-001  |  08/11/2020  |  $268,957.28  |  RMC - 636437001  |  REPAIR CONC PAVMT AND SPALL REPAI  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ISI CONTRACTING, INC.
WILSON BUILDING SERVICES, INC.
MAIN LANE INDUSTRIES LTD.
CPAVE, INC.
SALV,HAUL& STKPL RCL APH PV(VAR DEPTH)
SY 200.000 $15.000 $8.000 $3.750 $10.000 $63.000
D-GR HMA(SQ) TY-D PG64-22
TON 30.000 $100.000 $255.000 $300.000 $150.000 $815.000
FULL - DEPTH REPAIR CRCP (8")
SY 100.000 $260.000 $285.000 $195.000 $410.000 $330.000
FULL - DEPTH REPAIR CRCP (9")
SY 100.000 $262.000 $302.000 $175.000 $440.000 $340.000
FULL - DEPTH REPAIR CRCP (10")
SY 100.000 $275.000 $315.000 $325.000 $450.000 $350.000
FULL - DEPTH REPAIR CRCP (11")
SY 100.000 $290.000 $355.000 $150.000 $460.000 $360.000
FULL - DEPTH REPAIR CPJR (9")
SY 100.000 $260.000 $301.000 $310.000 $420.000 $335.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 100.000 $81.500 $90.000 $246.430 $100.000 $125.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 18.000 $130.960 $145.000 $135.000 $250.000 $335.000
MOBILIZATION (CALLOUT)
EA 15.000 $200.000 $500.000 $750.000 $50.000 $2,000.000
MOBILIZATION (EMERGENCY)
EA 5.000 $950.000 $1,800.000 $2,700.000 $100.000 $2,700.000
SPALLING REPAIR (HYDRAULIC CEMENT)
CF 250.000 $100.000 $218.000 $250.000 $275.000 $140.000
FIBER REINF POLYMER PATCHNG MATLS (SPL)
LB 25,000.000 $2.280 $2.200 $2.450 $3.500 $5.500
RAISING AND UNDERSEALING CONCRETE SLAB
LB 1,000.000 $7.000 $7.000 $6.500 $9.000 $13.650
TMA (STATIONARY)
DAY 105.000 $200.000 $100.000 $245.270 $5.000 $300.000
Totals: $268,957.280 $320,160.000 $333,076.350 $406,025.000 $488,230.000