County: BRAZORIA Highway: SH0288 Date: 10/15/2019 (5 years ago) Engineer's Estimate: $247,935 Control Number: 6349-80-001
Project: RMC - 634980001 District: HOUSTON Time: 365 CALENDAR DAYS Type: PUMP STATION & DRAINAGE SYSTEM CLEANING

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $247,935.00
AIMS COMPANIES   $275,555.00 1
11.14% | $27,620.00

Bid Items

Items: 17, 0 filtered
BRAZORIA SH0288  |  HOUSTON  |  6349-80-001  |  10/15/2019  |  $247,935  |  RMC - 634980001  |  PUMP STATION & DRAINAGE SYSTEM CLEANING  |  365 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate AIMS COMPANIES
500 6033 MOBILIZATION (CALLOUT) EA 6.000 $900.000 $1,200.000
764 6001 DRAIN INLET CLEANING EA 50.000 $78.000 $80.000
764 6002 PUMP STATION WELL CLEANING EA 4.000 $1,600.000 $1,600.000
764 6003 BASKET AND INLET PIPE CLEANING EA 4.000 $525.000 $525.000
764 6005 SUMP CLEANING EA 4.000 $475.000 $475.000
764 6007 STORM SEWER CLEANING (PIPE)(12"-18"DIA) LF 10,000.000 $4.450 $4.750
764 6008 STORM SEWER CLEANING (PIPE)(19"-24"DIA) LF 25,000.000 $4.750 $5.500
764 6009 STORM SEWER CLEANING (PIPE)(25"-30"DIA) LF 2,500.000 $6.000 $6.000
764 6010 STORM SEWER CLEANING (PIPE)(31"-36"DIA) LF 1,000.000 $7.000 $7.000
764 6011 STORM SEWER CLEANING (PIPE)(37"-42"DIA) LF 500.000 $7.000 $8.000
764 6012 STORM SEWER CLEANING (PIPE)(43"-54"DIA) LF 250.000 $8.000 $8.500
764 6016 STORM SEWER CLEAN (BOX CULV) (6-<12 SF) LF 500.000 $9.000 $9.000
764 6017 STORM SEWER CLEAN (BOX CULV)(12-<24 SF) LF 500.000 $16.000 $16.000
764 6018 STORM SEWER CLEAN (BOX CULV)(24-<48 SF) LF 500.000 $17.500 $17.000
764 6021 SLOTTED DRAIN CLEANING LF 620.000 $3.000 $2.750
6185 6002 TMA (STATIONARY) DAY 125.000 $100.000 $125.000
7019 6001 STORM SEWER (TELEVISION INSPECTION) LF 500.000 $3.750 $5.000
Totals: $247,935.00 $275,555.00