BRAZORIA SH0288 (6328-18-001)

Items: 56

County: BRAZORIA
Length: N/A
Highway: SH0288
District: HOUSTON
Control Number: 6328-18-001
DBE Goal: N/A
Project: RMC - 632818001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $471,077.00
Date: 06/05/2018 (8 years ago)
Contract Number: N/A
Type: GUARDRAIL REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (1)
E
Engineer's Estimate
$471,077.00
$477,375.00
Over/Under Est: 1.34% $6,298.00

Bid Items & Bid Tabulations

56 Total 0 of 56
BRAZORIA  |  SH0288  |  HOUSTON  |  6328-18-001  |  06/05/2018  |  $471,077.00  |  RMC - 632818001  |  GUARDRAIL REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ISI CONTRACTING, INC.
REMOVING CONCRETE(MOW STRIP)
LF 50.000 $15.000 $10.000
REMOVING STAB BASE AND ASPH PAV (4")
SY 200.000 $25.000 $16.000
CONC STR REPAIR (STANDARD)
SF 10.000 $90.000 $95.000
RIPRAP (MOW STRIP)(4 IN)
CY 35.000 $400.000 $390.000
MOBILIZATION (CALLOUT)
EA 30.000 $200.000 $200.000
MOBILIZATION (EMERGENCY)
EA 6.000 $800.000 $800.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 900.000 $6.000 $5.000
MTL W-BEAM GD FEN (TIM POST)
LF 725.000 $20.000 $22.000
MTL W-BEAM GD FEN (STEEL POST)
LF 25.000 $20.000 $22.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 5.000 $2,100.000 $2,400.000
SHORT RADIUS
LF 50.000 $26.760 $40.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 5.000 $500.000 $500.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 5.000 $1,400.000 $1,200.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 1.000 $1,462.500 $700.000
REMOVE METAL BEAM GUARD FENCE
LF 1,200.000 $1.000 $1.000
GUARDRAIL END TREATMENT (INSTALL)
EA 5.000 $2,600.000 $2,900.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $600.000 $600.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL2)
EA 1.000 $17,000.000 $17,000.000
CRASH CUSH ATTEN (INSTL)(L)(N)(70)
EA 1.000 $21,000.000 $24,000.000
REPAIR RAIL ELEMENT (W - BEAM)
LF 4,700.000 $15.000 $15.000
REPAIR RAIL ELEMENT (THRIE - BEAM)
LF 20.000 $15.000 $15.000
REP RAIL ELMNT(THRIE-BM TRANS TO W -BM)
LF 10.000 $15.000 $15.000
REM/REPAIR RAIL ELEMENT (CURVED RAIL)
LF 50.000 $22.130 $20.000
RAISE RAIL ELEMENT
LF 600.000 $5.000 $5.000
REM / REPL TIMBER/STL POST W/O CONC FND
EA 800.000 $40.000 $40.000
REM / REPL TIMBER / STL POST W/CONC FND
EA 200.000 $50.000 $50.000
REM / REPL STEEL POST W / CONC FND
EA 1.000 $90.000 $90.000
REPAIR STEEL POST WITH BASE PLATE
EA 5.000 $25.000 $25.000
REALIGN POSTS
EA 200.000 $8.000 $8.000
REMOVE & REPLACE BLOCKOUT
EA 125.000 $5.000 $5.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 2,650.000 $18.000 $19.500
REPLACE SINGLE GDRAIL TERMINAL POST
EA 300.000 $55.000 $45.000
REMOVE GDRAIL END TRT / REPL WITH SGT
EA 10.000 $2,500.000 $2,600.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 65.000 $1,100.000 $1,050.000
REM & RESET SGT IMPACT HEAD
EA 25.000 $100.000 $100.000
REPLACE SGT CABLE ASSEMBLY
EA 30.000 $75.000 $75.000
REPLACE SGT CABLE ANCHOR
EA 30.000 $70.000 $70.000
REPLACE SGT STRUT
EA 30.000 $50.000 $50.000
REPLACE SGT OBJECT MARKER
EA 55.000 $25.000 $25.000
REMOVE AND REPLACE LONG SPAN CRT POST
EA 6.000 $55.000 $60.000
REPLACE POSTS (TL-3)
EA 25.000 $95.000 $95.000
CABLE SPLICE / TURNBUCKLE (TL-3)
EA 2.000 $100.000 $100.000
REPAIR CONCRETE FOUNDATION (TL-3)
EA 1.000 $100.000 $100.000
REPR OR REPLC CABLE BARR TERM SEC(TL-3)
EA 1.000 $1,200.000 $1,200.000
CHECK / RE-TENSION CABLE
EA 5.000 $250.000 $250.000
REPAIR (TRACC)
LF 25.000 $75.000 $75.000
REPAIR (ENERGY ABSORB SYS) (GDRAIL)
EA 1.000 $2,000.000 $2,000.000
REPAIR REACT (MISC) (HARDWARE)
EA 1.000 $1,000.000 $1,000.000
REPAIR REACT (CYLINDERS)
EA 1.000 $3,000.000 $3,000.000
REPAIR (SHORTRACC)
LF 25.000 $50.000 $50.000
REPAIR TAU II (N)
LF 35.000 $200.000 $200.000
REPAIR TAU II (W)
LF 25.000 $225.000 $225.000
REPAIR (SMTC) (N)
LF 50.000 $165.000 $165.000
REPAIR (STEEL POST W/ W-BEAM - T101)
LF 25.000 $5.000 $5.000
REPAIR (STL POST W/ DOUBLED W-BEAMS-T6)
LF 25.000 $5.000 $5.000
TMA (STATIONARY)
DAY 150.000 $120.000 $150.000
Totals: $471,077.000 $477,375.000