PREPARING ROW
|
STA
|
20.560
|
$15,000.000
|
$4,000.000
|
$10,710.000
|
$6,425.000
|
|
|
RMV TRT & UNTRT BASE & ASPH PV(12"-18")
|
SY
|
3,114.000
|
$18.000
|
$10.000
|
$13.990
|
$10.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
1,097.000
|
$30.000
|
$25.000
|
$14.730
|
$30.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
3,701.000
|
$30.000
|
$25.000
|
$19.640
|
$30.000
|
|
|
EMBANK(FINAL)(DC)(TY E)(CSBE)
|
CY
|
1,155.000
|
$70.000
|
$65.000
|
$32.730
|
$100.000
|
|
|
BLOCK SODDING
|
SY
|
2,865.000
|
$5.400
|
$8.000
|
$7.850
|
$8.070
|
|
|
STRAW OR HAY MULCH
|
SY
|
2,865.000
|
$0.300
|
$5.000
|
$0.560
|
$5.050
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
2,865.000
|
$0.400
|
$2.000
|
$0.960
|
$2.210
|
|
|
FERTILIZER
|
AC
|
1.190
|
$1,350.000
|
$5,500.000
|
$841.500
|
$5,627.220
|
|
|
VEGETATIVE WATERING
|
MG
|
44.700
|
$150.000
|
$75.000
|
$107.290
|
$75.000
|
|
|
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
|
SY
|
5,350.000
|
$40.000
|
$45.000
|
$42.640
|
$50.000
|
|
|
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
|
TON
|
101.000
|
$300.000
|
$400.000
|
$319.770
|
$325.000
|
|
|
LIME TRT (SUBGRADE)(8")
|
SY
|
5,591.000
|
$7.000
|
$9.000
|
$10.800
|
$15.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
1,277.000
|
$10.000
|
$8.000
|
$5.610
|
$6.500
|
|
|
STRUCT EXCAV
|
CY
|
520.000
|
$80.000
|
$12.000
|
$19.640
|
$12.500
|
|
|
CEM STABIL BKFL
|
CY
|
525.000
|
$100.000
|
$50.000
|
$168.300
|
$85.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
122.000
|
$16.000
|
$10.000
|
$5.900
|
$5.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
100.000
|
$160.000
|
$160.000
|
$326.640
|
$200.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
730.000
|
$220.000
|
$500.000
|
$329.440
|
$600.000
|
|
|
CL C CONC (ABUT)
|
CY
|
89.000
|
$1,160.000
|
$1,500.000
|
$1,734.900
|
$2,000.000
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
2.500
|
$1,010.000
|
$1,500.000
|
$948.380
|
$775.000
|
|
|
REINF CONC SLAB
|
SF
|
4,648.000
|
$30.000
|
$35.000
|
$35.500
|
$60.000
|
|
|
APPROACH SLAB
|
CY
|
85.000
|
$700.000
|
$900.000
|
$658.210
|
$775.000
|
|
|
PRESTR CONC GIRDER (TX28)
|
LF
|
278.000
|
$250.000
|
$225.000
|
$327.940
|
$325.000
|
|
|
PRESTR CONC GIRDER (TX34)
|
LF
|
337.170
|
$260.000
|
$225.000
|
$315.210
|
$325.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
272.000
|
$620.000
|
$640.000
|
$548.450
|
$950.000
|
|
|
RIPRAP (CONC)(CL B)(RR8&RR9)
|
CY
|
109.000
|
$420.000
|
$700.000
|
$645.510
|
$850.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
70.000
|
$565.000
|
$700.000
|
$409.890
|
$850.000
|
|
|
RAIL (TY T223)
|
LF
|
528.300
|
$175.000
|
$175.000
|
$298.790
|
$185.000
|
|
|
ARMOR JOINT (SEALED)
|
LF
|
142.000
|
$150.000
|
$110.000
|
$140.250
|
$225.000
|
|
|
CONC BOX CULV (9 FT X 6 FT)
|
LF
|
68.000
|
$1,200.000
|
$2,500.000
|
$1,203.030
|
$1,725.000
|
|
|
CONC BOX CULV (9FT X 4FT)
|
LF
|
32.000
|
$850.000
|
$2,400.000
|
$1,087.940
|
$525.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
640.000
|
$110.000
|
$100.000
|
$96.220
|
$40.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
176.000
|
$120.000
|
$105.000
|
$116.090
|
$185.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
84.000
|
$230.000
|
$150.000
|
$191.740
|
$315.000
|
|
|
RC PIPE (CL III)(72 IN)
|
LF
|
87.000
|
$500.000
|
$700.000
|
$674.960
|
$850.000
|
|
|
WINGWALL (PW - 2) (HW=10 FT)
|
EA
|
2.000
|
$65,000.000
|
$30,000.000
|
$61,289.250
|
$100,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (3: 1) (C)
|
EA
|
2.000
|
$1,100.000
|
$1,250.000
|
$1,107.980
|
$2,100.000
|
|
|
SET (TY II) (18 IN) (RCP) (3: 1) (P)
|
EA
|
1.000
|
$1,350.000
|
$1,250.000
|
$1,107.980
|
$2,100.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
2.000
|
$1,400.000
|
$1,300.000
|
$1,136.030
|
$2,200.000
|
|
|
SET (TY II) (24 IN) (RCP) (3: 1) (C)
|
EA
|
2.000
|
$1,450.000
|
$1,350.000
|
$1,248.230
|
$2,300.000
|
|
|
REMOV STR (PIPE)
|
LF
|
681.000
|
$25.000
|
$28.000
|
$21.750
|
$20.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
32.000
|
$130.000
|
$350.000
|
$129.730
|
$50.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
3.000
|
$37,200.000
|
$25,000.000
|
$25,245.000
|
$55,500.000
|
|
|
REMOV STR (RET WALL)
|
LF
|
56.000
|
$100.000
|
$50.000
|
$104.990
|
$100.000
|
|
|
REMOVING ROCK RIPRAP
|
LF
|
150.000
|
$100.000
|
$1.000
|
$42.080
|
$25.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$343,736.660
|
$380,000.000
|
$477,799.390
|
$190,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
23.000
|
$10,000.000
|
$700.000
|
$7,613.890
|
$10,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
240.000
|
$42.000
|
$65.000
|
$74.760
|
$75.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
468.000
|
$35.000
|
$70.000
|
$31.660
|
$60.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
468.000
|
$10.000
|
$10.000
|
$13.820
|
$20.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
3,846.000
|
$3.750
|
$7.000
|
$6.730
|
$3.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
3,846.000
|
$1.200
|
$1.000
|
$1.680
|
$1.500
|
|
|
CONSTRUCTING DETOURS
|
SY
|
829.000
|
$110.000
|
$140.000
|
$141.510
|
$50.000
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
5.000
|
$6,000.000
|
$4,200.000
|
$1,402.500
|
$4,800.000
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
360.000
|
$80.000
|
$80.000
|
$50.490
|
$90.000
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
360.000
|
$25.000
|
$30.000
|
$19.640
|
$30.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
1,017.000
|
$65.000
|
$80.000
|
$100.980
|
$90.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
750.000
|
$30.000
|
$25.000
|
$27.210
|
$24.250
|
|
|
MTL BEAM GD FEN TRANS (TL2)
|
EA
|
8.000
|
$1,405.000
|
$1,000.000
|
$1,632.510
|
$1,455.000
|
|
|
SHORT RADIUS
|
LF
|
150.000
|
$60.000
|
$35.000
|
$61.710
|
$55.000
|
|
|
DRIVEWAY TERMINAL ANCHOR SECTION
|
EA
|
11.000
|
$1,100.000
|
$790.000
|
$1,178.100
|
$1,050.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
5.000
|
$1,615.000
|
$1,500.000
|
$1,755.930
|
$1,565.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$3,535.000
|
$3,250.000
|
$3,422.100
|
$3,050.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
4.000
|
$1,450.000
|
$2,200.000
|
$1,122.000
|
$1,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
4.000
|
$20,000.000
|
$35,000.000
|
$32,538.000
|
$8,500.000
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 1
|
EA
|
2.000
|
$550.000
|
$260.000
|
$799.400
|
$450.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
13.000
|
$700.000
|
$650.000
|
$566.610
|
$505.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
|
EA
|
2.000
|
$700.000
|
$650.000
|
$611.490
|
$545.000
|
|
|
RELOCATE SM RD SN SUP&AM(SIGN ONLY)
|
EA
|
2.000
|
$300.000
|
$60.000
|
$437.580
|
$390.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
14.000
|
$140.000
|
$60.000
|
$100.980
|
$90.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
|
EA
|
41.000
|
$30.000
|
$30.000
|
$28.050
|
$25.000
|
|
|
INSTL OM ASSM (OM-3L)(TWT)GND
|
EA
|
6.000
|
$360.000
|
$220.000
|
$235.620
|
$210.000
|
|
|
INSTL OM ASSM (OM-3R)(TWT)GND
|
EA
|
6.000
|
$360.000
|
$220.000
|
$235.620
|
$210.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
7.000
|
$25.000
|
$20.000
|
$28.050
|
$50.000
|
|
|
WK ZN PAV MRK REMOV (W)6"(SLD)
|
LF
|
2,046.000
|
$1.500
|
$1.350
|
$2.240
|
$2.100
|
|
|
PAVEMENT SEALER 6"
|
LF
|
7,764.000
|
$0.250
|
$0.550
|
$0.220
|
$0.100
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
3,654.000
|
$0.950
|
$1.300
|
$1.680
|
$1.450
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
4,110.000
|
$1.000
|
$1.300
|
$1.680
|
$1.450
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
53.000
|
$8.000
|
$7.500
|
$8.980
|
$10.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
7,764.000
|
$0.200
|
$0.150
|
$0.060
|
$0.050
|
|
|
TACK COAT
|
GAL
|
301.000
|
$10.000
|
$5.000
|
$8.980
|
$6.500
|
|
|
D-GR HMA TY-D SAC-B PG70-22 (EXEMPT)
|
TON
|
410.000
|
$160.000
|
$225.000
|
$258.060
|
$200.000
|
|
|
D-GR HMA TY-D PG70-22 (EXEMPT)
|
TON
|
418.000
|
$180.000
|
$230.000
|
$258.060
|
$200.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
1,498.000
|
$160.000
|
$5.000
|
$112.200
|
$25.000
|
|
Totals: |
$3,999,103.160
|
$3,799,246.850
|
$4,246,590.121
|
$4,382,019.092
|