REMOVING CONC (PAV)
|
SY
|
2,238.000
|
$5.420
|
$7.000
|
$5.230
|
$10.000
|
$10.820
|
$20.000
|
$9.600
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
450.500
|
$7.000
|
$6.000
|
$5.220
|
$15.000
|
$9.760
|
$10.000
|
$8.800
|
|
|
REMOVING CONC (DRAIN)
|
SY
|
108.000
|
$2.000
|
$8.000
|
$15.000
|
$12.000
|
$11.540
|
$10.000
|
$10.500
|
|
|
REMOVING STAB BASE AND ASPH PAV(8")
|
SY
|
4,938.000
|
$5.000
|
$3.000
|
$10.000
|
$6.000
|
$13.850
|
$8.000
|
$12.500
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
2,215.000
|
$8.000
|
$20.000
|
$9.520
|
$8.000
|
$11.950
|
$20.000
|
$13.500
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
40,463.000
|
$6.250
|
$0.010
|
$2.000
|
$1.000
|
$1.000
|
$20.000
|
$1.350
|
|
|
BACKFILL (TY A OR B)
|
STA
|
12.000
|
$100.000
|
$380.000
|
$107.750
|
$300.000
|
$571.880
|
$600.000
|
$800.000
|
|
|
BLOCK SODDING
|
SY
|
5,903.000
|
$3.000
|
$4.500
|
$3.390
|
$4.000
|
$3.910
|
$3.000
|
$3.500
|
|
|
FERTILIZER
|
AC
|
1.220
|
$665.000
|
$802.790
|
$802.790
|
$300.000
|
$926.270
|
$1,000.000
|
$840.000
|
|
|
VEGETATIVE WATERING
|
MG
|
146.000
|
$16.000
|
$18.000
|
$52.340
|
$50.000
|
$38.450
|
$35.000
|
$52.000
|
|
|
LIME TRT (EXST MATL) (6")
|
SY
|
7,564.000
|
$1.800
|
$2.700
|
$5.000
|
$5.000
|
$5.240
|
$4.000
|
$5.500
|
|
|
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
|
TON
|
102.000
|
$176.000
|
$179.000
|
$180.220
|
$189.000
|
$206.530
|
$200.000
|
$245.000
|
|
|
CEM TRT(PLNT MX) (CL N)(TY E)(GR 4)(6")
|
SY
|
2,239.000
|
$6.450
|
$13.500
|
$15.000
|
$13.000
|
$22.630
|
$15.000
|
$19.250
|
|
|
CEM TRT(PLNT MX) (CLN)(TYA)(GR1-2)(10")
|
SY
|
5,218.000
|
$9.000
|
$22.500
|
$32.000
|
$20.000
|
$31.190
|
$35.000
|
$28.000
|
|
|
ASPHALT STAB BASE (GR 2)(PG 64)
|
TON
|
2,066.000
|
$75.000
|
$88.000
|
$88.000
|
$90.690
|
$105.020
|
$109.000
|
$62.000
|
|
|
ASPHALT STAB BASE (GR 4)(PG 64)
|
TON
|
124.000
|
$70.000
|
$100.000
|
$100.000
|
$102.690
|
$119.340
|
$113.000
|
$84.000
|
|
|
SALV, HAUL & STKPL RCL APH PV (3")
|
SY
|
2,238.000
|
$0.600
|
$2.600
|
$3.520
|
$5.000
|
$4.180
|
$3.000
|
$2.750
|
|
|
SALV, HAUL & STKPL RCL APH PV (4")
|
SY
|
4,703.000
|
$1.000
|
$2.500
|
$1.600
|
$6.000
|
$1.910
|
$3.000
|
$1.300
|
|
|
D-GR HMA(SQ) TY-D SAC-B PG70-22
|
TON
|
849.000
|
$105.000
|
$102.000
|
$102.000
|
$104.690
|
$121.730
|
$109.000
|
$120.000
|
|
|
CONC PVMT (CONT REINF - CRCP) (10")
|
SY
|
2,253.000
|
$50.000
|
$72.000
|
$75.000
|
$65.000
|
$122.630
|
$116.000
|
$95.000
|
|
|
CEM STABIL BKFL
|
CY
|
460.000
|
$60.000
|
$85.000
|
$50.000
|
$75.000
|
$75.260
|
$100.000
|
$54.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
8,652.000
|
$15.000
|
$20.000
|
$100.000
|
$6.000
|
$8.710
|
$45.000
|
$175.000
|
|
|
TEMPORARY SPL SHORING (COFFERDAM)
|
SF
|
3,648.000
|
$40.000
|
$580.000
|
$150.350
|
$600.000
|
$1.000
|
$55.000
|
$980.000
|
|
|
FOUNDATION LOAD TEST (D4945) (PILE)
|
EA
|
21.000
|
$20,000.000
|
$2,800.000
|
$7,000.000
|
$16,966.540
|
$4,004.210
|
$35,000.000
|
$5,600.000
|
|
|
PRESTR CONC PIL (20 IN SQ)
|
LF
|
33,368.000
|
$198.000
|
$90.000
|
$140.000
|
$89.870
|
$103.690
|
$150.000
|
$105.000
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
16.000
|
$141.100
|
$121.000
|
$209.870
|
$121.000
|
$272.300
|
$300.000
|
$240.000
|
|
|
CL A CONC (MEDIAN)
|
CY
|
66.000
|
$1,000.000
|
$340.000
|
$501.000
|
$375.000
|
$431.000
|
$550.000
|
$520.000
|
|
|
CL B CONC (FLUME)
|
CY
|
24.000
|
$475.000
|
$500.000
|
$410.000
|
$425.000
|
$517.980
|
$550.000
|
$420.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
169.000
|
$900.000
|
$600.000
|
$715.690
|
$772.000
|
$1,066.780
|
$900.000
|
$1,320.000
|
|
|
CL C CONC (CAP)(HPC)(MASS)
|
CY
|
1,026.300
|
$900.000
|
$1,200.000
|
$1,250.000
|
$965.000
|
$1,292.650
|
$1,000.000
|
$1,650.000
|
|
|
CL C CONC (COLUMN)(HPC)(MASS)
|
CY
|
983.600
|
$1,200.000
|
$1,400.000
|
$1,400.000
|
$1,150.000
|
$1,419.690
|
$800.000
|
$2,600.000
|
|
|
CL C CONC (FOOTING)(HPC)(MASS)
|
CY
|
1,630.200
|
$1,000.000
|
$1,000.000
|
$1,400.000
|
$1,100.000
|
$717.980
|
$800.000
|
$1,180.000
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
119,037.000
|
$20.000
|
$15.750
|
$22.000
|
$17.000
|
$27.130
|
$25.000
|
$31.000
|
|
|
BRIDGE SIDEWALK (HPC)
|
SF
|
14,801.000
|
$20.000
|
$7.500
|
$11.000
|
$12.720
|
$14.190
|
$15.000
|
$11.500
|
|
|
APPROACH SLAB
|
CY
|
79.000
|
$1,000.000
|
$550.000
|
$500.000
|
$507.180
|
$786.050
|
$500.000
|
$1,200.000
|
|
|
CIP CONC SPLICES AND DIAPH
|
CY
|
621.600
|
$1,500.000
|
$950.000
|
$1,153.530
|
$1,821.030
|
$1,847.990
|
$2,500.000
|
$2,550.000
|
|
|
CIP CLOSURE
|
CY
|
23.400
|
$1,500.000
|
$1,500.000
|
$6,000.000
|
$2,320.390
|
$2,873.070
|
$2,500.000
|
$4,300.000
|
|
|
PRESTR CONC GIRDER (TX70)
|
LF
|
6,540.080
|
$155.000
|
$205.000
|
$239.920
|
$405.420
|
$497.060
|
$175.000
|
$570.000
|
|
|
PRESTR CONC GIRDER (STX7)
|
LF
|
6,347.220
|
$400.000
|
$810.000
|
$778.720
|
$650.160
|
$871.570
|
$1,000.000
|
$970.000
|
|
|
PT FOR SPLICE GIRDER(3 IN)
|
LF
|
25,844.000
|
$20.000
|
$22.500
|
$31.610
|
$19.190
|
$36.810
|
$30.000
|
$32.500
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
60.000
|
$400.000
|
$475.000
|
$514.000
|
$412.050
|
$653.980
|
$550.000
|
$530.000
|
|
|
RIPRAP (CONC) (CL B) (4")
|
CY
|
0.700
|
$375.000
|
$774.590
|
$635.000
|
$1,478.060
|
$818.340
|
$550.000
|
$670.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
16.000
|
$450.000
|
$500.000
|
$635.000
|
$507.820
|
$818.360
|
$550.000
|
$670.000
|
|
|
ELASTOMERIC BEARING (LAMINATED)
|
EA
|
26.000
|
$1,000.000
|
$4,600.000
|
$5,000.000
|
$2,923.780
|
$8,300.490
|
$5,000.000
|
$5,400.000
|
|
|
ELASTOMERIC BEARING (SPECIAL)
|
EA
|
26.000
|
$4,000.000
|
$3,300.000
|
$5,000.000
|
$4,459.960
|
$8,713.750
|
$10,000.000
|
$7,200.000
|
|
|
STR STEEL (MISC NON - BRIDGE)
|
LB
|
5,354.500
|
$10.000
|
$12.500
|
$12.000
|
$35.000
|
$12.560
|
$10.000
|
$9.000
|
|
|
RAIL (TY T402)(HPC)
|
LF
|
1,929.500
|
$200.000
|
$130.000
|
$95.000
|
$161.000
|
$181.810
|
$60.000
|
$185.000
|
|
|
RAIL (TY C402)(HPC)
|
LF
|
1,478.500
|
$205.000
|
$135.000
|
$178.000
|
$250.000
|
$199.910
|
$150.000
|
$220.000
|
|
|
RAIL (CLF-RO)
|
LF
|
192.000
|
$100.000
|
$200.000
|
$108.000
|
$56.080
|
$110.050
|
$125.000
|
$165.000
|
|
|
RAIL (PEDESTRIAN FENCE)
|
LF
|
192.000
|
$100.000
|
$165.000
|
$140.000
|
$123.910
|
$152.590
|
$150.000
|
$130.000
|
|
|
SEALED EXPAN JT (5 IN) (SEJ - M) (GALV)
|
LF
|
434.000
|
$110.000
|
$132.000
|
$250.000
|
$151.160
|
$155.900
|
$175.000
|
$230.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$1,700.000
|
$1,900.000
|
$1,456.600
|
$2,503.670
|
$2,676.920
|
$1,800.000
|
$2,100.000
|
|
|
REMOV STR (BRIDGE 1000 FT OR GREATER)
|
EA
|
1.000
|
$750,000.000
|
$3,750,000.000
|
$1,350,000.000
|
$1,738,483.000
|
$1,743,334.820
|
$6,630,164.000
|
$2,200,000.000
|
|
|
REMOV STR (DOLPHIN AND FENDER SYS)
|
EA
|
1.000
|
$40,000.000
|
$175,000.000
|
$52,705.200
|
$150,000.000
|
$68,500.880
|
$50,000.000
|
$85,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$2,194,591.000
|
$2,800,000.000
|
$2,900,000.000
|
$2,825,000.000
|
$2,793,264.920
|
$4,000,000.000
|
$2,800,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
29.000
|
$6,500.000
|
$4,000.000
|
$1,000.000
|
$6,000.000
|
$3,049.090
|
$5,000.000
|
$2,200.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
25.000
|
$64.780
|
$46.000
|
$46.160
|
$100.000
|
$488.870
|
$50.000
|
$48.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
25.000
|
$10.410
|
$15.000
|
$35.100
|
$50.000
|
$17.420
|
$10.000
|
$15.500
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
222.000
|
$25.000
|
$28.000
|
$28.140
|
$25.000
|
$156.670
|
$50.000
|
$30.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
222.000
|
$8.000
|
$8.000
|
$7.850
|
$10.000
|
$9.060
|
$10.000
|
$8.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
5,585.000
|
$2.500
|
$2.000
|
$2.200
|
$2.000
|
$4.820
|
$3.000
|
$2.400
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
5,585.000
|
$0.700
|
$0.500
|
$0.770
|
$1.000
|
$0.890
|
$1.000
|
$0.800
|
|
|
CONC CURB (TY II)
|
LF
|
38.000
|
$8.000
|
$17.500
|
$25.000
|
$12.480
|
$33.110
|
$11.000
|
$26.000
|
|
|
CONC SIDEWALKS (6")
|
SY
|
84.000
|
$57.000
|
$60.000
|
$89.000
|
$68.440
|
$114.710
|
$100.000
|
$94.000
|
|
|
CURB RAMPS (TY 1)
|
EA
|
1.000
|
$1,800.000
|
$1,550.000
|
$2,250.000
|
$1,761.440
|
$2,926.930
|
$1,800.000
|
$2,300.000
|
|
|
SIDEWALK CURB DRAIN (1 FT WIDE)
|
EA
|
1.000
|
$1,500.000
|
$390.000
|
$5,000.000
|
$1,505.710
|
$2,599.510
|
$1,800.000
|
$850.000
|
|
|
CONC MEDIAN
|
SY
|
46.100
|
$70.000
|
$70.000
|
$101.000
|
$45.500
|
$85.000
|
$100.000
|
$105.000
|
|
|
CONC DIRECTIONAL ISLAND
|
SY
|
259.800
|
$59.000
|
$85.000
|
$89.000
|
$52.000
|
$85.000
|
$100.000
|
$95.000
|
|
|
CONCRETE MEDIAN (NOSE)
|
SY
|
0.800
|
$136.000
|
$1,000.000
|
$370.000
|
$272.200
|
$2,900.000
|
$10,000.000
|
$380.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
100.000
|
$20.000
|
$44.010
|
$19.540
|
$27.500
|
$42.560
|
$25.000
|
$42.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$1,840.000
|
$1,903.450
|
$1,723.260
|
$2,550.000
|
$2,371.070
|
$2,000.000
|
$1,800.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
4,250.000
|
$2.800
|
$1.100
|
$2.610
|
$5.000
|
$3.650
|
$2.500
|
$1.050
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
2.000
|
$205.110
|
$192.550
|
$164.140
|
$500.000
|
$364.780
|
$200.000
|
$180.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$2,600.000
|
$3,317.290
|
$2,445.600
|
$3,165.000
|
$3,647.800
|
$3,000.000
|
$3,200.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
2.000
|
$350.000
|
$302.570
|
$286.990
|
$250.000
|
$303.990
|
$500.000
|
$290.000
|
|
|
CHAIN LINK FENCE (INSTALL) (6')
|
LF
|
2,760.000
|
$19.000
|
$55.010
|
$26.500
|
$17.000
|
$12.220
|
$30.000
|
$17.500
|
|
|
CHAIN LINK FENCE (REMOVE)
|
LF
|
2,760.000
|
$7.000
|
$7.700
|
$9.710
|
$3.240
|
$6.010
|
$5.000
|
$3.400
|
|
|
RELOCATE RD IL ASM (TRANS-BASE)
|
EA
|
2.000
|
$3,000.000
|
$1,290.000
|
$1,725.000
|
$1,290.000
|
$2,019.180
|
$2,500.000
|
$1,800.000
|
|
|
REPLACE LUMINAIRE W/LED (400W EQ)
|
EA
|
2.000
|
$570.000
|
$330.000
|
$839.000
|
$330.000
|
$548.070
|
$750.000
|
$500.000
|
|
|
IN RD IL (TY SA) 40B-10 (250W EQ) LED
|
EA
|
12.000
|
$2,486.000
|
$3,568.000
|
$3,871.000
|
$3,568.000
|
$4,211.430
|
$4,000.000
|
$3,800.000
|
|
|
CONDT (PVC) (SCH 80) (2")
|
LF
|
25.000
|
$7.720
|
$13.110
|
$57.000
|
$13.110
|
$13.670
|
$15.000
|
$12.500
|
|
|
ELEC CONDR (NO.8) BARE
|
LF
|
1,931.000
|
$0.990
|
$1.210
|
$1.160
|
$1.210
|
$1.620
|
$2.000
|
$1.450
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
3,862.000
|
$1.040
|
$1.510
|
$1.260
|
$1.510
|
$1.900
|
$2.000
|
$1.750
|
|
|
GROUND BOX TY D (162922)W/APRON
|
EA
|
1.000
|
$1,150.000
|
$691.000
|
$921.720
|
$691.000
|
$980.740
|
$1,500.000
|
$900.000
|
|
|
ELC SRV TY A 240/480 060(SS)SS(E)GC(U)
|
EA
|
1.000
|
$6,038.500
|
$6,997.000
|
$7,350.000
|
$6,997.000
|
$6,576.760
|
$8,000.000
|
$6,000.000
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
7.000
|
$500.000
|
$1,540.360
|
$75.920
|
$611.260
|
$521.530
|
$600.000
|
$1,450.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
38.000
|
$20.000
|
$22.010
|
$21.250
|
$25.000
|
$120.000
|
$25.000
|
$21.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
12.000
|
$29.940
|
$49.510
|
$26.300
|
$35.000
|
$125.770
|
$30.000
|
$47.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
300.000
|
$0.890
|
$1.970
|
$1.380
|
$1.380
|
$3.460
|
$1.000
|
$2.000
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
100.000
|
$3.200
|
$3.010
|
$3.750
|
$3.750
|
$5.770
|
$3.500
|
$3.150
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
51.000
|
$6.500
|
$6.020
|
$7.500
|
$7.500
|
$7.790
|
$7.000
|
$6.300
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
2.000
|
$150.000
|
$110.000
|
$175.000
|
$175.000
|
$173.080
|
$150.000
|
$115.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
2.000
|
$150.000
|
$120.000
|
$190.000
|
$190.000
|
$173.080
|
$200.000
|
$124.000
|
|
REFL PAV MRK TY I(Y)(MED NOSE)(100MIL)
|
EA
|
1.000
|
$300.000
|
$215.220
|
$250.000
|
$250.000
|
$403.840
|
$350.000
|
$220.000
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
6,165.000
|
$0.480
|
$0.860
|
$0.680
|
$0.680
|
$0.670
|
$0.750
|
$0.900
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
6,528.000
|
$1.000
|
$0.860
|
$0.680
|
$0.680
|
$0.670
|
$0.750
|
$0.900
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
78.000
|
$4.000
|
$5.310
|
$6.000
|
$6.000
|
$5.770
|
$3.500
|
$5.500
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
12,693.000
|
$0.150
|
$0.160
|
$0.100
|
$0.100
|
$0.010
|
$0.100
|
$0.170
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
300.000
|
$0.150
|
$0.220
|
$0.120
|
$0.120
|
$0.010
|
$0.200
|
$0.230
|
|
|
PAV SURF PREP FOR MRK (12")
|
LF
|
100.000
|
$0.400
|
$0.370
|
$0.150
|
$0.150
|
$0.060
|
$0.400
|
$0.380
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
51.000
|
$0.800
|
$2.490
|
$0.200
|
$0.200
|
$0.120
|
$1.000
|
$2.600
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
2.000
|
$20.000
|
$42.000
|
$20.000
|
$20.000
|
$5.770
|
$20.000
|
$44.000
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
2.000
|
$20.000
|
$42.000
|
$20.000
|
$20.000
|
$5.770
|
$25.000
|
$44.000
|
|
|
FULL - WIDTH MOWING
|
CYC
|
5.000
|
$3,190.000
|
$500.000
|
$3,000.000
|
$1,500.000
|
$3,972.080
|
$3,000.000
|
$4,500.000
|
|
|
LITTER REMOVAL
|
CYC
|
5.000
|
$2,260.000
|
$500.000
|
$1,667.290
|
$1,500.000
|
$2,889.130
|
$3,000.000
|
$2,000.000
|
|
|
WIDE FLANGE PAVEMENT TERMINALS
|
LF
|
126.000
|
$200.000
|
$450.000
|
$246.260
|
$534.650
|
$454.030
|
$100.000
|
$725.000
|
|
|
TEMP CONSTRUCTION ACCESS
|
LS
|
1.000
|
$200,000.000
|
$50,000.000
|
$44,543.330
|
$2,000,000.000
|
$1,392,406.700
|
$500,000.000
|
$125,000.000
|
|
|
DOLPHIN AND FENDER SYSTEM
|
LS
|
1.000
|
$350,000.000
|
$200,000.000
|
$220,865.000
|
$188,800.000
|
$241,513.340
|
$100,000.000
|
$375,000.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
42.000
|
$88.000
|
$65.000
|
$145.000
|
$250.000
|
$340.550
|
$10.000
|
$90.000
|
|
|
SOLAR-PWR MARINE NAV LIGHT SYSTEM
|
LS
|
1.000
|
$30,000.000
|
$100,000.000
|
$17,942.000
|
$50,000.000
|
$60,575.380
|
$50,000.000
|
$53,000.000
|
|
Totals: |
$24,916,222.430
|
$28,742,987.417
|
$29,221,175.284
|
$29,899,477.235
|
$31,477,850.005
|
$37,460,284.050
|
$39,823,551.560
|