Job Info for 6452-09-001

County: BOWIE Highway: US0067 Date: 11/02/2023 (1 year ago) Engineer's Estimate: $733,318 Control Number: 6452-09-001
Project: BPM - 645209001 District: ATLANTA Time: 100 W Type: BRIDGE PREVENTATIVE MAINTENANCE
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8
Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $733,318.30
BECK-REIT & SONS, LTD.   $549,785.00 1
-25.03% | -$183,533.30
THK CONSTRUCTION LLC   $597,465.88 2
-18.53% | -$135,852.42
8.67% | $47,680.88
GARRET SHIELDS INFRASTRUCTURE   $613,300.00 3
-16.37% | -$120,018.30
11.55% | $63,515.00
2.65% | $15,834.12
3LW CIVIL LLC   $671,670.00 4
-8.41% | -$61,648.30
22.17% | $121,885.00
9.52% | $58,370.00
SCOUT 5 CONSTRUCTION LLC   $681,805.00 5
-7.02% | -$51,513.30
24.01% | $132,020.00
1.51% | $10,135.00
TRUE ROADS CONSTRUCTION, LLC   $684,305.00 6
-6.68% | -$49,013.30
24.47% | $134,520.00
0.37% | $2,500.00
ICOS MANAGEMENT, LLC   $701,768.00 7
-4.3% | -$31,550.30
27.64% | $151,983.00
2.55% | $17,463.00
PATHFIELD INVESTMENTS LLC   $704,341.00 8
-3.95% | -$28,977.30
28.11% | $154,556.00
0.37% | $2,573.00
RAYFORD'S TRUCK & TRACTOR   $731,975.00 9
-0.18% | -$1,343.30
33.14% | $182,190.00
3.92% | $27,634.00
EAST TEXAS BRIDGE, INC.   $864,975.00 10
17.95% | $131,656.70
57.33% | $315,190.00
18.17% | $133,000.00
CDM HOLDINGS   $952,510.00 11
29.89% | $219,191.70
73.25% | $402,725.00
10.12% | $87,535.00

Bid Items

Items: 9, 0 filtered
BOWIE US0067  |  ATLANTA  |  6452-09-001  |  11/02/2023  |  $733,318  |  BPM - 645209001  |  BRIDGE PREVENT MAINT  |  100 W
Item code Description Unit Quantity Engineer's Estimate BECK-REIT & SONS, LTD. THK CONSTRUCTION LLC GARRET SHIELDS INFRASTRUCTURE 3LW CIVIL LLC SCOUT 5 CONSTRUCTION LLC TRUE ROADS CONSTRUCTION, LLC ICOS MANAGEMENT, LLC PATHFIELD INVESTMENTS LLC RAYFORD'S TRUCK & TRACTOR EAST TEXAS BRIDGE, INC. CDM HOLDINGS
110 6002 EXCAVATION (CHANNEL) CY 315.000 $53.000 $120.000 $45.920 $100.000 $40.000 $35.000 $50.000 $165.000 $60.000 $75.000 $50.000 $165.000
132 6001 EMBANKMENT (FINAL)(ORD COMP)(TY A) CY 264.000 $90.000 $100.000 $51.470 $50.000 $45.000 $80.000 $60.000 $90.000 $100.000 $100.000 $75.000 $105.000
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 499.000 $200.000 $175.000 $137.000 $200.000 $225.000 $130.000 $175.000 $220.000 $210.000 $300.000 $300.000 $265.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 1,547.000 $233.000 $190.000 $200.000 $200.000 $240.000 $260.000 $240.000 $246.000 $233.000 $220.000 $250.000 $235.000
432 6039 BEDDING MATERIAL (6 IN) CY 389.000 $267.000 $70.000 $200.000 $100.000 $215.000 $130.000 $240.000 $220.000 $200.000 $190.000 $275.000 $315.000
500 6001 MOBILIZATION LS 1.000 $66,665.300 $66,000.000 $55,000.000 $60,000.000 $35,000.000 $78,000.000 $65,000.000 $50,000.000 $60,000.000 $60,000.000 $85,000.000 $95,000.000
502 6025 BARR, SIGNS, TRAFFIC HANDLING EA 11.000 $3,394.000 $1,000.000 $3,600.000 $5,000.000 $4,000.000 $3,500.000 $2,000.000 $1.000 $5,000.000 $3,000.000 $6,000.000 $12,000.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 50.000 $180.000 $1.000 $175.000 $10.000 $10.000 $260.000 $75.000 $1.000 $10.000 $200.000 $400.000 $250.000
6185 6002 TMA (STATIONARY) DAY 50.000 $315.000 $1.000 $210.000 $100.000 $10.000 $50.000 $200.000 $1.000 $10.000 $300.000 $300.000 $300.000
Totals: $733,318.30 $549,785.00 $597,465.88 $613,300.00 $671,670.00 $681,805.00 $684,305.00 $701,768.00 $704,341.00 $731,975.00 $864,975.00 $952,510.00