Job Info for 6299-32-001

County: BOWIE Highway: IH0030 Date: 02/01/2018 (6 years ago) Engineer's Estimate: $1,197,405 Control Number: 6299-32-001
Project: BPM - 629932001 District: ATLANTA Time: 250 W Type: BRIDGE PREVENTIVE MAINTENANCE

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,197,405.00
CDM HOLDINGS, LLC   $853,995.00 1
-28.68% | -$343,410.00
STATELINE CONSTRUCTION, LLC   $1,036,476.00 2
-13.44% | -$160,929.00
21.37% | $182,481.00
EAST TEXAS BRIDGE, INC.   $1,074,471.00 3
-10.27% | -$122,934.00
25.82% | $220,476.00
3.67% | $37,995.00
HARTBEAT CONSTRUCTION   $1,077,777.00 4
-9.99% | -$119,628.00
26.2% | $223,782.00
0.31% | $3,306.00
L.C. JORDAN & SON   $1,084,167.00 5
-9.46% | -$113,238.00
26.95% | $230,172.00
0.59% | $6,390.00
PIERCE R & B LLC   $1,174,447.00 6
-1.92% | -$22,958.00
37.52% | $320,452.00
8.33% | $90,280.00
HODGES AND SON CONSTRUCTION COMPANY, INC.   $1,315,370.00 7
9.85% | $117,965.00
54.03% | $461,375.00
12.00% | $140,923.00
SJ&J CONSTRUCTION, LLC   $1,415,180.00 8
18.19% | $217,775.00
65.71% | $561,185.00
7.59% | $99,810.00
FNH CONSTRUCTION, LLC   $1,482,060.00 9
23.77% | $284,655.00
73.54% | $628,065.00
4.73% | $66,880.00
CHAMPION INFRASTRUCTURE, LLC   $1,613,145.00 10
34.72% | $415,740.00
88.89% | $759,150.00
8.84% | $131,085.00

Bid Items

Items: 30, 0 filtered
BOWIE IH0030  |  ATLANTA  |  6299-32-001  |  02/01/2018  |  $1,197,405  |  BPM - 629932001  |  BRIDGE PREVENT MAINT  |  250 W
Item code Description Unit Quantity Engineer's Estimate CDM HOLDINGS, LLC STATELINE CONSTRUCTION, LLC EAST TEXAS BRIDGE, INC. HARTBEAT CONSTRUCTION L.C. JORDAN & SON PIERCE R & B LLC HODGES AND SON CONSTRUCTION COMPANY, INC. SJ&J CONSTRUCTION, LLC FNH CONSTRUCTION, LLC CHAMPION INFRASTRUCTURE, LLC
104 6009 REMOVING CONC (RIPRAP) SY 398.000 $15.000 $0.000 $22.000 $22.000 $18.000 $20.000 $22.000 $125.000 $40.000 $30.000 $60.000
104 6025 REMOVE CONC (WINGWALL) CY 44.000 $350.000 $0.000 $125.000 $350.000 $250.000 $100.000 $250.000 $180.000 $150.000 $300.000 $1,400.000
104 6054 REMOVING CONCRETE(MOW STRIP) LF 960.000 $12.000 $0.000 $12.000 $10.000 $7.000 $20.000 $35.000 $10.000 $10.000 $15.000 $65.000
110 6002 EXCAVATION (CHANNEL) CY 650.000 $10.000 $0.000 $14.000 $35.000 $25.000 $15.000 $25.000 $40.000 $18.000 $30.000 $60.000
132 6001 EMBANKMENT (FINAL)(ORD COMP)(TY A) CY 190.000 $15.000 $0.000 $32.000 $40.000 $29.000 $50.000 $55.000 $40.000 $90.000 $35.000 $50.000
401 6001 FLOWABLE BACKFILL CY 145.000 $350.000 $0.000 $200.000 $325.000 $250.000 $215.000 $350.000 $180.000 $200.000 $350.000 $210.000
403 6001 TEMPORARY SPL SHORING SF 1,400.000 $50.000 $0.000 $23.000 $30.000 $52.000 $10.000 $52.000 $25.000 $12.000 $45.000 $40.000
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 260.000 $250.000 $0.000 $110.000 $185.000 $330.000 $160.000 $185.000 $200.000 $190.000 $1,000.000 $210.000
429 6009 CONC STR REPAIR (STANDARD) SF 4.000 $500.000 $0.000 $500.000 $400.000 $380.000 $400.000 $250.000 $400.000 $100.000 $1,000.000 $300.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 1,850.000 $200.000 $0.000 $145.000 $150.000 $165.000 $185.000 $165.000 $175.000 $130.000 $185.000 $280.000
432 6039 BEDDING MATERIAL (6 IN) CY 617.000 $230.000 $0.000 $110.000 $150.000 $110.000 $176.000 $150.000 $100.000 $35.000 $60.000 $240.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 150.000 $525.000 $0.000 $410.000 $425.000 $490.000 $500.000 $475.000 $550.000 $700.000 $550.000 $875.000
466 6142 WINGWALL (FW - 0) (HW=10 FT) EA 1.000 $23,000.000 $0.000 $27,510.000 $23,000.000 $17,280.000 $20,000.000 $35,000.000 $20,000.000 $40,000.000 $20,000.000 $26,000.000
466 6144 WINGWALL (FW - 0) (HW=12 FT) EA 2.000 $40,000.000 $0.000 $38,865.000 $30,000.000 $32,000.000 $30,000.000 $40,000.000 $35,000.000 $50,000.000 $35,000.000 $29,000.000
466 6169 WINGWALL (FW - S) (HW=8 FT) EA 1.000 $16,000.000 $0.000 $26,410.000 $20,000.000 $17,200.000 $15,000.000 $30,000.000 $12,000.000 $35,000.000 $20,000.000 $22,000.000
466 6170 WINGWALL (FW - S) (HW=9 FT) EA 1.000 $20,000.000 $0.000 $33,125.000 $22,000.000 $22,500.000 $16,000.000 $30,000.000 $12,000.000 $38,000.000 $25,600.000 $24,000.000
480 6001 CLEAN EXIST CULVERTS EA 5.000 $3,000.000 $0.000 $2,000.000 $5,000.000 $4,500.000 $10,000.000 $1,000.000 $20,000.000 $2,000.000 $1,500.000 $1,600.000
500 6001 MOBILIZATION LS 1.000 $100,000.000 $0.000 $100,000.000 $110,000.000 $104,708.000 $120,000.000 $106,000.000 $115,000.000 $420,000.000 $140,000.000 $100,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 12.000 $2,500.000 $0.000 $3,200.000 $5,000.000 $6,000.000 $4,000.000 $5,000.000 $16,000.000 $6,000.000 $9,000.000 $7,000.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 1,825.000 $22.000 $0.000 $18.000 $20.000 $8.000 $20.000 $18.500 $30.000 $50.000 $35.000 $25.000
540 6017 MTL BM GD FEN (LONG SPAN SYSTEM) LF 150.000 $30.000 $0.000 $24.000 $25.000 $35.000 $25.000 $24.000 $30.000 $70.000 $35.000 $80.000
540 6021 MTL THRIE-BEAM GD FEN (TIM POST) EA 1.000 $1,600.000 $0.000 $1,500.000 $1,600.000 $1,400.000 $1,500.000 $1,550.000 $800.000 $1,800.000 $2,850.000 $3,200.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 625.000 $4.000 $0.000 $1.000 $5.000 $3.000 $5.000 $4.500 $2.000 $5.000 $3.000 $20.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 4.000 $250.000 $0.000 $300.000 $350.000 $190.000 $400.000 $325.000 $400.000 $500.000 $500.000 $500.000
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 1.000 $275.000 $0.000 $300.000 $300.000 $200.000 $400.000 $275.000 $400.000 $500.000 $500.000 $300.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 13.000 $2,500.000 $0.000 $2,350.000 $2,500.000 $2,500.000 $300.000 $2,350.000 $2,500.000 $2,500.000 $2,850.000 $3,600.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 5.000 $300.000 $0.000 $250.000 $300.000 $300.000 $400.000 $375.000 $400.000 $600.000 $850.000 $600.000
658 6001 INSTL DEL ASSM (D-SW)SZ 1(FLX)GND EA 3.000 $50.000 $0.000 $50.000 $55.000 $50.000 $65.000 $52.000 $50.000 $90.000 $100.000 $60.000
658 6002 INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BI) EA 18.000 $60.000 $0.000 $50.000 $50.000 $40.000 $65.000 $45.000 $50.000 $90.000 $100.000 $60.000
788 6001 CONCRETE BEAM REPAIR EA 3.000 $2,500.000 $0.000 $40,000.000 $12,000.000 $3,000.000 $12,000.000 $10,000.000 $4,000.000 $10,000.000 $22,000.000 $9,500.000
Totals: $1,197,405.00 $0.00 $1,036,476.00 $1,074,471.00 $1,077,777.00 $1,084,167.00 $1,174,447.00 $1,315,370.00 $1,415,180.00 $1,482,060.00 $1,613,145.00