Job Info for 0945-01-042

County: BOWIE Highway: SH 93 Date: 12/04/2019 (4 years ago) Engineer's Estimate: $1,622,469 Control Number: 0945-01-042
Project: STP 2020(064) District: ATLANTA Time: 268 WORKING DAYS Type: PED

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,622,468.53
J.R. POPE COMPANY, INC.   $1,637,145.40 1
0.9% | $14,676.87
TI-ZACK CONCRETE, INC.   $1,732,104.18 2
6.76% | $109,635.65
5.8% | $94,958.78
EAST TEXAS BRIDGE, INC.   $2,019,619.92 3
24.48% | $397,151.39
23.36% | $382,474.52
16.60% | $287,515.74
ENCINO LANDSCAPE, INC.   $2,044,475.40 4
26.01% | $422,006.87
24.88% | $407,330.00
1.23% | $24,855.48
FNH CONSTRUCTION, LLC   $2,094,188.00 5
29.07% | $471,719.47
27.92% | $457,042.60
2.43% | $49,712.60

Bid Items

Items: 51, 0 filtered
BOWIE SH 93  |  ATLANTA  |  0945-01-042  |  12/04/2019  |  $1,622,469  |  STP 2020(064)  |  PED  |  268 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate J.R. POPE COMPANY, INC. TI-ZACK CONCRETE, INC. EAST TEXAS BRIDGE, INC. ENCINO LANDSCAPE, INC. FNH CONSTRUCTION, LLC
104 6017 REMOVING CONC (DRIVEWAYS) SY 2,653.000 $20.000 $20.000 $20.000 $15.000 $20.000 $20.000
104 6023 REMOVING CONC (CTB) LF 120.000 $9.800 $50.000 $15.000 $40.000 $20.000 $100.000
104 6029 REMOVING CONC (CURB OR CURB & GUTTER) LF 2,792.000 $20.000 $10.000 $10.000 $9.000 $20.000 $20.000
104 6036 REMOVING CONC (SIDEWALK OR RAMP) SY 98.000 $11.200 $20.000 $25.000 $15.000 $20.000 $50.000
132 6001 EMBANKMENT (FINAL)(ORD COMP)(TY A) CY 186.000 $9.300 $38.000 $45.000 $40.000 $50.000 $35.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 8,380.000 $1.100 $5.000 $4.000 $3.000 $5.000 $6.000
162 6002 BLOCK SODDING SY 8,380.000 $5.000 $5.000 $4.500 $5.000 $5.000 $6.000
164 6055 BONDED FBR MTRX SEED (TEMP)(WARM) SY 8,380.000 $0.600 $1.000 $1.000 $0.750 $0.750 $2.000
168 6001 VEGETATIVE WATERING MG 134.540 $27.240 $50.000 $40.000 $18.000 $10.000 $50.000
423 6008 RETAINING WALL (CAST - IN - PLACE) SF 838.000 $66.250 $50.000 $47.000 $85.000 $120.000 $85.000
432 6001 RIPRAP (CONC)(4 IN) CY 8.000 $405.400 $800.000 $900.000 $550.000 $500.000 $550.000
432 6003 RIPRAP (CONC)(6 IN) CY 4.000 $554.950 $800.000 $900.000 $550.000 $600.000 $650.000
450 6030 RAIL (TY C221) LF 449.000 $62.790 $157.000 $145.000 $200.000 $150.000 $185.000
450 6048 RAIL (HANDRAIL)(TY B) LF 60.000 $122.800 $96.000 $115.000 $120.000 $150.000 $185.000
500 6001 MOBILIZATION LS 1.000 $142,000.000 $150,000.000 $144,000.000 $180,000.000 $160,000.000 $200,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 18.000 $2,500.000 $3,000.000 $1,500.000 $6,000.000 $8,000.000 $8,500.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 6,806.000 $3.850 $2.000 $0.010 $3.200 $3.000 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 6,806.000 $2.240 $0.600 $0.010 $1.500 $1.000 $2.000
506 6042 BIODEG EROSN CONT LOGS (INSTL) (18") LF 1,798.000 $4.800 $5.400 $0.010 $7.000 $5.000 $18.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,798.000 $1.330 $1.500 $0.010 $2.500 $1.000 $12.000
529 6002 CONC CURB (TY II) LF 357.000 $17.000 $10.000 $35.000 $20.000 $20.000 $30.000
529 6008 CONC CURB & GUTTER (TY II) LF 1,815.000 $30.000 $30.000 $39.000 $40.000 $30.000 $35.000
530 6004 DRIVEWAYS (CONC) SY 2,804.000 $95.000 $75.000 $91.000 $100.000 $100.000 $85.000
531 6003 CONC SIDEWALKS (6") SY 7,704.000 $66.570 $66.000 $91.000 $80.000 $80.000 $65.000
531 6004 CURB RAMPS (TY 1) EA 7.000 $1,439.850 $1,500.000 $1,400.000 $2,500.000 $1,500.000 $2,000.000
531 6006 CURB RAMPS (TY 3) EA 8.000 $1,925.950 $1,800.000 $1,400.000 $2,500.000 $1,800.000 $2,000.000
531 6009 CURB RAMPS (TY 6) EA 16.000 $2,113.500 $1,800.000 $1,400.000 $2,500.000 $2,500.000 $2,000.000
531 6010 CURB RAMPS (TY 7) EA 19.000 $1,510.700 $1,500.000 $1,400.000 $2,500.000 $1,800.000 $2,000.000
531 6013 CURB RAMPS (TY 10) EA 7.000 $1,848.950 $1,500.000 $1,400.000 $2,500.000 $1,800.000 $2,000.000
531 6032 CONC SIDEWALKS (SPECIAL) (TYPE A) SY 34.000 $190.490 $150.000 $225.000 $500.000 $160.000 $75.000
531 6033 CONC SIDEWALKS (SPECIAL) (TYPE B) SY 445.000 $107.170 $80.000 $200.000 $160.000 $180.000 $85.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 150.000 $2.900 $10.000 $11.000 $4.000 $4.000 $3.000
624 6009 GROUND BOX TY D (162922) EA 2.000 $990.900 $900.000 $450.000 $1,000.000 $800.000 $850.000
624 6028 REMOVE GROUND BOX EA 2.000 $158.950 $300.000 $50.000 $500.000 $300.000 $250.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 9.000 $539.000 $700.000 $350.000 $1,000.000 $500.000 $650.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 1.000 $1,081.560 $870.000 $350.000 $1,000.000 $750.000 $650.000
644 6060 IN SM RD SN SUP&AM TYTWT(1)WS(P) EA 9.000 $585.600 $510.000 $350.000 $700.000 $500.000 $650.000
644 6068 RELOCATE SM RD SN SUP&AM TY 10BWG EA 14.000 $493.870 $780.000 $350.000 $700.000 $500.000 $450.000
644 6070 RELOCATE SM RD SN SUP&AM TY S80 EA 1.000 $497.680 $900.000 $350.000 $700.000 $500.000 $450.000
644 6071 RELOCATE SM RD SN SUP&AM TY TWT EA 2.000 $377.500 $540.000 $350.000 $700.000 $500.000 $450.000
644 6076 REMOVE SM RD SN SUP&AM EA 25.000 $96.300 $120.000 $100.000 $275.000 $100.000 $150.000
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 1,014.000 $5.900 $14.400 $9.000 $16.500 $7.000 $20.000
666 6230 PAVEMENT SEALER 24" LF 1,014.000 $1.910 $3.600 $1.000 $2.500 $4.000 $20.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 186.000 $1.000 $3.600 $1.000 $5.000 $1.000 $2.000
677 6003 ELIM EXT PAV MRK & MRKS (8") LF 601.000 $1.520 $6.000 $1.500 $9.000 $5.000 $6.000
677 6007 ELIM EXT PAV MRK & MRKS (24") LF 938.000 $4.300 $7.200 $1.500 $12.000 $5.000 $6.000
678 6008 PAV SURF PREP FOR MRK (24") LF 1,014.000 $2.200 $3.600 $0.500 $2.500 $2.000 $6.000
690 6030 REMOVAL OF PEDESTRIAN PUSH BUTTONS EA 14.000 $65.900 $150.000 $50.000 $115.000 $100.000 $500.000
690 6032 INSTALL OF PEDESTRIAN PUSH BUTTONS EA 14.000 $300.000 $900.000 $250.000 $275.000 $900.000 $1,850.000
6185 6002 TMA (STATIONARY) DAY 350.000 $210.000 $250.000 $25.000 $175.000 $250.000 $350.000
6185 6005 TMA (MOBILE OPERATION) DAY 14.000 $32.500 $250.000 $25.000 $100.000 $250.000 $850.000
Totals: $1,622,468.53 $1,637,145.40 $1,732,104.18 $2,019,619.92 $2,044,475.40 $2,094,188.00