BOWIE US 67 (0010-13-092)

Items: 25

County: BOWIE
Length: N/A
Highway: US 67
District: ATLANTA
Control Number: 0010-13-092
DBE Goal: N/A
Project: NH 2019(260)
Guaranty: N/A
Time: 26 WORKING DAYS
Engineer's Estimate: $698,054.02
Date: 12/05/2018 (7 years ago)
Contract Number: N/A
Type: PLANING, SURFACING & PAV MRKS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$698,054.02
$761,772.13
Over/Under Est: 9.13% $63,718.11
$849,849.09
Over/Under Est: 21.75% $151,795.07
Amt Left: 11.56% $88,076.96
Over/Under Est: 25.05% $174,890.18
Amt Left: 14.59% $111,172.07
Delta: -2.72% -$23,095.11

Bid Items & Bid Tabulations

25 Total 0 of 25
BOWIE  |  US 67  |  ATLANTA  |  0010-13-092  |  12/05/2018  |  $698,054.02  |  NH 2019(260)  |  PLANING, SURF & PAV MRKS  |  26 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EAST TEXAS BRIDGE, INC.
RK HALL, LLC
LONGVIEW BRIDGE AND ROAD, LTD.
SUPERPAVE MIXTURES SP-C SAC-A PG76-22
TON 1,516.000 $120.000 $110.000 $145.580 $115.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 2,494.000 $125.000 $173.000 $177.540 $185.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")
SY 150.000 $15.000 $35.000 $43.940 $50.000
PLANE ASPH CONC PAV (2")
SY 36,457.000 $1.000 $1.250 $1.860 $1.700
MOBILIZATION
LS 1.000 $65,000.000 $45,000.000 $57,416.090 $80,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $6,000.000 $6,000.000 $1,636.740 $6,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 1.000 $650.000 $1,200.000 $1,080.000 $1,650.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 3,924.000 $0.280 $0.850 $0.590 $1.650
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 3,532.000 $0.200 $1.100 $1.440 $1.400
PREFAB PAV MRK TY C (W) (8") (SLD)
LF 1,036.000 $50.000 $5.500 $7.560 $5.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 636.000 $11.000 $16.500 $14.040 $13.750
PREFAB PAV MRK TY C (W) (ARROW)
EA 4.000 $200.000 $265.000 $291.600 $220.000
PREFAB PAV MRK TY C (W) (WORD)
EA 2.000 $265.000 $265.000 $410.400 $330.000
PREFAB PAV MRK TY C (Y) (24") (SLD)
LF 110.000 $11.000 $16.500 $14.040 $13.750
REFL PAV MRKR TY I-A
EA 50.000 $2.750 $4.600 $5.400 $5.500
REFL PAV MRKR TY I-C
EA 8.000 $3.100 $4.600 $5.400 $5.500
REFL PAV MRKR TY II-C-R
EA 130.000 $3.300 $4.600 $5.400 $5.500
ELIM EXT PAV MRK & MRKS (8")
LF 280.000 $0.620 $1.100 $2.160 $2.200
ELIM EXT PAV MRK & MRKS (24")
LF 378.000 $2.750 $2.200 $3.240 $4.400
REFL PAV MRK AWT (W) 4" (SLD) (100MIL)
LF 4,682.000 $0.250 $1.310 $0.810 $1.650
REFL PAV MRK AWT (W) 4" (BRK) (100MIL)
LF 2,607.000 $0.350 $1.310 $0.860 $1.650
REFL PAV MRK AWT (W) 4" (DOT) (100MIL)
LF 140.000 $1.000 $1.310 $1.400 $1.650
REFL PAV MRK AWT (Y) 4" (SLD) (100MIL)
LF 5,019.000 $0.450 $1.310 $0.810 $1.650
TMA (STATIONARY)
EA 1.000 $18,000.000 $8,000.000 $4,710.670 $20,000.000
TMA (MOBILE OPERATION)
HR 40.000 $15.000 $35.000 $116.220 $33.000
Totals: $698,054.020 $761,772.130 $849,849.090 $872,944.200