Job Info for 0386-02-026

County: BOSQUE Highway: SH 144 Date: 10/06/2023 (1 year ago) Engineer's Estimate: $5,257,068 Control Number: 0386-02-026
Project: F 2024(112) District: WACO Time: 90 WORKING DAYS Type: SURFACING/ROADWAY RESTORATION
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10
Plans: Plans | Revision | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $5,257,067.94
BIG CREEK CONSTRUCTION, LTD.   $4,557,803.14 1
-13.3% | -$699,264.80
TEXAS MATERIALS GROUP, INC.   $4,574,093.69 2
-12.99% | -$682,974.25
0.36% | $16,290.55
KNIFE RIVER CORPORATION - SOUTH   $4,579,854.86 3
-12.88% | -$677,213.08
0.48% | $22,051.72
0.13% | $5,761.17
NORTHEASTERN PAVERS, LLC   $4,600,469.49 4
-12.49% | -$656,598.45
0.94% | $42,666.35
0.45% | $20,614.63
Subcontractor Percentage Amount
STX CIVIL 5.41% $246,577.15
HJC FARMS, INC. 2.80% $127,618.49
D. I. J. CONSTRUCTION, INC. 2.44% $111,210.40
PROFESSIONAL TRAFFIC CONTROL LLC 0.32% $14,584.97
KING GEORGE TRAFFIC SOLUTIONS LLC 0.25% $11,394.51
NIXON ENGINEERING 0.14% $6,380.92
DALLAS LITE AND BARRICADE, INC. 0.00% $0.00
Total: 11.36% $517,766.44

Bid Items

Items: 57, 0 filtered
BOSQUE SH 144  |  WACO  |  0386-02-026  |  10/06/2023  |  $5,257,068  |  F 2024(112)  |  SURF/ROADWAY RESTOR  |  90 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate BIG CREEK CONSTRUCTION, LTD. TEXAS MATERIALS GROUP, INC. KNIFE RIVER CORPORATION - SOUTH NORTHEASTERN PAVERS, LLC
100 6002 PREPARING ROW STA 8.000 $1,219.100 $3,000.000 $1,950.000 $920.000 $1,100.000
134 6004 BACKFILL (TY A OR B) STA 300.000 $350.000 $250.000 $171.000 $190.000 $260.000
351 6004 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 20,027.000 $65.000 $63.000 $59.500 $59.000 $58.000
354 6188 PLANE ASPH CONC PAV(MICRO-MLLING)(1") SY 104,551.000 $1.500 $1.250 $1.650 $1.250 $2.000
400 6005 CEM STABIL BKFL CY 149.000 $188.350 $225.000 $300.000 $210.000 $305.000
400 6008 CUT & RESTORE ASPH PAVING SY 84.000 $102.200 $150.000 $150.000 $260.000 $210.000
402 6001 TRENCH EXCAVATION PROTECTION LF 122.000 $116.000 $15.000 $10.000 $21.000 $12.250
403 6001 TEMPORARY SPL SHORING SF 296.000 $64.800 $25.000 $80.000 $52.000 $20.000
432 6024 RIPRAP (STONE COMMON)(DRY)(12 IN) CY 16.700 $251.700 $300.000 $300.000 $210.000 $365.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 44.000 $497.300 $800.000 $675.000 $765.000 $825.000
462 6003 CONC BOX CULV (4 FT X 2 FT) LF 116.000 $401.350 $500.000 $500.000 $842.000 $610.000
462 6010 CONC BOX CULV (6 FT X 3 FT) LF 64.000 $627.600 $750.000 $750.000 $1,000.000 $915.000
466 6179 WINGWALL (PW - 1) (HW=4 FT) EA 2.000 $17,766.000 $25,000.000 $9,500.000 $8,400.000 $11,600.000
466 6180 WINGWALL (PW - 1) (HW=5 FT) EA 2.000 $21,278.000 $27,500.000 $11,000.000 $10,500.000 $13,500.000
496 6007 REMOV STR (PIPE) LF 202.000 $20.800 $25.000 $15.000 $63.000 $20.000
500 6001 MOBILIZATION LS 1.000 $468,369.810 $315,000.000 $340,600.000 $379,000.000 $405,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $7,000.000 $5,000.000 $2,500.000 $10,000.000 $7,250.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 900.000 $4.400 $5.000 $6.000 $9.750 $6.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 900.000 $1.600 $1.000 $1.000 $2.100 $3.000
510 6003 ONE-WAY TRAF CONT (PORT TRAF SIG) MO 1.000 $3,812.000 $7,500.000 $7,900.000 $8,500.000 $8,000.000
512 6013 PORT CTB (DES SOURCE)(SGL SLP)(TY 1) LF 240.000 $20.700 $50.000 $47.000 $48.000 $75.000
512 6025 PORT CTB (MOVE)(SGL SLP)(TY 1) LF 240.000 $11.500 $50.000 $47.000 $40.000 $30.000
512 6037 PORT CTB (STKPL)(SGL SLP)(TY 1) LF 240.000 $17.000 $50.000 $47.000 $46.000 $75.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 58,256.300 $0.200 $0.200 $0.160 $0.300 $0.250
533 6002 RUMBLE STRIPS (CENTERLINE) LF 29,128.150 $0.200 $0.200 $0.200 $0.300 $0.350
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 625.000 $34.800 $40.000 $26.500 $27.900 $35.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 2.000 $1,412.000 $1,500.000 $1,100.000 $1,150.000 $1,350.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 350.000 $2.200 $5.000 $3.000 $3.150 $3.750
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 2.000 $3,150.000 $3,500.000 $2,800.000 $2,950.000 $3,500.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 2.000 $286.000 $500.000 $250.000 $265.000 $310.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 2.000 $2,015.000 $2,500.000 $1,650.810 $3,000.000 $2,500.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 2.000 $1,600.000 $1,500.000 $1,239.470 $1,150.000 $2,000.000
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 2.000 $5,000.000 $7,500.000 $8,736.000 $7,500.000 $10,000.000
644 6060 IN SM RD SN SUP&AM TYTWT(1)WS(P) EA 7.000 $433.000 $800.000 $775.000 $1,000.000 $625.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 6.000 $40.000 $50.000 $45.000 $50.000 $55.000
658 6099 INSTL OM ASSM (OM-2Z)(WFLX)GND EA 4.000 $84.000 $150.000 $125.000 $100.000 $90.000
662 6004 WK ZN PAV MRK NON-REMOV (W)4"(SLD) LF 1,200.000 $0.750 $2.000 $0.550 $2.110 $0.550
662 6012 WK ZN PAV MRK NON-REMOV (W)8"(SLD) LF 406.000 $0.750 $1.000 $1.000 $1.050 $1.000
662 6016 WK ZN PAV MRK NON-REMOV (W)24"(SLD) LF 112.000 $4.300 $2.000 $8.000 $2.110 $8.000
662 6032 WK ZN PAV MRK NON-REMOV (Y)4"(BRK) LF 10,860.000 $0.550 $0.500 $0.650 $0.470 $0.650
662 6034 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) LF 57,920.000 $0.450 $0.500 $0.550 $0.470 $0.550
662 6109 WK ZN PAV MRK SHT TERM (TAB)TY W EA 102.000 $1.600 $1.500 $0.900 $1.450 $1.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 3,081.000 $1.600 $1.500 $0.900 $1.450 $1.000
666 6036 REFL PAV MRK TY I (W)8"(SLD)(100MIL) LF 203.000 $1.100 $1.000 $1.000 $1.050 $1.000
666 6048 REFL PAV MRK TY I (W)24"(SLD)(100MIL) LF 56.000 $11.050 $40.000 $7.400 $31.590 $7.400
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 58,100.000 $0.900 $0.800 $0.680 $0.760 $0.680
666 6318 RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL) LF 5,430.000 $1.000 $0.800 $0.750 $0.760 $0.750
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 28,960.000 $0.950 $0.800 $0.680 $0.760 $0.680
672 6009 REFL PAV MRKR TY II-A-A EA 657.000 $7.750 $5.000 $5.000 $5.250 $5.000
672 6010 REFL PAV MRKR TY II-C-R EA 13.000 $6.750 $15.000 $5.000 $12.500 $5.000
3076 6043 D-GR HMA TY-D PG70-22 (LEVEL-UP) TON 5,747.000 $135.000 $120.000 $142.000 $130.000 $122.000
3077 6023 SP MIXES SP-C SAC-B PG70-22 TON 11,505.000 $150.000 $110.000 $121.000 $119.000 $122.000
3077 6075 TACK COAT GAL 10,452.000 $4.000 $3.500 $3.050 $0.010 $0.010
3085 6001 UNDERSEAL COURSE GAL 26,135.000 $3.100 $4.000 $0.010 $0.010 $0.010
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $11,772.000 $7,500.000 $10,000.000 $15,000.000 $15,000.000
6185 6002 TMA (STATIONARY) DAY 90.000 $150.000 $275.000 $261.000 $500.000 $0.010
6185 6003 TMA (MOBILE OPERATION) HR 360.000 $70.000 $50.000 $20.000 $1.000 $0.010
Totals: $5,257,067.94 $4,557,803.14 $4,574,093.70 $4,579,854.87 $4,600,469.50