Job Info for 6397-45-001

County: BEXAR Highway: IH0010 Date: 03/16/2022 (2 years ago) Engineer's Estimate: $266,000 Control Number: 6397-45-001
Project: MMC - 639745001 District: SAN ANTONIO Time: 120 CALENDAR DAYS Type: DENSE GRADED HOT MIX

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $266,000.00
VULCAN CONSTRUCTION MATERIALS, LLC   $332,800.00 1
25.11% | $66,800.00
COLORADO MATERIALS, LTD.   $372,000.00 2
39.85% | $106,000.00
11.78% | $39,200.00
LONE STAR PAVING COMPANY   $394,350.00 3
48.25% | $128,350.00
18.49% | $61,550.00
6.01% | $22,350.00

Bid Items

Items: 4, 0 filtered
BEXAR IH0010  |  SAN ANTONIO  |  6397-45-001  |  03/16/2022  |  $266,000  |  MMC - 639745001  |  DENSE GRADED HOT MIX  |  120 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate VULCAN CONSTRUCTION MATERIALS, LLC COLORADO MATERIALS, LTD. LONE STAR PAVING COMPANY
8011 6014 D-GR HMA(SQ)TY B PG 64-22 (PICKUP) TON 200.000 $50.000 $60.000 $65.000 $68.000
8011 6015 D-GR HMA(SQ)TY B PG 64-22(DELIVERY) TON 3,000.000 $60.000 $75.400 $85.000 $88.250
8011 6036 D-GR HMA (SQ) TY C PG 70-22 (DELIVERY) TON 1,000.000 $65.000 $81.400 $90.000 $100.000
8011 6037 D-GR HMA (SQ) TY C PG 70-22 (PICKUP) TON 200.000 $55.000 $66.000 $70.000 $80.000
Totals: $266,000.00 $332,800.00 $372,000.00 $394,350.00