BEXAR ALAMO PKWY N (0915-12-741)
Items: 105
County: BEXAR
Length: 0.7000 MILES
Highway: ALAMO PKWY N
District: SAN ANTONIO
Control Number: 0915-12-741
DBE Goal: 2.5%
Project: STP 2025(663)VRU
Guaranty: $18,000.00
Time: 95 WORKING DAYS
Engineer's Estimate: $878,040.82
Date: 04/03/2025 (1 year ago)
Contract Number: 4253029
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00184576
Contract Type: Federal
Project Description: INSTALL TRAFFIC SIGNAL, INSTALL ADVANCED WARNING SIGNALS AND SIGNS (INTERSECTION)
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DALE PICHA
ORLANDO GALLEGOS
BEXAR ALAMO PKWY N (0915-12-741)
Project Name: N/A
Project: STP 2025(663)VRU
Length: 0.2000 MILES
Project Type: CONSTRUCTION
Limits From: ALAMO PKWY FROM 0.1 MI N OF WILD PI
Limits To: 0.1 MI S OF WILD PINE/ROCKWALL MILL
Project Description: INSTALL TRAFFIC SIGNAL, INSTALL ADVANCED WARNING SIGNALS AND SIGNS (INTERSECTION)
BEXAR JARRATT RD (0915-12-750)
Project Name: 2024 HSIP-BEXAR COUNTY-VARIOUS
Project: STP 2025(661)HES
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: JARRATT RD FROM 0.1 MI W OF EDWARDS RD
Limits To: TO 0.1 MI EAST OF EDWARDS RD
Project Description: INSTALL ADVANCED WARNING SIGNS (CURVE), INSTALL LED FLASHING CHEVRONS (CURVE)
BEXAR FOWLER RD (0915-12-744)
Project Name: 2024 HSIP - BEXAR COUNTY-CR5673
Project: STP 2025(662)HRR
Length: 0.5000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: FOWLER RD FROM .05MI W OF HERMOSA VALLEY
Limits To: 0.2 MI EAST OF HERMOSA VALLEY
Project Description: INSTALL ADVANCED WARNING SIGNS (CURVE), INSTALL CHEVRONS (CURVE)
BEXAR WALZEM RD (0915-12-745)
Project Name: 2024 HSIP-BEXAR COUNTY
Project: STP 2025(664)VRU
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: WALZEM RD FROM 0.1 MI NORTH OF ELM TRL
Limits To: 0.1 MI SOUTH OF ELM TRL
Project Description: IMPROVE TRAFFIC SIGNALS
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$878,040.82 | |||
| $689,689.00 |
-21.45%
-$188,351.82
|
|||
| $818,268.48 |
-6.81%
-$59,772.34
|
18.64%
$128,579.48
|
||
| $834,148.17 |
-5%
-$43,892.65
|
20.95%
$144,459.17
|
-1.94%
-$15,879.69
|
E
Engineer's Estimate
$878,040.82
1
Awarded
$689,689.00
Over/Under Est:
-21.45%
-$188,351.82
$818,268.48
Over/Under Est:
-6.81%
-$59,772.34
Amt Left:
18.64%
$128,579.48
$834,148.17
Over/Under Est:
-5%
-$43,892.65
Amt Left:
20.95%
$144,459.17
Delta:
-1.94%
-$15,879.69
| Subcontractor | Percentage | Amount |
|---|---|---|
| LOZANO CONSTRUCTION COMPANY, INC. | 0.00% | $0.00 |
| M & M STRIPING & POWER WASHING, LLC | 0.00% | $0.00 |
| SOUTH TEXAS TRAFFIC ALLIANCE INC. | 0.00% | $0.00 |
| Total: | 0.00% | $0.00 |
Bid Items & Bid Tabulations
105
Total
0 of 105
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| Total: | $3,000.00 |