Bid Cobra

BEXAR VA (0915-00-238)

Items: 33

County: BEXAR
Length: N/A
Highway: VA
District: SAN ANTONIO
Control Number: 0915-00-238
DBE Goal: N/A
Project: C 915-00-238
Guaranty: N/A
Time: 290 WORKING DAYS
Engineer's Estimate: $2,174,551.20
Date: 05/05/2022 (4 years ago)
Contract Number: N/A
Type: PURCHASE AND INSTALL SIGNS & EQUIP
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$2,174,551.20
$1,675,784.44
Over/Under Est: -22.94% -$498,766.76
$2,163,531.45
Over/Under Est: -0.51% -$11,019.75
Amt Left: 29.11% $487,747.01
Over/Under Est: 15.76% $342,688.80
Amt Left: 50.21% $841,455.56
Delta: -16.35% -$353,708.55
Subcontractor Percentage Amount
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. 13.84% $304,868.62
FLASHER EQUIPMENT COMPANY 4.80% $105,734.78
ENVIRONMENTAL SAFETY SERVICES, INC. 0.67% $14,758.81
Total: 19.31% $425,362.21

Bid Items & Bid Tabulations

33 Total 0 of 33
BEXAR  |  VA  |  SAN ANTONIO  |  0915-00-238  |  05/05/2022  |  $2,174,551.20  |  C 915-00-238  |  PURCHASE AND INSTL SIGNS & EQUIP  |  290 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THE LEVY COMPANY, INC.
MICA CORPORATION
E-Z BEL CONSTRUCTION, LLC
DRILL SHAFT (36 IN)
LF 34.000 $253.000 $290.830 $454.000 $430.000
DRILL SHAFT (48 IN)
LF 26.000 $450.000 $428.980 $738.000 $780.000
DRILL SHAFT (SIGN MTS) (54 IN)
LF 31.000 $630.000 $488.670 $775.000 $950.000
RIPRAP (MOW STRIP)(4 IN)
CY 11.000 $600.000 $941.370 $1,298.000 $950.000
REMOV STR (DRILL SHAFT)
EA 6.000 $6,100.000 $2,025.890 $1,812.000 $2,300.000
MOBILIZATION
LS 1.000 $213,784.000 $125,191.260 $196,095.000 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 17.000 $8,600.000 $2,835.780 $11,577.000 $16,000.000
MTL W-BEAM GD FEN (TIM POST)
LF 125.000 $42.000 $62.320 $44.000 $50.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $2,200.000 $1,445.000 $1,600.000 $3,500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $3,800.000 $3,555.000 $4,000.000 $4,500.000
CONDT (RM) (1")
LF 60.000 $50.000 $21.690 $44.200 $70.000
CONDT (RM) (2")
LF 60.000 $60.000 $75.160 $58.200 $95.000
GROUND BOX TY D (162922)
EA 1.000 $1,800.000 $1,030.050 $2,830.000 $1,500.000
ALUMINUM SIGNS (TY O)
SF 873.000 $35.000 $27.850 $33.400 $50.000
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 3,633.000 $78.000 $47.920 $41.850 $50.000
REPLACE EXISTING ALUMINUM SIGNS(TY G)
SF 4,636.000 $78.000 $36.010 $35.950 $60.000
REPLACE EXISTING ALUMINUM SIGNS(TY O)
SF 11,950.000 $48.000 $50.180 $61.240 $60.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 39.000 $758.800 $875.920 $1,282.000 $925.000
IN SM RD SN SUP&AM (RAIL MOUNT)
EA 10.000 $5,200.000 $3,551.340 $7,865.000 $3,750.000
REMOVE SM RD SN SUP&AM
EA 1.000 $115.000 $154.570 $682.000 $175.000
REMOVE LRSA
EA 1.000 $1,300.000 $1,146.090 $1,812.000 $1,750.000
INS OH SN SUP(30 FT BAL TEE)
EA 1.000 $43,800.000 $35,381.190 $35,660.000 $50,000.000
INS OH SN SUP(30 FT CANT)
EA 1.000 $31,100.000 $32,616.830 $32,360.000 $45,000.000
INS OH SN SUP(75 FT BRDG)
EA 1.000 $63,120.000 $56,713.970 $50,590.000 $75,000.000
INS OH SN SUP(80 FT BRDG)
EA 2.000 $55,000.000 $64,261.920 $66,470.000 $85,000.000
REMOVE OVERHD SIGN SUP
EA 2.000 $9,000.000 $6,682.470 $9,230.000 $18,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 102.000 $110.000 $121.350 $227.000 $115.000
FIBER OPTIC FUSION SPLICE
EA 2.000 $250.000 $281.660 $431.000 $650.000
FIBER OPTIC PATCH PANEL (6 POSITION)
EA 2.000 $2,800.000 $1,096.000 $1,315.000 $3,000.000
INSTALL DMS (POLE MTD CABINET)
EA 1.000 $24,300.000 $8,505.540 $29,205.000 $25,000.000
INSTALL DMS (FOUNDATION MTD CABINET)
EA 1.000 $16,080.000 $13,608.230 $33,340.000 $25,000.000
ETHERNET SWITCH (INSTALL ONLY)
EA 2.000 $510.000 $438.560 $2,275.000 $1,000.000
TMA (MOBILE OPERATION)
DAY 220.000 $250.000 $378.880 $419.000 $400.000
Totals: $2,174,551.200 $1,675,784.440 $2,163,531.450 $2,517,240.000