Bid Cobra

BEXAR VA (0915-00-223)

Items: 98

County: BEXAR
Length: N/A
Highway: VA
District: SAN ANTONIO
Control Number: 0915-00-223
DBE Goal: N/A
Project: STP 2019(905)
Guaranty: N/A
Time: 212 WORKING DAYS
Engineer's Estimate: $3,591,226.87
Date: 05/07/2019 (7 years ago)
Contract Number: N/A
Type: INTERSECTION OPERATIONAL IMPROVEMENTS-SOUTH
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$3,591,226.87
$3,461,234.91
Over/Under Est: -3.62% -$129,991.96
Over/Under Est: -3.51% -$125,905.62
Amt Left: 0.12% $4,086.34
$3,567,410.01
Over/Under Est: -0.66% -$23,816.86
Amt Left: 3.07% $106,175.10
Delta: -2.95% -$102,088.76
Over/Under Est: 0.63% $22,804.13
Amt Left: 4.41% $152,796.09
Delta: -1.31% -$46,620.99
Over/Under Est: 3.94% $141,364.15
Amt Left: 7.84% $271,356.11
Delta: -3.28% -$118,560.02
Over/Under Est: 13.37% $479,993.63
Amt Left: 17.62% $609,985.59
Delta: -9.07% -$338,629.48

Bid Items & Bid Tabulations

98 Total 0 of 98
BEXAR  |  VA  |  SAN ANTONIO  |  0915-00-223  |  05/07/2019  |  $3,591,226.87  |  STP 2019(905)  |  INTERS OPERATIONAL IMPRVS-SOUTH  |  212 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CAPITAL EXCAVATION COMPANY
CURRAN CONTRACTING COMPANY
RELMCO, INC.
ANGEL BROTHERS HOLDINGS CORP.
DEAN WORD COMPANY, LTD.
E-Z BEL CONSTRUCTION, LLC
PREPARING ROW
STA 105.100 $2,497.000 $1,370.000 $2,300.000 $850.000 $700.000 $1,572.412 $1,300.000
EXCAVATION (ROADWAY)
CY 2,373.000 $9.200 $20.000 $12.000 $12.000 $16.800 $15.433 $22.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 5,258.000 $7.990 $30.000 $2.000 $15.000 $19.500 $20.811 $20.000
BLADING
HR 30.000 $134.850 $109.310 $107.000 $100.000 $130.000 $99.000 $140.000
COMPOST MANUF TOPSOIL (4")
SY 86,693.000 $1.250 $3.000 $1.500 $3.000 $1.150 $1.436 $3.500
BROADCAST SEED (PERM) (URBAN) (SANDY)
SY 86,693.000 $0.630 $0.180 $0.250 $0.150 $0.200 $0.168 $0.200
VEGETATIVE WATERING
MG 1.500 $23.470 $500.000 $48.000 $500.000 $785.000 $1,512.500 $400.000
PROOF ROLLING
HR 14.000 $86.310 $77.700 $84.000 $80.000 $95.000 $93.500 $68.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 5,778.000 $47.130 $65.000 $57.000 $62.000 $84.500 $74.170 $70.000
PRIME COAT(MC-30 OR AE-P)
GAL 6,596.000 $3.600 $4.000 $5.100 $4.200 $4.500 $6.138 $3.500
ASPH(AC-15P,AC-20-5TR,AC-20XP,AC10-2TR)
GAL 21,612.000 $2.830 $4.400 $4.900 $4.720 $4.500 $3.784 $4.000
AGGR (TY-PB GR-4)
CY 884.000 $94.840 $90.000 $150.250 $215.250 $135.000 $94.556 $85.000
SUPERPAVE MIXTURES SP-D SAC-B PG70-22
TON 5,248.000 $116.100 $105.000 $96.000 $93.450 $97.000 $96.146 $108.000
PLANE ASPH CONC PAV (1.5")
SY 31,933.000 $1.290 $3.000 $1.900 $2.100 $3.000 $3.513 $2.500
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 198.000 $334.240 $167.180 $179.300 $322.500 $195.000 $315.000 $280.000
CMP AR (GAL STL DES 4)
LF 39.000 $109.060 $204.620 $160.700 $80.000 $150.000 $127.449 $148.000
CONC BOX CULV (3 FT X 2 FT)
LF 10.000 $200.440 $486.160 $1,800.000 $600.000 $680.000 $600.600 $415.000
CONC BOX CULV (4 FT X 2 FT)
LF 22.000 $247.840 $264.650 $750.000 $600.000 $515.000 $454.367 $460.000
CONC BOX CULV (5 FT X 5 FT)
LF 19.000 $388.410 $369.280 $1,700.000 $650.000 $600.000 $526.103 $750.000
RC PIPE (CL III)(30 IN)
LF 32.000 $110.000 $254.710 $103.050 $180.000 $140.000 $124.646 $250.000
SET (TY I)(S=3 FT)(HW=2FT)(3:1)(C)
EA 2.000 $4,000.000 $5,129.820 $4,148.000 $4,250.000 $5,000.000 $4,396.487 $2,900.000
SET (TY I)(S= 4 FT)(HW= 2 FT)(3:1) (C)
EA 2.000 $5,891.810 $5,379.360 $6,407.650 $5,500.000 $5,600.000 $4,977.263 $3,800.000
SET (TY I)(S= 5 FT)(HW= 5 FT)(3:1) (C)
EA 2.000 $8,500.000 $6,754.860 $9,198.450 $6,500.000 $8,000.000 $6,991.950 $6,300.000
SET (TY II) (30 IN) (RCP) (3: 1) (P)
EA 2.000 $2,500.000 $1,808.330 $1,607.750 $1,800.000 $3,500.000 $2,984.625 $3,100.000
SET (TY II) (DES 4) (CMP) (3: 1) (C)
EA 6.000 $2,026.670 $1,688.310 $1,279.500 $1,250.000 $2,725.000 $2,415.000 $4,500.000
REMOV STR (WINGWALL)
EA 6.000 $1,750.000 $1,273.580 $315.200 $900.000 $1,150.000 $1,010.625 $1,500.000
REMOV STR (HEADWALL)
EA 2.000 $1,100.000 $1,273.870 $235.650 $900.000 $1,150.000 $1,010.625 $1,500.000
MOBILIZATION
LS 1.000 $312,990.330 $340,000.000 $340,000.000 $350,000.000 $385,000.000 $367,734.746 $390,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $8,315.750 $7,000.000 $10,000.000 $9,500.000 $6,000.000 $11,739.457 $3,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 720.000 $20.350 $13.850 $37.000 $14.000 $43.850 $11.550 $37.040
CONSTRUCTION EXITS (REMOVE)
SY 720.000 $7.170 $4.750 $6.100 $6.000 $18.300 $2.100 $15.430
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,500.000 $2.380 $2.530 $3.200 $2.750 $5.700 $2.363 $4.800
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,500.000 $0.640 $0.510 $1.600 $0.600 $1.800 $1.050 $1.510
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 720.000 $3.700 $7.680 $4.250 $6.500 $9.450 $4.725 $7.970
BIODEG EROSN CONT LOGS (REMOVE)
LF 720.000 $1.470 $1.520 $1.600 $2.500 $3.000 $1.313 $2.510
CONSTRUCTING DETOURS
SY 3,058.000 $44.670 $40.000 $34.650 $38.000 $38.350 $41.888 $40.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 330.000 $87.910 $129.500 $88.000 $95.000 $75.000 $56.100 $50.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 9,690.000 $33.170 $9.630 $26.650 $18.000 $25.000 $29.700 $65.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 7,450.000 $4.790 $6.540 $10.000 $10.000 $9.000 $9.900 $10.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 9,690.000 $6.530 $9.630 $10.050 $16.000 $11.000 $15.400 $10.000
DRIVEWAYS (ACP)
SY 208.000 $43.560 $89.300 $175.000 $80.000 $132.000 $47.630 $70.000
CRASH CUSH ATTEN (INSTL)
EA 28.000 $11,996.860 $8,192.400 $6,000.000 $7,000.000 $8,000.000 $6,667.500 $6,350.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 20.000 $1,491.200 $854.720 $851.250 $900.000 $1,300.000 $840.000 $800.000
CRASH CUSH ATTEN (REMOVE)
EA 28.000 $815.040 $314.800 $573.900 $600.000 $600.000 $210.000 $200.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 2.000 $185.000 $200.000 $212.200 $241.870 $275.000 $236.250 $225.000
CONDT (PVC) (SCH 80) (2")
LF 190.000 $14.090 $14.640 $15.150 $17.200 $17.000 $16.800 $20.000
CONDT (PVC) (SCH 80) (3")
LF 340.000 $20.810 $15.260 $15.800 $18.270 $17.500 $17.850 $21.000
ELEC CONDR (NO.6) BARE
LF 1,522.000 $1.490 $1.090 $1.100 $1.230 $1.250 $1.208 $1.750
TRAY CABLE (4 CONDR) (12 AWG)
LF 1,386.000 $2.750 $1.610 $1.650 $2.680 $1.900 $2.625 $2.500
GROUND BOX TY A (122311)W/APRON
EA 9.000 $2,008.500 $725.130 $750.050 $833.120 $840.000 $813.750 $750.000
GROUND BOX TY D (162922)W/APRON
EA 4.000 $1,037.000 $926.160 $958.000 $1,021.250 $1,100.000 $997.500 $900.000
ZINC-COAT STL WIRE STRAND (3/16")
LF 1,471.000 $3.830 $4.810 $5.000 $4.300 $5.550 $4.200 $2.000
ZINC-COAT STL WIRE STRAND (5/16")
LF 1,471.000 $3.890 $4.820 $5.000 $4.300 $5.550 $4.200 $2.250
REMOVE ELECTRICAL SERVICES
EA 1.000 $515.000 $1,146.670 $1,186.050 $430.000 $1,325.000 $420.000 $600.000
ELC SRV TY D 120/240 070(NS)AL(E)TP(O)
EA 4.000 $5,910.170 $4,200.000 $4,344.350 $3,762.500 $4,850.000 $3,675.000 $4,800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 25.000 $524.080 $568.000 $602.600 $510.620 $560.000 $498.750 $475.000
RELOCATE SM RD SN SUP&AM TY S80
EA 43.000 $495.760 $400.000 $424.350 $456.870 $500.000 $446.250 $425.000
REMOVE SM RD SN SUP&AM
EA 1.000 $77.670 $100.000 $156.100 $104.270 $115.000 $101.850 $97.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 24.000 $69.150 $53.840 $57.100 $55.900 $61.600 $54.600 $52.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 25,299.000 $0.540 $0.520 $0.800 $0.670 $0.600 $0.662 $0.650
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 25,104.000 $0.580 $0.520 $0.800 $0.670 $0.600 $0.662 $0.650
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,883.000 $1.010 $1.010 $1.800 $6.000 $0.700 $2.475 $1.850
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 13,305.000 $0.880 $0.910 $1.000 $0.820 $1.100 $0.809 $0.790
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 108.000 $5.790 $6.520 $6.350 $8.600 $7.650 $8.400 $8.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 19.000 $121.740 $123.230 $122.000 $164.570 $145.000 $143.850 $137.000
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
EA 12.000 $475.000 $328.280 $265.200 $405.270 $385.000 $395.850 $377.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 19.000 $153.590 $156.570 $159.150 $164.570 $185.000 $160.650 $153.000
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 10.000 $57.970 $45.460 $26.500 $47.300 $53.000 $46.200 $44.000
REFL PAV MRK TY I(Y)(MED NOSE)(100MIL)
EA 4.000 $335.840 $459.600 $424.350 $369.800 $540.000 $361.200 $344.000
PAVEMENT SEALER 4"
LF 44,545.000 $0.180 $0.160 $0.200 $0.180 $0.200 $0.179 $0.170
PAVEMENT SEALER 8"
LF 13,305.000 $0.270 $0.290 $0.400 $0.430 $0.350 $0.420 $0.400
PAVEMENT SEALER 24"
LF 108.000 $2.820 $3.030 $3.200 $3.580 $3.550 $3.497 $3.300
PAVEMENT SEALER (ARROW)
EA 19.000 $45.000 $55.560 $58.350 $67.720 $65.000 $66.150 $63.000
PAVEMENT SEALER (WORD)
EA 19.000 $47.850 $78.790 $68.950 $67.720 $92.450 $66.150 $63.000
PAVEMENT SEALER (MED NOSE)
EA 4.000 $149.040 $227.270 $159.150 $262.300 $265.000 $256.200 $244.000
PAVEMENT SEALER (LNDP ARROW)
EA 12.000 $142.000 $156.570 $132.600 $142.970 $185.000 $139.650 $133.000
PAVEMENT SEALER (YLD TRI)
EA 10.000 $16.000 $10.100 $15.900 $35.470 $11.850 $34.650 $33.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 19,445.000 $0.480 $0.380 $0.550 $0.430 $0.450 $0.420 $0.400
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 25,100.000 $0.520 $0.380 $0.550 $0.430 $0.450 $0.420 $0.400
REFL PAV MRKR TY I-C
EA 671.000 $3.630 $4.800 $5.300 $4.510 $5.500 $4.410 $4.200
REFL PAV MRKR TY II-A-A
EA 1,191.000 $3.360 $4.800 $5.300 $4.050 $5.500 $3.959 $3.800
ELIM EXT PAV MRK & MRKS (4")
LF 14,455.000 $0.460 $0.480 $0.550 $0.570 $0.600 $0.557 $0.530
PAV SURF PREP FOR MRK (4")
LF 44,545.000 $1.000 $0.050 $0.010 $0.110 $0.100 $0.105 $0.100
PAV SURF PREP FOR MRK (8")
LF 13,305.000 $1.000 $0.050 $0.020 $0.250 $0.100 $0.252 $0.240
PAV SURF PREP FOR MRK (24")
LF 108.000 $1.430 $0.510 $0.050 $2.150 $0.600 $2.100 $2.000
PAV SURF PREP FOR MRK (ARROW)
EA 31.000 $35.000 $10.100 $5.300 $59.120 $12.000 $57.750 $55.000
PAV SURF PREP FOR MRK (WORD)
EA 19.000 $50.000 $10.100 $5.300 $59.120 $12.000 $57.750 $55.000
PAV SURF PREP FOR MRK (36")(YLD TRI)
EA 10.000 $30.000 $5.050 $2.100 $23.650 $6.000 $23.100 $22.000
PAV SURF PREP FOR MRK (MED NOSE)
EA 3.000 $75.000 $35.350 $15.900 $154.800 $42.000 $151.200 $144.000
INSTALL HWY TRF SIG (FLASH BEACON)
EA 4.000 $4,932.570 $5,432.820 $5,619.500 $7,525.000 $6,300.000 $7,350.000 $2,600.000
REMOVING TRAFFIC SIGNALS
EA 1.000 $4,154.550 $1,847.180 $1,910.650 $5,375.000 $2,135.000 $5,250.000 $2,250.000
VEH SIG SEC (12")LED(YEL)
EA 28.000 $250.260 $295.380 $305.550 $247.250 $340.000 $241.500 $250.000
VEH SIG SEC (12")LED(RED)
EA 16.000 $223.910 $295.380 $305.550 $247.250 $340.000 $241.500 $250.000
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
LF 2,942.000 $2.050 $1.280 $1.350 $2.410 $1.500 $2.363 $2.150
INS TRF SIG PL AM (S)STR(TY B)
EA 8.000 $4,000.000 $3,816.410 $3,947.550 $4,837.500 $4,400.000 $4,725.000 $5,000.000
INS TRF SIG PL AM (S)STR(TY B)LUM
EA 7.000 $4,590.150 $5,205.130 $5,384.000 $6,450.000 $6,000.000 $6,300.000 $6,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 8.000 $79.230 $130.100 $38.000 $500.000 $175.000 $1,100.000 $425.000
TMA (MOBILE OPERATION)
DAY 116.000 $196.000 $354.550 $294.000 $200.000 $355.000 $660.000 $625.000
Totals: $3,591,226.875 $3,461,234.910 $3,465,321.250 $3,567,410.010 $3,614,031.000 $3,732,591.197 $4,071,220.500