PREPARING ROW
|
STA
|
98.100
|
$1,500.000
|
$700.000
|
$1,200.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
2,447.000
|
$9.200
|
$18.000
|
$40.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
246.000
|
$7.990
|
$50.000
|
$30.000
|
|
|
BLADING
|
HR
|
9.000
|
$163.830
|
$150.000
|
$200.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
10,877.000
|
$1.250
|
$5.000
|
$2.500
|
|
|
BROADCAST SEED (PERM) (URBAN) (SANDY)
|
SY
|
10,877.000
|
$0.630
|
$0.450
|
$0.250
|
|
|
VEGETATIVE WATERING
|
MG
|
0.180
|
$23.470
|
$1,500.000
|
$1,000.000
|
|
|
PROOF ROLLING
|
HR
|
1.000
|
$86.310
|
$500.000
|
$200.000
|
|
|
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
|
CY
|
980.000
|
$47.130
|
$85.000
|
$90.000
|
|
|
LIME (HYDRATED LIME (SLURRY))
|
TON
|
26.000
|
$132.210
|
$300.000
|
$400.000
|
|
|
LIME TRT (SUBGRADE)(8")
|
SY
|
349.000
|
$3.100
|
$15.000
|
$10.000
|
|
|
LIME TRT (SUBGRADE)(6")
|
SY
|
839.000
|
$5.250
|
$15.000
|
$10.000
|
|
|
CEMENT
|
TON
|
0.400
|
$136.330
|
$5,000.000
|
$1,000.000
|
|
|
CEMENT TREAT (SUBGRADE)(6")
|
SY
|
32.000
|
$2.170
|
$50.000
|
$10.000
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
551.000
|
$3.600
|
$8.000
|
$4.000
|
|
|
ASPH(AC-15P,AC-20-5TR,AC-20XP,AC10-2TR)
|
GAL
|
11,902.000
|
$2.830
|
$5.000
|
$4.000
|
|
|
AGGR (TY-PB GR-4)
|
CY
|
491.000
|
$94.840
|
$150.000
|
$100.000
|
|
|
D-GR HMA(SQ) TY-B PG64-22
|
TON
|
2,793.000
|
$94.470
|
$85.000
|
$100.000
|
|
|
SUPERPAVE MIXTURES SP-D SAC-B PG70-22
|
TON
|
3,874.000
|
$81.990
|
$121.000
|
$115.000
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
30,896.000
|
$1.250
|
$3.460
|
$3.500
|
|
|
DRILL SHAFT (54 IN)
|
LF
|
25.000
|
$157.700
|
$483.750
|
$1,000.000
|
|
|
DRILL SHAFT (SIGN MTS) (30 IN)
|
LF
|
23.000
|
$257.000
|
$215.000
|
$350.000
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
24.000
|
$166.000
|
$215.000
|
$350.000
|
|
|
DRILL SHAFT (TRF SIG POLE) (24 IN)
|
LF
|
5.700
|
$168.980
|
$188.120
|
$200.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
12.400
|
$670.970
|
$2,500.000
|
$1,800.000
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
20.000
|
$424.180
|
$1,500.000
|
$1,200.000
|
|
|
CL C CONC (COLLAR)
|
EA
|
2.000
|
$1,173.900
|
$1,500.000
|
$1,000.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
60.000
|
$389.290
|
$415.000
|
$800.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
19.000
|
$442.550
|
$435.000
|
$800.000
|
|
|
RAIL (TY T221)
|
LF
|
30.000
|
$126.640
|
$105.000
|
$1,000.000
|
|
|
RAIL (HANDRAIL)(TY D)
|
LF
|
49.000
|
$309.420
|
$145.920
|
$200.000
|
|
|
CONC BOX CULV (5 FT X 2 FT)
|
LF
|
14.000
|
$309.420
|
$800.000
|
$800.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
5.000
|
$62.320
|
$300.000
|
$150.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
16.000
|
$86.070
|
$300.000
|
$200.000
|
|
|
INLET (COMPL)(PCO)(3FT)(RIGHT)
|
EA
|
1.000
|
$5,606.090
|
$7,500.000
|
$10,000.000
|
|
|
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
|
EA
|
2.000
|
$4,968.420
|
$7,500.000
|
$12,500.000
|
|
|
WINGWALL (FW - S) (HW=3 FT)
|
EA
|
1.000
|
$6,658.040
|
$6,500.000
|
$12,000.000
|
|
|
REMOV STR (INLET)
|
EA
|
1.000
|
$801.000
|
$1,500.000
|
$500.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
1.000
|
$1,750.000
|
$1,500.000
|
$650.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$240,456.290
|
$245,000.000
|
$310,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
21.000
|
$8,315.750
|
$10,000.000
|
$10,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
30.000
|
$823.000
|
$40.000
|
$25.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
30.000
|
$8.010
|
$12.000
|
$10.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
640.000
|
$20.350
|
$16.000
|
$14.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
640.000
|
$7.170
|
$5.000
|
$6.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,225.000
|
$2.380
|
$4.000
|
$2.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,225.000
|
$0.640
|
$1.000
|
$0.500
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
320.000
|
$3.700
|
$8.000
|
$8.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
320.000
|
$1.470
|
$2.000
|
$2.000
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
2,980.000
|
$59.430
|
$18.000
|
$35.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
1,400.000
|
$42.740
|
$18.000
|
$25.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
260.000
|
$41.410
|
$18.000
|
$30.000
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
480.000
|
$6.440
|
$12.000
|
$12.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
1,140.000
|
$6.150
|
$12.000
|
$10.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
160.000
|
$9.350
|
$12.000
|
$10.000
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
2,980.000
|
$11.150
|
$12.000
|
$15.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
1,400.000
|
$10.190
|
$12.000
|
$10.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
260.000
|
$10.550
|
$12.000
|
$10.000
|
|
|
REMOVE AND RELAY PAVERS
|
SY
|
102.000
|
$66.670
|
$100.000
|
$140.000
|
|
|
CONC CURB (TY I)
|
LF
|
3,715.000
|
$14.670
|
$22.000
|
$25.000
|
|
|
CONC CURB (TY F3)
|
LF
|
49.000
|
$148.740
|
$125.000
|
$450.000
|
|
|
CONC CURB & GUTTER (ARMOR CURB)
|
LF
|
28.000
|
$270.390
|
$185.000
|
$300.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
134.000
|
$69.520
|
$75.000
|
$125.000
|
|
|
CONC SIDEWALKS (4")
|
SY
|
144.000
|
$49.980
|
$65.000
|
$90.000
|
|
|
CURB RAMPS (TY 6)
|
EA
|
1.000
|
$1,810.030
|
$1,800.000
|
$3,000.000
|
|
|
CONC MEDIAN
|
SY
|
3.000
|
$56.490
|
$300.000
|
$500.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
600.000
|
$20.720
|
$22.220
|
$21.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
2.000
|
$1,093.440
|
$1,199.000
|
$1,250.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
500.000
|
$2.010
|
$2.200
|
$1.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
3.000
|
$2,652.810
|
$3,003.000
|
$3,000.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
1.000
|
$192.360
|
$220.000
|
$75.000
|
|
|
CRASH CUSH ATTEN (INSTL)
|
EA
|
9.000
|
$14,745.250
|
$7,800.000
|
$7,000.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
6.000
|
$2,076.700
|
$1,500.000
|
$750.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
9.000
|
$1,087.150
|
$900.000
|
$250.000
|
|
|
RELOCATE RD IL ASM (SHOE-BASE)
|
EA
|
2.000
|
$1,392.720
|
$1,210.000
|
$2,000.000
|
|
|
RELOCATE RD IL ASM (TRANS-BASE)
|
EA
|
3.000
|
$2,812.780
|
$1,925.000
|
$3,000.000
|
|
|
IN RD IL (U/P) (TY 1) (150W EQ) LED
|
EA
|
8.000
|
$1,120.590
|
$1,650.000
|
$1,750.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
1,465.000
|
$9.060
|
$15.400
|
$13.000
|
|
|
CONDT (PVC) (SCH 80) (2")
|
LF
|
510.000
|
$14.090
|
$17.600
|
$10.000
|
|
|
CONDT (PVC) (SCH 80) (2") (BORE)
|
LF
|
90.000
|
$36.290
|
$55.000
|
$75.000
|
|
|
CONDT (RM) (1")
|
LF
|
270.000
|
$24.340
|
$18.700
|
$60.000
|
|
|
ELEC CONDR (NO.8) BARE
|
LF
|
1,250.000
|
$1.780
|
$1.210
|
$2.500
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
2,500.000
|
$1.600
|
$1.210
|
$2.500
|
|
|
ELEC CONDR (NO.6) BARE
|
LF
|
585.000
|
$1.490
|
$1.430
|
$2.500
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
1,150.000
|
$2.500
|
$1.430
|
$2.500
|
|
|
TRAY CABLE (4 CONDR) (12 AWG)
|
LF
|
500.000
|
$2.750
|
$2.200
|
$3.000
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
10.000
|
$2,008.500
|
$1,045.000
|
$1,600.000
|
|
|
ELC SRV TY A 240/480 060(NS)SS(E)SP(O)
|
EA
|
1.000
|
$6,256.450
|
$5,060.000
|
$8,000.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
27.000
|
$28.970
|
$23.100
|
$30.000
|
|
|
ALUMINUM SIGNS (TY O)
|
SF
|
2,711.100
|
$24.080
|
$24.200
|
$36.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
12.000
|
$524.080
|
$588.500
|
$650.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
18.000
|
$506.710
|
$423.500
|
$500.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
4.000
|
$77.670
|
$49.500
|
$200.000
|
|
|
REMOVE SM RD SN SUP&AM (SIGN ONLY)
|
EA
|
5.000
|
$77.670
|
$55.000
|
$125.000
|
|
|
RELOCATE LRSA
|
EA
|
1.000
|
$7,192.530
|
$2,750.000
|
$2,500.000
|
|
|
INS OH SN SUP(40 FT CANT)
|
EA
|
1.000
|
$25,000.000
|
$32,450.000
|
$45,000.000
|
|
|
INS OH SN SUP(40 FT CANT)(SPAN ONLY)
|
EA
|
1.000
|
$10.000
|
$21,010.000
|
$35,000.000
|
|
|
REMOVE OVERHD SIGN SUP
|
EA
|
1.000
|
$6,252.490
|
$5,500.000
|
$2,500.000
|
|
|
REMOVE OVERHD SIGN SUP (SIGN ONLY)
|
EA
|
5.000
|
$720.000
|
$660.000
|
$2,000.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
|
LF
|
1,790.000
|
$0.280
|
$1.650
|
$1.500
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
5,840.000
|
$0.330
|
$1.650
|
$1.500
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
2,390.000
|
$0.280
|
$1.650
|
$1.500
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
2,550.000
|
$0.430
|
$5.500
|
$5.000
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
1,026.000
|
$6.850
|
$0.550
|
$0.500
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
7,232.000
|
$0.880
|
$0.770
|
$0.700
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
445.000
|
$3.910
|
$2.560
|
$2.330
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
1,034.000
|
$5.790
|
$6.710
|
$6.100
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
30.000
|
$121.740
|
$165.000
|
$150.000
|
|
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
|
EA
|
7.000
|
$213.140
|
$206.800
|
$188.000
|
|
REFL PAV MRK TY I(W)(UTURN ARW)(100MIL)
|
EA
|
5.000
|
$171.210
|
$244.200
|
$222.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
32.000
|
$153.590
|
$165.000
|
$150.000
|
|
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
|
EA
|
35.000
|
$57.970
|
$55.000
|
$50.000
|
|
|
PAVEMENT SEALER 4"
|
LF
|
19,258.000
|
$0.180
|
$0.220
|
$0.200
|
|
|
PAVEMENT SEALER 8"
|
LF
|
7,232.000
|
$0.270
|
$0.440
|
$0.400
|
|
|
PAVEMENT SEALER 12"
|
LF
|
445.000
|
$0.730
|
$1.460
|
$1.330
|
|
|
PAVEMENT SEALER 24"
|
LF
|
1,034.000
|
$2.820
|
$3.410
|
$3.100
|
|
|
PAVEMENT SEALER (ARROW)
|
EA
|
30.000
|
$45.000
|
$69.300
|
$63.000
|
|
|
PAVEMENT SEALER (WORD)
|
EA
|
32.000
|
$47.850
|
$69.300
|
$63.000
|
|
|
PAVEMENT SEALER (DBL ARROW)
|
EA
|
7.000
|
$102.300
|
$102.300
|
$93.000
|
|
|
PAVEMENT SEALER (UTURN ARROW)
|
EA
|
5.000
|
$100.340
|
$122.100
|
$111.000
|
|
|
PAVEMENT SEALER (YLD TRI)
|
EA
|
35.000
|
$16.240
|
$36.300
|
$33.000
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
10,714.000
|
$0.460
|
$0.550
|
$0.500
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
3,031.000
|
$0.480
|
$0.550
|
$0.500
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
4,948.000
|
$0.520
|
$0.550
|
$0.500
|
|
REFL PAV MRKR TY I-C
|
EA
|
126.000
|
$3.630
|
$11.000
|
$10.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
8.000
|
$3.360
|
$16.500
|
$15.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
135.000
|
$4.530
|
$11.000
|
$10.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
11,005.000
|
$0.610
|
$0.730
|
$0.670
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
470.000
|
$2.130
|
$2.200
|
$2.000
|
|
|
ELIM EXT PAV MRK & MRKS (24")
|
LF
|
217.000
|
$20.000
|
$4.400
|
$4.000
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
1.000
|
$151.200
|
$73.700
|
$67.000
|
|
|
ELIM EXT PAV MRK & MRKS (WORD)
|
EA
|
1.000
|
$64.000
|
$73.700
|
$67.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
19,258.000
|
$1.000
|
$0.160
|
$0.150
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
7,232.000
|
$1.000
|
$0.270
|
$0.250
|
|
|
PAV SURF PREP FOR MRK (12")
|
LF
|
445.000
|
$0.520
|
$1.650
|
$1.500
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
1,034.000
|
$1.430
|
$2.200
|
$2.000
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
30.000
|
$840.000
|
$60.500
|
$55.000
|
|
|
PAV SURF PREP FOR MRK (DBL ARROW)
|
EA
|
7.000
|
$97.320
|
$82.500
|
$75.000
|
|
|
PAV SURF PREP FOR MRK (UTURN ARR)
|
EA
|
5.000
|
$26.620
|
$82.500
|
$75.000
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
32.000
|
$50.000
|
$60.500
|
$55.000
|
|
|
PAV SURF PREP FOR MRK (36")(YLD TRI)
|
EA
|
35.000
|
$30.000
|
$24.200
|
$22.000
|
|
|
INSTALL HWY TRF SIG (UPGRADE)
|
EA
|
4.000
|
$12,181.520
|
$2,821.500
|
$5,000.000
|
|
|
VEH SIG SEC (12")LED(GRN)
|
EA
|
1.000
|
$220.320
|
$242.000
|
$300.000
|
|
|
VEH SIG SEC (12")LED(GRN ARW)
|
EA
|
2.000
|
$227.490
|
$242.000
|
$300.000
|
|
|
VEH SIG SEC (12")LED(YEL)
|
EA
|
1.000
|
$250.260
|
$242.000
|
$300.000
|
|
|
VEH SIG SEC (12")LED(YEL ARW)
|
EA
|
2.000
|
$225.020
|
$242.000
|
$300.000
|
|
|
VEH SIG SEC (12")LED(RED)
|
EA
|
3.000
|
$223.910
|
$242.000
|
$300.000
|
|
|
BACK PLATE (12")(3 SEC)
|
EA
|
3.000
|
$90.150
|
$242.000
|
$200.000
|
|
|
BACK PLATE (12")(5 SEC)
|
EA
|
1.000
|
$95.260
|
$137.500
|
$200.000
|
|
|
TRF SIG CBL (TY A)(12 AWG)(5 CONDR)
|
LF
|
10.000
|
$2.780
|
$2.200
|
$3.000
|
|
|
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
|
LF
|
95.000
|
$2.970
|
$2.470
|
$3.000
|
|
|
RELOCATE PED POLE ASSEMBLY
|
EA
|
1.000
|
$1,645.460
|
$907.500
|
$2,000.000
|
|
|
REMOVAL OF SIGNAL HEAD ASSM
|
EA
|
3.000
|
$146.930
|
$880.000
|
$400.000
|
|
|
INSTALL OF SIGNAL HEAD ASSM
|
EA
|
2.000
|
$360.000
|
$550.000
|
$400.000
|
|
|
TREE REMOVAL (24" - 30" DIA)
|
EA
|
5.000
|
$1,200.000
|
$1,500.000
|
$200.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
84.000
|
$54.000
|
$300.000
|
$150.000
|
|
|
TMA (STATIONARY)
|
DAY
|
16.000
|
$181.620
|
$300.000
|
$200.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
152.000
|
$178.050
|
$300.000
|
$400.000
|
|
Totals: |
$2,550,498.399
|
$2,758,844.474
|
$3,124,710.200
|