PREPARING ROW
|
STA
|
55.000
|
$11,000.000
|
$153,000.000
|
$130,995.000
|
$173,794.870
|
$173,794.870
|
|
|
REMOVING CONC (PAV)
|
SY
|
12,078.000
|
$39.000
|
$20.630
|
$35.000
|
$10.980
|
$10.980
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
2,728.000
|
$50.000
|
$9.080
|
$59.710
|
$5.610
|
$5.610
|
|
|
REMOVING CONC (SIDEWALKS)
|
SY
|
1,736.000
|
$20.000
|
$5.690
|
$53.040
|
$6.690
|
$6.690
|
|
|
REMOVING CONC (CTB)
|
LF
|
2,623.000
|
$25.000
|
$3.400
|
$18.850
|
$10.400
|
$10.400
|
|
|
REMOVING CONC (CURB OR CURB & GUTTER)
|
LF
|
5,805.000
|
$68.000
|
$3.790
|
$6.900
|
$2.170
|
$2.170
|
|
|
REMOVING CONC (FLUME)
|
SY
|
80.000
|
$130.000
|
$40.280
|
$151.700
|
$27.800
|
$27.800
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
5,231.000
|
$17.000
|
$1.760
|
$9.610
|
$2.990
|
$2.990
|
|
|
REMOVING STAB BASE & ASPH PAV(12"-27")
|
SY
|
40,480.000
|
$15.000
|
$7.890
|
$18.800
|
$17.290
|
$17.290
|
|
|
OBLITERATING ABANDONED ROAD
|
SY
|
407.000
|
$25.000
|
$33.680
|
$29.950
|
$16.780
|
$16.780
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
78,726.000
|
$25.000
|
$16.060
|
$8.000
|
$28.000
|
$28.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY A)
|
CY
|
61,397.000
|
$18.000
|
$24.570
|
$20.000
|
$55.000
|
$55.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY A)
|
CY
|
2,943.000
|
$40.000
|
$86.500
|
$45.000
|
$85.000
|
$85.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
31,606.000
|
$6.000
|
$4.290
|
$3.220
|
$9.130
|
$9.130
|
|
|
DRILL SEEDING (PERM) (URBAN) (CLAY)
|
SY
|
31,606.000
|
$1.000
|
$0.320
|
$0.200
|
$0.200
|
$0.200
|
|
|
DRILL SEED (TEMP)(WARM OR COOL)
|
SY
|
31,606.000
|
$1.000
|
$0.230
|
$0.180
|
$0.180
|
$0.180
|
|
|
VEGETATIVE WATERING
|
MG
|
984.000
|
$100.000
|
$27.520
|
$45.850
|
$50.000
|
$50.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY A)
|
SY
|
31,606.000
|
$5.000
|
$1.860
|
$1.000
|
$1.000
|
$1.000
|
|
|
PROOF ROLLING
|
HR
|
3.000
|
$120.000
|
$225.000
|
$11,000.000
|
$128.560
|
$128.560
|
|
|
FB(CMP IN PLC)(TY D GR 1-2 OR 5)(12")
|
SY
|
13,113.000
|
$30.000
|
$29.790
|
$12.000
|
$23.390
|
$23.390
|
|
|
CEM TRT(PLNT MX) (CL L)(TYA)(GR1-2)(6")
|
SY
|
1,247.000
|
$40.000
|
$40.650
|
$35.750
|
$35.780
|
$35.780
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
1,540.000
|
$6.000
|
$5.720
|
$5.000
|
$4.580
|
$4.580
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(10")
|
SY
|
1,947.000
|
$90.000
|
$148.520
|
$129.190
|
$116.500
|
$116.500
|
|
|
PLANE ASPH CONC PAV(0" TO 4")
|
SY
|
22,209.000
|
$6.000
|
$9.770
|
$5.630
|
$5.090
|
$5.090
|
|
|
PAV JT UNDERSEAL (24")
|
LF
|
184.000
|
$40.000
|
$49.700
|
$38.000
|
$60.000
|
$60.000
|
|
|
CONC PVMT (CONT REINF - CRCP) (8")
|
SY
|
1,267.000
|
$138.000
|
$140.400
|
$153.170
|
$128.930
|
$128.930
|
|
|
CONC PVMT (CONT REINF - CRCP) (13")
|
SY
|
37,875.000
|
$114.000
|
$154.090
|
$129.340
|
$145.970
|
$145.970
|
|
|
CONC PVMT (CONT REINF-CRCP)(HES)(15")
|
SY
|
538.000
|
$147.000
|
$300.000
|
$281.040
|
$188.730
|
$188.730
|
|
|
CEM STABIL BKFL
|
CY
|
3,776.000
|
$250.000
|
$171.020
|
$325.000
|
$209.200
|
$209.200
|
|
|
CUT & RESTORE CONC PAVING
|
SY
|
1,269.000
|
$350.000
|
$210.420
|
$258.070
|
$279.650
|
$279.650
|
|
|
CEMENT STAB BACKFILL (INLET OR MH)
|
CY
|
43.000
|
$120.000
|
$422.430
|
$325.000
|
$215.720
|
$215.720
|
|
|
FLOWABLE BACKFILL
|
CY
|
201.000
|
$300.000
|
$237.190
|
$325.000
|
$276.130
|
$276.130
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
1,898.000
|
$40.000
|
$34.280
|
$41.330
|
$52.030
|
$52.030
|
|
|
TEMPORARY SPL SHORING
|
SF
|
39,820.000
|
$42.000
|
$45.000
|
$40.000
|
$45.300
|
$45.300
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
286.000
|
$200.000
|
$164.690
|
$206.880
|
$209.290
|
$209.290
|
|
|
DRILL SHAFT (42 IN)
|
LF
|
2,212.000
|
$586.000
|
$385.480
|
$544.000
|
$434.910
|
$434.910
|
|
|
DRILL SHAFT (48 IN)
|
LF
|
42.000
|
$495.000
|
$897.930
|
$909.000
|
$600.000
|
$600.000
|
|
|
DRILL SHAFT (72 IN)
|
LF
|
1,806.000
|
$900.000
|
$939.010
|
$854.100
|
$1,000.000
|
$1,000.000
|
|
|
DRILL SHAFT (NON - REINFORCED) (12 IN)
|
LF
|
7.000
|
$124.000
|
$225.890
|
$200.000
|
$125.000
|
$125.000
|
|
|
DRILL SHAFT (SIGN MTS) (42 IN)
|
LF
|
764.000
|
$550.000
|
$542.160
|
$480.000
|
$436.040
|
$436.040
|
|
|
DRILL SHAFT (SIGN MTS) (54 IN)
|
LF
|
31.000
|
$800.000
|
$847.120
|
$750.000
|
$850.000
|
$850.000
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
320.000
|
$300.000
|
$429.210
|
$380.000
|
$350.000
|
$350.000
|
|
|
DRILL SHAFT (TRF SIG POLE) (36 IN)
|
LF
|
13.000
|
$400.000
|
$530.860
|
$470.000
|
$450.000
|
$450.000
|
|
|
CL C CONC (ABUT)
|
CY
|
339.600
|
$1,500.000
|
$1,280.230
|
$1,475.270
|
$1,800.000
|
$1,800.000
|
|
|
CL C CONC (CAP)
|
CY
|
118.200
|
$1,600.000
|
$2,827.170
|
$2,473.390
|
$2,500.000
|
$2,500.000
|
|
|
CL C CONC (CAP)(MASS)
|
CY
|
1,079.200
|
$1,300.000
|
$1,352.050
|
$1,202.110
|
$1,400.000
|
$1,400.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
526.200
|
$1,800.000
|
$945.210
|
$1,569.770
|
$1,900.000
|
$1,900.000
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
144.000
|
$800.000
|
$740.040
|
$639.270
|
$736.720
|
$736.720
|
|
|
CL C CONC (SIGN COLUMN)
|
CY
|
305.000
|
$1,600.000
|
$1,480.010
|
$1,904.350
|
$2,146.100
|
$2,146.100
|
|
|
CL C CONC (MISC)
|
CY
|
148.000
|
$2,000.000
|
$1,051.720
|
$1,399.270
|
$1,170.940
|
$1,170.940
|
|
|
CL C CONC (SIGN FOOTING)
|
CY
|
84.000
|
$1,200.000
|
$1,115.610
|
$2,174.990
|
$1,687.590
|
$1,687.590
|
|
|
REINF CONC SLAB
|
SF
|
148,665.000
|
$27.000
|
$30.880
|
$28.080
|
$32.760
|
$32.760
|
|
|
APPROACH SLAB
|
CY
|
642.900
|
$800.000
|
$766.790
|
$956.150
|
$728.490
|
$728.490
|
|
|
RETAINING WALL (MSE)
|
SF
|
43,721.000
|
$200.000
|
$87.280
|
$81.020
|
$120.000
|
$120.000
|
|
|
RETAINING WALL (TEMP WALL)
|
SF
|
19,376.000
|
$30.000
|
$30.960
|
$12.000
|
$20.000
|
$20.000
|
|
|
PRESTR CONC GIRDER (TX70)
|
LF
|
6,787.800
|
$277.000
|
$228.370
|
$325.000
|
$261.130
|
$261.130
|
|
|
SILICONE RESIN PAINT FINISH
|
SF
|
1,780.000
|
$20.000
|
$12.080
|
$5.200
|
$5.200
|
$5.200
|
|
|
CONC STR REPAIR(RAPID DECK REP(PRT DPT)
|
SF
|
60.000
|
$175.000
|
$33.910
|
$157.630
|
$175.000
|
$175.000
|
|
|
CONC STR REPAIR (VERTICAL & OVERHEAD)
|
SF
|
38.000
|
$250.000
|
$35.870
|
$259.250
|
$360.000
|
$360.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
2,247.000
|
$845.000
|
$559.170
|
$405.000
|
$479.940
|
$479.940
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
11.000
|
$650.000
|
$803.580
|
$650.000
|
$808.790
|
$808.790
|
|
|
RIPRAP (CONC)(CL B)
|
CY
|
7.500
|
$650.000
|
$940.410
|
$650.000
|
$1,090.150
|
$1,090.150
|
|
|
RIPRAP(CONC)(SIGN MOUNTS)(CL B)
|
CY
|
10.000
|
$940.000
|
$1,352.540
|
$1,013.780
|
$1,220.160
|
$1,220.160
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
286.000
|
$570.000
|
$435.970
|
$360.000
|
$590.170
|
$590.170
|
|
|
ELASTOMERIC BEARING (E7)
|
EA
|
21.000
|
$5,300.000
|
$4,867.270
|
$4,499.630
|
$5,232.240
|
$5,232.240
|
|
|
ELASTOMERIC BEARING (F7)
|
EA
|
21.000
|
$5,200.000
|
$4,867.270
|
$4,499.630
|
$5,232.240
|
$5,232.240
|
|
|
SLIDING ELASTOMERIC BEARING (ES 4)
|
EA
|
42.000
|
$5,200.000
|
$4,867.270
|
$3,199.620
|
$3,656.690
|
$3,656.690
|
|
|
CLEANING AND SEALING EXISTING JOINTS
|
LF
|
98.000
|
$40.000
|
$97.140
|
$88.000
|
$60.000
|
$60.000
|
|
|
CLEANING AND SEALING JOINTS (FOAM)
|
LF
|
98.000
|
$75.000
|
$169.420
|
$160.000
|
$129.000
|
$129.000
|
|
|
STR STEEL (PLATE GIRDER)
|
LB
|
4,619,300.000
|
$4.000
|
$2.550
|
$2.650
|
$3.140
|
$3.140
|
|
|
STR STEEL (MISCELLANEOUS BRIDGE)
|
LB
|
43,720.000
|
$16.000
|
$2.180
|
$2.800
|
$3.000
|
$3.000
|
|
|
STR STEEL (DIAPHRAGM & STIFFENER)
|
LB
|
375,130.000
|
$25.000
|
$2.180
|
$3.030
|
$3.000
|
$3.000
|
|
|
STR STEEL (SHEAR CONNECTOR)
|
LB
|
54,550.000
|
$14.000
|
$2.180
|
$2.620
|
$3.000
|
$3.000
|
|
|
RAIL (TY SSTR)
|
LF
|
9,511.000
|
$70.000
|
$102.900
|
$60.000
|
$64.950
|
$64.950
|
|
|
RAIL (TY SSTR) (W/DRAIN SLOTS)
|
LF
|
621.000
|
$105.000
|
$67.030
|
$65.000
|
$79.100
|
$79.100
|
|
|
RAIL (TY SSTR)(MOD)
|
LF
|
5,103.000
|
$198.000
|
$94.720
|
$150.000
|
$134.290
|
$134.290
|
|
|
RAIL (CLF-RO)
|
LF
|
1,140.000
|
$125.000
|
$98.270
|
$115.850
|
$104.080
|
$104.080
|
|
|
RETROFIT RAIL (TY T2P)
|
LF
|
409.000
|
$672.000
|
$420.780
|
$308.030
|
$562.700
|
$562.700
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
441.500
|
$220.000
|
$289.300
|
$295.490
|
$345.960
|
$345.960
|
|
|
SEALED EXPANSION JOINT (5 IN) (SEJ - M)
|
LF
|
441.000
|
$270.000
|
$289.630
|
$295.600
|
$345.950
|
$345.950
|
|
|
CONC BOX CULV (3 FT X 2 FT)
|
LF
|
1,009.000
|
$408.000
|
$301.710
|
$267.070
|
$395.400
|
$395.400
|
|
|
CONC BOX CULV (4 FT X 2 FT)
|
LF
|
810.000
|
$450.000
|
$319.160
|
$297.380
|
$410.090
|
$410.090
|
|
|
CONC BOX CULV (5 FT X 2 FT)
|
LF
|
1,366.000
|
$570.000
|
$441.620
|
$415.570
|
$554.440
|
$554.440
|
|
|
CONC BOX CULV (5 FT X 3 FT)
|
LF
|
225.000
|
$500.000
|
$442.810
|
$458.450
|
$566.550
|
$566.550
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
273.000
|
$132.000
|
$87.410
|
$142.490
|
$124.240
|
$124.240
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
53.000
|
$150.000
|
$104.990
|
$185.600
|
$150.310
|
$150.310
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
378.000
|
$222.000
|
$122.900
|
$129.520
|
$158.990
|
$158.990
|
|
|
RC PIPE (CL IV)(18 IN)
|
LF
|
56.000
|
$120.000
|
$98.730
|
$141.730
|
$143.200
|
$143.200
|
|
|
RC PIPE (CL IV)(24 IN)
|
LF
|
2,080.000
|
$150.000
|
$109.140
|
$97.590
|
$147.520
|
$147.520
|
|
|
RC PIPE (CL IV)(30 IN)
|
LF
|
512.000
|
$200.000
|
$135.100
|
$123.160
|
$201.550
|
$201.550
|
|
|
RC PIPE (CL IV)(36 IN)
|
LF
|
290.000
|
$300.000
|
$181.620
|
$203.160
|
$268.550
|
$268.550
|
|
|
JCTBOX(COMPL)(PJB)(3FTX5FT)
|
EA
|
1.000
|
$8,200.000
|
$6,765.660
|
$6,441.460
|
$7,056.390
|
$7,056.390
|
|
|
INLET (COMPL)(PCO)(3FT)(NONE)
|
EA
|
1.000
|
$10,000.000
|
$7,449.000
|
$6,419.630
|
$10,889.880
|
$10,889.880
|
|
|
INLET (COMPL)(PCU)(3FT)(NONE)
|
EA
|
2.000
|
$15,000.000
|
$7,947.140
|
$9,634.160
|
$11,261.080
|
$11,261.080
|
|
|
INLET (COMPL)(PSL)(SL)(4FTX4FT)
|
EA
|
2.000
|
$5,000.000
|
$7,412.890
|
$8,082.530
|
$7,116.790
|
$7,116.790
|
|
|
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
|
EA
|
4.000
|
$6,000.000
|
$7,864.690
|
$6,671.190
|
$7,615.920
|
$7,615.920
|
|
|
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
|
EA
|
5.000
|
$7,600.000
|
$14,340.100
|
$15,499.480
|
$13,384.000
|
$13,384.000
|
|
|
INLET(COMPL)(PAZD)(FG)(3FTX3FT-3FTX3FT)
|
EA
|
1.000
|
$8,970.000
|
$8,341.340
|
$10,135.260
|
$8,123.740
|
$8,123.740
|
|
|
INLET(COMPL)(PAZD)(FG)(4FTX4FT-4FTX4FT)
|
EA
|
1.000
|
$14,000.000
|
$8,962.560
|
$11,198.670
|
$8,679.510
|
$8,679.510
|
|
|
INLET (COMPL)(TY MSE1)
|
EA
|
6.000
|
$6,500.000
|
$6,451.910
|
$15,146.850
|
$11,119.920
|
$11,119.920
|
|
|
INLET (COMPL)(TY MSE2)
|
EA
|
7.000
|
$11,000.000
|
$9,166.510
|
$18,683.540
|
$12,298.840
|
$12,298.840
|
|
|
INLET (COMPL)(ARMOR CURB SLOT)
|
EA
|
3.000
|
$6,000.000
|
$7,831.880
|
$8,411.070
|
$5,236.920
|
$5,236.920
|
|
|
SET (TY I)(S=3 FT)(HW= 3 FT)(6:1)(C)
|
EA
|
2.000
|
$15,000.000
|
$13,796.950
|
$14,419.810
|
$16,485.830
|
$16,485.830
|
|
|
SET (TY I)(S=3 FT)(HW= 3 FT)(6:1)(P)
|
EA
|
2.000
|
$8,715.000
|
$10,033.800
|
$16,447.610
|
$15,866.010
|
$15,866.010
|
|
|
SET (TY I)(S= 4 FT)(HW= 3 FT)(6:1) (P)
|
EA
|
2.000
|
$8,500.000
|
$11,288.190
|
$15,022.470
|
$19,051.610
|
$19,051.610
|
|
|
SET (TY I)(S= 5 FT)(HW= 2 FT)(6:1) (P)
|
EA
|
1.000
|
$11,000.000
|
$13,234.380
|
$19,255.880
|
$18,330.440
|
$18,330.440
|
|
|
SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1) (P)
|
EA
|
2.000
|
$10,000.000
|
$13,796.950
|
$21,938.080
|
$24,472.750
|
$24,472.750
|
|
|
SET (TY I)(S= 5 FT)(HW= 4 FT)(6:1) (P)
|
EA
|
2.000
|
$12,000.000
|
$15,051.340
|
$22,623.890
|
$26,888.060
|
$26,888.060
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (P)
|
EA
|
2.000
|
$2,600.000
|
$4,484.110
|
$2,709.050
|
$2,587.380
|
$2,587.380
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (C)
|
EA
|
1.000
|
$2,575.000
|
$4,866.990
|
$3,571.050
|
$3,293.680
|
$3,293.680
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
6.000
|
$2,400.000
|
$4,867.010
|
$3,887.970
|
$3,293.680
|
$3,293.680
|
|
|
SET (TY II) (30 IN) (RCP) (6: 1) (P)
|
EA
|
5.000
|
$4,100.000
|
$6,165.920
|
$6,247.760
|
$5,144.180
|
$5,144.180
|
|
|
GRATE AND FRAME (BRIDGE DRAIN)
|
EA
|
14.000
|
$4,500.000
|
$3,242.290
|
$5,872.810
|
$3,098.030
|
$3,098.030
|
|
|
PIPE (PVC) (SCH 40) (6 IN)
|
LF
|
279.000
|
$181.000
|
$74.860
|
$150.000
|
$119.970
|
$119.970
|
|
|
REMOV STR (INLET)
|
EA
|
8.000
|
$1,525.000
|
$1,036.160
|
$1,500.000
|
$1,233.000
|
$1,233.000
|
|
|
REMOV STR (SET)
|
EA
|
14.000
|
$760.000
|
$1,021.120
|
$1,500.000
|
$624.980
|
$624.980
|
|
|
REMOV STR (WINGWALL)
|
EA
|
3.000
|
$2,355.000
|
$760.950
|
$3,000.000
|
$3,002.120
|
$3,002.120
|
|
|
REMOV STR (HEADWALL)
|
EA
|
6.000
|
$3,300.000
|
$1,381.540
|
$3,000.000
|
$3,098.100
|
$3,098.100
|
|
|
REMOV STR (PIPE)
|
LF
|
5,663.000
|
$55.000
|
$14.640
|
$30.000
|
$39.110
|
$39.110
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
620.000
|
$140.000
|
$23.270
|
$70.000
|
$71.400
|
$71.400
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
2.000
|
$200,000.000
|
$209,947.500
|
$375,000.000
|
$350,000.000
|
$350,000.000
|
|
|
REMOV STR (RET WALL)
|
LF
|
340.000
|
$73.000
|
$113.960
|
$200.000
|
$199.880
|
$199.880
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$8,933,405.090
|
$8,415,000.000
|
$8,650,000.000
|
$9,560,000.000
|
$9,560,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
54.000
|
$10,000.000
|
$24,000.000
|
$97,500.000
|
$43,594.680
|
$43,594.680
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
540.000
|
$40.000
|
$41.630
|
$36.860
|
$42.000
|
$42.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
540.000
|
$15.000
|
$8.110
|
$7.180
|
$15.000
|
$15.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
3,600.000
|
$5.000
|
$3.960
|
$3.500
|
$4.500
|
$4.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
3,600.000
|
$1.500
|
$0.280
|
$0.250
|
$1.000
|
$1.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
438.000
|
$8.000
|
$7.350
|
$6.500
|
$5.000
|
$5.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
438.000
|
$2.500
|
$1.020
|
$0.900
|
$1.500
|
$1.500
|
|
|
CONSTRUCTING DETOURS (TY 1)
|
SY
|
22,904.000
|
$90.000
|
$120.000
|
$109.150
|
$94.000
|
$94.000
|
|
|
CONSTRUCTING DETOURS (TY 2)
|
SY
|
400.000
|
$65.000
|
$166.450
|
$121.030
|
$150.000
|
$150.000
|
|
|
ONE-WAY TRAF CONT (FLAGGER CONT)
|
HR
|
1,260.000
|
$72.000
|
$67.770
|
$64.950
|
$40.230
|
$40.230
|
|
|
ONE-WAY TRAF CONT (PILOT CAR)
|
HR
|
252.000
|
$95.000
|
$73.420
|
$70.360
|
$52.260
|
$52.260
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
27,014.000
|
$54.000
|
$29.000
|
$36.180
|
$36.340
|
$36.340
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
7,758.000
|
$55.000
|
$30.000
|
$35.540
|
$54.450
|
$54.450
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
280.000
|
$60.000
|
$101.720
|
$98.790
|
$55.170
|
$55.170
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
19,604.000
|
$20.000
|
$5.130
|
$7.800
|
$6.760
|
$6.760
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
9,411.000
|
$17.000
|
$4.520
|
$10.590
|
$10.070
|
$10.070
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
1,967.000
|
$16.000
|
$10.000
|
$17.280
|
$9.740
|
$9.740
|
|
|
PORT CTB (STKPL)(SGL SLP)(TY 1)
|
LF
|
667.000
|
$20.000
|
$57.340
|
$20.660
|
$14.710
|
$14.710
|
|
|
PORT CTB (STKPL)(LOW PROF)(TY 1)
|
LF
|
934.000
|
$20.000
|
$55.440
|
$19.610
|
$11.560
|
$11.560
|
|
|
PORT CTB (STKPL)(LOW PROF)(TY 2)
|
LF
|
20.000
|
$20.000
|
$30.180
|
$57.740
|
$40.450
|
$40.450
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
21,547.000
|
$20.000
|
$7.850
|
$17.470
|
$8.800
|
$8.800
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
7,055.000
|
$20.000
|
$5.000
|
$17.480
|
$11.660
|
$11.660
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
180.000
|
$24.000
|
$18.440
|
$50.760
|
$12.670
|
$12.670
|
|
|
PERM CTB (SGL SLOPE) (TY 1) (42 )
|
LF
|
1,026.000
|
$90.000
|
$81.780
|
$79.810
|
$102.290
|
$102.290
|
|
|
PERM CTB (SGL SLOPE) (TY 3) (42 )
|
LF
|
77.000
|
$280.000
|
$670.660
|
$251.790
|
$293.440
|
$293.440
|
|
|
PERM CTB (TRAN SSCB TO SSTR) (MOD)
|
LF
|
30.000
|
$230.000
|
$634.200
|
$252.220
|
$319.630
|
$319.630
|
|
|
CONC CURB (TY I)
|
LF
|
6,746.000
|
$25.000
|
$12.870
|
$11.000
|
$11.560
|
$11.560
|
|
|
CONC SIDEWALKS (6")
|
SY
|
3,156.000
|
$125.000
|
$87.150
|
$49.000
|
$70.770
|
$70.770
|
|
|
CURB RAMPS (TY 1)
|
EA
|
4.000
|
$2,400.000
|
$3,240.080
|
$2,700.000
|
$3,548.180
|
$3,548.180
|
|
|
CURB RAMPS (TY 2)
|
EA
|
2.000
|
$2,500.000
|
$3,420.630
|
$2,700.000
|
$3,548.180
|
$3,548.180
|
|
|
CURB RAMPS (TY 5)
|
EA
|
3.000
|
$3,000.000
|
$3,635.810
|
$3,000.000
|
$3,854.310
|
$3,854.310
|
|
|
CURB RAMPS (TY 7)
|
EA
|
1.000
|
$2,500.000
|
$4,110.690
|
$3,000.000
|
$3,854.310
|
$3,854.310
|
|
|
CURB RAMPS (TY 21)
|
EA
|
2.000
|
$3,200.000
|
$3,749.600
|
$3,000.000
|
$3,854.310
|
$3,854.310
|
|
|
CONC MEDIAN
|
SY
|
36.000
|
$120.000
|
$175.000
|
$120.000
|
$178.070
|
$178.070
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
2,640.000
|
$25.000
|
$34.870
|
$29.000
|
$25.460
|
$25.460
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$1,800.000
|
$2,854.570
|
$2,700.000
|
$2,086.740
|
$2,086.740
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
5.000
|
$1,500.000
|
$1,688.600
|
$1,680.000
|
$1,219.390
|
$1,219.390
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
5,000.000
|
$11.000
|
$2.830
|
$4.000
|
$2.040
|
$2.040
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
8.000
|
$480.000
|
$1,784.610
|
$275.000
|
$204.080
|
$204.080
|
|
|
REMOVE DOWNSTREAM ANCHOR TERMINAL
|
EA
|
7.000
|
$250.000
|
$203.300
|
$275.000
|
$204.080
|
$204.080
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$352.000
|
$395.310
|
$225.000
|
$239.800
|
$239.800
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$2,900.000
|
$4,522.680
|
$3,345.000
|
$2,918.370
|
$2,918.370
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
15.000
|
$1,360.000
|
$2,541.370
|
$875.000
|
$1,341.840
|
$1,341.840
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
14.000
|
$900.000
|
$790.650
|
$850.000
|
$744.900
|
$744.900
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
4.000
|
$28,000.000
|
$36,236.530
|
$29,500.000
|
$29,897.960
|
$29,897.960
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(W)(TL3)
|
EA
|
1.000
|
$45,000.000
|
$48,481.580
|
$47,200.000
|
$40,612.240
|
$40,612.240
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
21.000
|
$8,720.000
|
$9,702.730
|
$8,075.000
|
$7,704.080
|
$7,704.080
|
|
|
REMOVE RD IL ASM (TRANS-BASE)
|
EA
|
12.000
|
$960.000
|
$530.860
|
$470.000
|
$357.140
|
$357.140
|
|
|
REPLACE LUMINAIRE W/LED (250W EQ)
|
EA
|
4.000
|
$800.000
|
$858.420
|
$760.000
|
$1,428.570
|
$1,428.570
|
|
|
IN RD IL (U/P) (TY 1) (150W EQ) LED
|
EA
|
10.000
|
$1,200.000
|
$2,597.840
|
$2,300.000
|
$1,836.740
|
$1,836.740
|
|
|
IN RD IL (TY SA) 40T-10 (250W EQ) LED
|
EA
|
10.000
|
$5,300.000
|
$4,969.790
|
$4,400.000
|
$5,408.160
|
$5,408.160
|
|
|
IN RD IL (TY SA) 50B-10 (400W EQ) LED
|
EA
|
14.000
|
$7,000.000
|
$6,099.280
|
$5,400.000
|
$6,122.450
|
$6,122.450
|
|
|
IN RD IL (TY SA) 50T-10-10(400W EQ)LED
|
EA
|
9.000
|
$5,000.000
|
$7,002.900
|
$6,200.000
|
$6,326.530
|
$6,326.530
|
|
|
TEMP RD IL (RD IL ASM)
|
EA
|
21.000
|
$6,000.000
|
$6,325.170
|
$5,600.000
|
$1,530.610
|
$1,530.610
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
9,405.000
|
$18.000
|
$16.940
|
$15.000
|
$15.310
|
$15.310
|
|
|
CONDT (PVC) (SCH 40) (3") (CONC ENCSE)
|
LF
|
4,865.000
|
$30.000
|
$42.920
|
$38.000
|
$34.690
|
$34.690
|
|
|
CONDT (PVC) (SCH 80) (2")
|
LF
|
10.000
|
$22.000
|
$64.380
|
$57.000
|
$40.820
|
$40.820
|
|
|
CONDT (PVC) (SCH 80) (2") (BORE)
|
LF
|
5,465.000
|
$32.000
|
$41.790
|
$37.000
|
$40.820
|
$40.820
|
|
|
CONDT (PVC) (SCH 80) (3")
|
LF
|
10.000
|
$30.000
|
$97.140
|
$86.000
|
$40.820
|
$40.820
|
|
|
CONDT (PVC) (SCH 80) (3") (BORE)
|
LF
|
5,455.000
|
$45.000
|
$49.700
|
$44.000
|
$45.920
|
$45.920
|
|
|
CONDT (RM) (3/4")
|
LF
|
445.000
|
$50.000
|
$42.920
|
$38.000
|
$26.530
|
$26.530
|
|
|
CONDT (RM) (2")
|
LF
|
10.000
|
$50.000
|
$124.240
|
$110.000
|
$40.820
|
$40.820
|
|
|
CONDT (RM) (3")
|
LF
|
1,775.000
|
$100.000
|
$93.760
|
$83.000
|
$76.530
|
$76.530
|
|
|
ELEC CONDR (NO.14) INSULATED
|
LF
|
8,710.000
|
$1.500
|
$1.300
|
$1.150
|
$1.530
|
$1.530
|
|
|
ELEC CONDR (NO.8) BARE
|
LF
|
1,730.000
|
$2.000
|
$3.110
|
$2.750
|
$2.300
|
$2.300
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
230.000
|
$2.000
|
$2.260
|
$2.000
|
$2.550
|
$2.550
|
|
|
ELEC CONDR (NO.6) BARE
|
LF
|
10,940.000
|
$2.500
|
$2.320
|
$2.050
|
$2.450
|
$2.450
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
27,560.000
|
$2.500
|
$2.490
|
$2.200
|
$2.760
|
$2.760
|
|
|
ELEC CONDR (NO.2) BARE
|
LF
|
1,270.000
|
$4.000
|
$4.290
|
$3.800
|
$4.590
|
$4.590
|
|
|
ELEC CONDR (NO.2) INSULATED
|
LF
|
2,530.000
|
$4.000
|
$4.860
|
$4.300
|
$4.900
|
$4.900
|
|
|
TRAY CABLE (4 CONDR) (12 AWG)
|
LF
|
700.000
|
$3.200
|
$4.070
|
$3.600
|
$3.060
|
$3.060
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
34.000
|
$1,200.000
|
$1,920.140
|
$1,700.000
|
$1,632.650
|
$1,632.650
|
|
|
GROUND BOX TY D (162922)W/APRON
|
EA
|
22.000
|
$1,550.000
|
$2,484.890
|
$2,200.000
|
$1,734.690
|
$1,734.690
|
|
|
REMOVE GROUND BOX
|
EA
|
10.000
|
$391.000
|
$192.010
|
$170.000
|
$561.230
|
$561.230
|
|
|
TIMBER POLE (CL 2) 50 FT
|
EA
|
4.000
|
$2,500.000
|
$4,517.990
|
$4,000.000
|
$1,836.740
|
$1,836.740
|
|
|
ELC SRV TY D 120/240 060(NS)SS(N)SP(O)
|
EA
|
3.000
|
$7,400.000
|
$10,165.480
|
$9,000.000
|
$9,387.760
|
$9,387.760
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
111.000
|
$40.000
|
$64.380
|
$57.000
|
$37.810
|
$37.810
|
|
|
ALUMINUM SIGNS (TY G)
|
SF
|
38.000
|
$35.000
|
$45.180
|
$40.000
|
$37.810
|
$37.810
|
|
|
ALUMINUM SIGNS (TY O)
|
SF
|
1,182.000
|
$35.000
|
$29.370
|
$26.000
|
$43.210
|
$43.210
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
6.000
|
$900.000
|
$960.070
|
$665.000
|
$864.250
|
$864.250
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
19.000
|
$950.000
|
$1,050.430
|
$765.000
|
$972.280
|
$972.280
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
3.000
|
$1,050.000
|
$1,355.390
|
$860.000
|
$1,080.310
|
$1,080.310
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
|
EA
|
1.000
|
$1,170.000
|
$1,581.310
|
$1,135.000
|
$1,512.440
|
$1,512.440
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
|
EA
|
4.000
|
$4,000.000
|
$2,936.690
|
$2,600.000
|
$3,240.940
|
$3,240.940
|
|
|
IN SM RD SN SUP&AM (RAIL MOUNT)
|
EA
|
5.000
|
$4,500.000
|
$2,823.750
|
$2,500.000
|
$4,321.260
|
$4,321.260
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
30.000
|
$170.000
|
$180.720
|
$153.280
|
$216.060
|
$216.060
|
|
|
INSTALL LRSS (STRUCT STEEL)
|
LB
|
197.000
|
$8.000
|
$9.320
|
$8.250
|
$9.720
|
$9.720
|
|
|
REMOVE LRSA
|
EA
|
4.000
|
$1,000.000
|
$869.700
|
$770.000
|
$1,404.410
|
$1,404.410
|
|
|
INS OH SN SUP(35 FT CANT)(SPAN ONLY)
|
EA
|
2.000
|
$31,000.000
|
$43,598.600
|
$38,600.000
|
$3,781.100
|
$3,781.100
|
|
|
INS OH SN SUP(55 FT BRDG)(SPAN ONLY)
|
EA
|
1.000
|
$75,000.000
|
$90,359.780
|
$80,000.000
|
$68,059.810
|
$68,059.810
|
|
|
INS OH SN SUP(60 FT BRDG)(SPAN ONLY)
|
EA
|
1.000
|
$55,000.000
|
$99,169.870
|
$87,800.000
|
$37,811.010
|
$37,811.010
|
|
|
INS OH SN SUP(75 FT BRDG)(SPAN ONLY)
|
EA
|
1.000
|
$76,000.000
|
$110,351.890
|
$97,700.000
|
$83,184.220
|
$83,184.220
|
|
|
INS OH SN SUP(85 FT BRDG)(SPAN ONLY)
|
EA
|
1.000
|
$75,000.000
|
$121,985.710
|
$108,000.000
|
$92,907.050
|
$92,907.050
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
9.000
|
$42.000
|
$16.940
|
$32.210
|
$32.000
|
$32.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
10.000
|
$65.000
|
$71.960
|
$93.090
|
$93.000
|
$93.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BR)
|
EA
|
46.000
|
$38.000
|
$50.950
|
$43.540
|
$45.000
|
$45.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2(BR)
|
EA
|
22.000
|
$38.000
|
$50.950
|
$38.960
|
$39.000
|
$39.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BR)
|
EA
|
69.000
|
$45.000
|
$26.660
|
$21.990
|
$22.000
|
$22.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BR)
|
EA
|
87.000
|
$21.000
|
$26.660
|
$21.990
|
$22.000
|
$22.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
|
LF
|
1,026.000
|
$1.000
|
$1.130
|
$1.000
|
$1.000
|
$1.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
5,190.000
|
$1.000
|
$0.850
|
$0.750
|
$0.750
|
$0.750
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
5,858.000
|
$1.000
|
$0.850
|
$0.750
|
$0.750
|
$0.750
|
|
|
WK ZN PAV MRK REMOV (W)6"(BRK)
|
LF
|
12,203.000
|
$2.000
|
$1.130
|
$1.000
|
$1.000
|
$1.000
|
|
|
WK ZN PAV MRK REMOV (W)6"(DOT)
|
LF
|
87.000
|
$2.000
|
$2.260
|
$2.000
|
$2.000
|
$2.000
|
|
|
WK ZN PAV MRK REMOV (W)6"(SLD)
|
LF
|
43,816.000
|
$1.500
|
$0.900
|
$0.800
|
$0.800
|
$0.800
|
|
|
WK ZN PAV MRK REMOV (W)12"(SLD)
|
LF
|
2,084.000
|
$3.000
|
$3.960
|
$3.500
|
$3.500
|
$3.500
|
|
|
WK ZN PAV MRK REMOV (W)(ARROW)
|
EA
|
4.000
|
$245.000
|
$338.850
|
$300.000
|
$300.000
|
$300.000
|
|
|
WK ZN PAV MRK REMOV (Y)6"(SLD)
|
LF
|
43,655.000
|
$1.000
|
$0.900
|
$0.800
|
$0.800
|
$0.800
|
|
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
|
LF
|
182.000
|
$2.000
|
$2.260
|
$2.000
|
$2.000
|
$2.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
1,018.000
|
$2.000
|
$1.130
|
$1.000
|
$1.000
|
$1.000
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
428.000
|
$10.000
|
$11.290
|
$10.000
|
$10.000
|
$10.000
|
|
REFL PAV MRK TY I(W)(ENTR GORE)(100MIL)
|
EA
|
6.000
|
$1,150.000
|
$847.120
|
$750.000
|
$750.000
|
$750.000
|
|
REFL PAV MRK TY I(W)(EXIT GORE)(100MIL)
|
EA
|
3.000
|
$1,700.000
|
$847.120
|
$750.000
|
$750.000
|
$750.000
|
|
|
PAVEMENT SEALER 6"
|
LF
|
37,157.000
|
$1.000
|
$0.400
|
$0.350
|
$0.350
|
$0.350
|
|
|
PAVEMENT SEALER 8"
|
LF
|
1,018.000
|
$1.000
|
$0.400
|
$0.350
|
$0.350
|
$0.350
|
|
|
PAVEMENT SEALER 24"
|
LF
|
428.000
|
$3.000
|
$2.260
|
$2.000
|
$2.000
|
$2.000
|
|
|
PAVEMENT SEALER (ENTR GORE)
|
EA
|
6.000
|
$260.000
|
$197.660
|
$175.000
|
$175.000
|
$175.000
|
|
|
PAVEMENT SEALER (EXIT GORE)
|
EA
|
3.000
|
$412.000
|
$197.660
|
$175.000
|
$175.000
|
$175.000
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
3,416.000
|
$1.000
|
$0.850
|
$0.750
|
$0.750
|
$0.750
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
10,960.000
|
$1.000
|
$0.850
|
$0.750
|
$0.750
|
$0.750
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
10,650.000
|
$1.000
|
$0.850
|
$0.750
|
$0.750
|
$0.750
|
|
|
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
|
LF
|
5,425.000
|
$1.000
|
$1.700
|
$1.500
|
$1.500
|
$1.500
|
|
|
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
|
LF
|
6,524.000
|
$1.000
|
$1.700
|
$1.500
|
$1.500
|
$1.500
|
|
PREFAB PAV MRK TY B (W)(6")(BRK)
|
LF
|
2,509.000
|
$10.000
|
$7.910
|
$7.000
|
$7.000
|
$7.000
|
|
PREFAB PAV MRK TY B (W)(6")(SLD)
|
LF
|
7,806.000
|
$10.000
|
$2.830
|
$2.500
|
$2.500
|
$2.500
|
|
PREFAB PAV MRK TY B (W)(6")(DOT)
|
LF
|
224.000
|
$16.000
|
$5.650
|
$5.000
|
$5.000
|
$5.000
|
|
PREFAB PAV MRK TY B (W)(6")(BRK)CNTST
|
LF
|
5,018.000
|
$20.000
|
$9.040
|
$8.000
|
$8.000
|
$8.000
|
|
PREFAB PAV MRK TY B (W)(ARROW)
|
EA
|
14.000
|
$560.000
|
$395.310
|
$350.000
|
$350.000
|
$350.000
|
|
PREFAB PAV MRK TY B (W)(DBL ARROW)
|
EA
|
2.000
|
$900.000
|
$734.170
|
$650.000
|
$650.000
|
$650.000
|
|
PREFAB PAV MRK TY B (W)(LNDP ARROW)
|
EA
|
2.000
|
$1,800.000
|
$1,524.820
|
$1,350.000
|
$1,350.000
|
$1,350.000
|
|
PREFAB PAV MRK TY B (W)(WORD)
|
EA
|
16.000
|
$900.000
|
$536.510
|
$475.000
|
$475.000
|
$475.000
|
|
PREFAB PAV MRK TY B (W)(ENTR GORE)
|
EA
|
3.000
|
$8,000.000
|
$11,859.720
|
$10,500.000
|
$10,500.000
|
$10,500.000
|
|
PREFAB PAV MRK TY B (W)(EXIT GORE)
|
EA
|
2.000
|
$15,000.000
|
$11,859.720
|
$10,500.000
|
$10,500.000
|
$10,500.000
|
|
PREFAB PAV MRK TY B (W)(36")(YLD TRI)
|
EA
|
18.000
|
$88.000
|
$84.720
|
$75.000
|
$75.000
|
$75.000
|
|
PREFAB PAV MRK TY B (Y)(6")(SLD)
|
LF
|
6,770.000
|
$10.000
|
$2.830
|
$2.500
|
$2.500
|
$2.500
|
|
PREFAB PAV MRK TY B (MULTI)(SHIELD)
|
EA
|
4.000
|
$3,500.000
|
$3,953.240
|
$3,500.000
|
$3,500.000
|
$3,500.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
51.000
|
$6.000
|
$6.220
|
$5.500
|
$5.500
|
$5.500
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
30.000
|
$8.000
|
$6.220
|
$5.500
|
$5.500
|
$5.500
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
690.000
|
$6.000
|
$6.220
|
$5.500
|
$5.500
|
$5.500
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
5,396.000
|
$1.000
|
$1.130
|
$1.000
|
$1.000
|
$1.000
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
3,026.000
|
$1.750
|
$2.260
|
$2.000
|
$2.000
|
$2.000
|
|
|
TEMP TRAF SIGNALS
|
EA
|
1.000
|
$115,000.000
|
$58,169.110
|
$51,500.000
|
$51,020.410
|
$51,020.410
|
|
|
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
|
LF
|
275.000
|
$2.500
|
$3.790
|
$3.350
|
$3.060
|
$3.060
|
|
|
TRF SIG CBL (TY A)(12 AWG)(7 CONDR)
|
LF
|
2,519.000
|
$3.500
|
$5.090
|
$4.500
|
$3.320
|
$3.320
|
|
|
TRF SIG CBL (TY C)(14 AWG)(2 CONDR)
|
LF
|
270.000
|
$2.000
|
$2.940
|
$2.600
|
$3.060
|
$3.060
|
|
|
REMOVAL OF CONDUIT
|
LF
|
927.000
|
$10.000
|
$12.420
|
$11.000
|
$9.690
|
$9.690
|
|
|
REMOVAL OF CABLES
|
LF
|
1,791.000
|
$2.000
|
$0.900
|
$0.800
|
$3.060
|
$3.060
|
|
|
REMOVAL OF TIMBER POLES
|
EA
|
1.000
|
$350.000
|
$734.170
|
$650.000
|
$555.000
|
$555.000
|
|
|
STRIP MOWING
|
AC
|
6.530
|
$40.000
|
$225.000
|
$350.000
|
$500.000
|
$500.000
|
|
|
LITTER REMOVAL
|
AC
|
21.410
|
$55.000
|
$275.000
|
$280.000
|
$50.000
|
$50.000
|
|
|
DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES)
|
CYC
|
30.000
|
$1,820.000
|
$3,000.000
|
$1,640.000
|
$678.570
|
$678.570
|
|
|
DEBRIS REMOVAL (FRONTAGE ROADS)
|
CYC
|
30.000
|
$1,320.000
|
$3,000.000
|
$1,320.000
|
$678.570
|
$678.570
|
|
|
DEBRIS REMOVAL (ENTRANCE/EXIT RAMPS)
|
CYC
|
30.000
|
$2,000.000
|
$3,000.000
|
$1,050.000
|
$678.570
|
$678.570
|
|
|
CLEANING / SWEEPING (CENTER MEDIAN)
|
CYC
|
30.000
|
$2,500.000
|
$1,500.000
|
$2,950.000
|
$678.570
|
$678.570
|
|
|
CLEANING / SWEEPING (OUTSIDE MAIN LANE)
|
CYC
|
30.000
|
$2,142.000
|
$1,500.000
|
$2,950.000
|
$678.570
|
$678.570
|
|
|
CLEANING / SWEEPING (FRONTAGE ROAD)
|
CYC
|
30.000
|
$1,700.000
|
$2,500.000
|
$1,980.000
|
$678.570
|
$678.570
|
|
|
CLEANING / SWEEPING(ENTRANCE/EXIT RAMP)
|
CYC
|
30.000
|
$1,840.000
|
$1,500.000
|
$2,950.000
|
$678.570
|
$678.570
|
|
|
ANTI - GRAFFITI COATING(PERMNENT-TY II)
|
SF
|
34,075.000
|
$1.000
|
$0.850
|
$0.790
|
$0.790
|
$0.790
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
14,322.000
|
$130.000
|
$148.660
|
$130.000
|
$124.080
|
$124.080
|
|
|
D-GR HMA TY-D PG64-22
|
TON
|
112.000
|
$175.000
|
$222.990
|
$195.000
|
$254.260
|
$254.260
|
|
|
TACK COAT
|
GAL
|
315.000
|
$10.000
|
$4.580
|
$4.000
|
$4.320
|
$4.320
|
|
|
SP MIXES SP-C SAC-A PG76-22
|
TON
|
5,707.000
|
$135.000
|
$171.530
|
$150.000
|
$177.980
|
$177.980
|
|
|
BONDING COURSE
|
GAL
|
1,743.000
|
$5.000
|
$5.720
|
$5.000
|
$5.590
|
$5.590
|
|
|
UNDERSEAL COURSE
|
GAL
|
3,990.000
|
$10.000
|
$5.720
|
$5.000
|
$5.590
|
$5.590
|
|
|
TIP TESTING(DRILL SHAFT)
|
EA
|
4.000
|
$5,250.000
|
$7,341.740
|
$7,349.350
|
$4,398.890
|
$4,398.890
|
|
|
INSTALL BRIDGE IDENTIFICATION NUMBERS
|
EA
|
3.000
|
$400.000
|
$903.590
|
$500.000
|
$770.190
|
$770.190
|
|
|
ITS COM CBL (SERIAL)
|
LF
|
410.000
|
$2.500
|
$3.960
|
$3.500
|
$4.080
|
$4.080
|
|
|
FIBER OPTIC CBL (SNGLE-MODE)(12 FIBER)
|
LF
|
1,005.000
|
$5.500
|
$19.200
|
$17.000
|
$5.610
|
$5.610
|
|
|
FIBER OPTIC CBL (SNGLE-MODE)(144 FIBER)
|
LF
|
26,200.000
|
$4.000
|
$5.370
|
$4.750
|
$5.820
|
$5.820
|
|
|
FIBER OPTIC SPLICE ENCLOSURE
|
EA
|
7.000
|
$1,600.000
|
$2,597.840
|
$2,300.000
|
$2,142.860
|
$2,142.860
|
|
|
FIBER OPTIC PATCH PANEL (12 POSITION)
|
EA
|
6.000
|
$1,400.000
|
$1,242.450
|
$1,100.000
|
$1,734.690
|
$1,734.690
|
|
|
FIBER OPTIC CABLE ROAD MARKER
|
EA
|
20.000
|
$500.000
|
$180.720
|
$160.000
|
$306.120
|
$306.120
|
|
|
FIBER OPTIC PATCH PANEL (144 POSITION)
|
EA
|
1.000
|
$6,700.000
|
$3,727.320
|
$3,300.000
|
$4,081.630
|
$4,081.630
|
|
|
FIBER OPTIC FUSION SPLICE
|
EA
|
240.000
|
$100.000
|
$192.010
|
$170.000
|
$112.240
|
$112.240
|
|
|
FIBER OPTIC JUMPERS
|
EA
|
168.000
|
$100.000
|
$225.890
|
$200.000
|
$51.020
|
$51.020
|
|
|
ITS GND MNT CAB(TY 6)(CONF 1)(INS ONLY)
|
EA
|
1.000
|
$12,500.000
|
$2,033.100
|
$1,800.000
|
$10,204.080
|
$10,204.080
|
|
|
CCTV FIELD EQUIPMENT (DIGITAL)
|
EA
|
2.000
|
$7,300.000
|
$10,165.480
|
$9,000.000
|
$8,673.470
|
$8,673.470
|
|
|
CCTV MOUNT (POLE)
|
EA
|
2.000
|
$500.000
|
$37.270
|
$33.000
|
$1,326.530
|
$1,326.530
|
|
|
REMOVE CCTV FIELD EQUIPMENT
|
EA
|
2.000
|
$1,000.000
|
$722.870
|
$640.000
|
$1,020.410
|
$1,020.410
|
|
|
CONDUIT (PREPARE)
|
LF
|
2,005.000
|
$2.500
|
$2.540
|
$2.250
|
$4.080
|
$4.080
|
|
|
GROUND BOX (PREPARE)
|
EA
|
11.000
|
$450.000
|
$192.010
|
$170.000
|
$663.270
|
$663.270
|
|
|
INSTALL DMS (POLE MTD CABINET)
|
EA
|
1.000
|
$15,000.000
|
$14,344.610
|
$12,700.000
|
$21,428.570
|
$21,428.570
|
|
|
ITS POLE (40 FT)(90 MPH)
|
EA
|
2.000
|
$15,000.000
|
$13,102.180
|
$11,600.000
|
$15,306.120
|
$15,306.120
|
|
|
ITS POLE (50 FT)(90 MPH)
|
EA
|
1.000
|
$17,000.000
|
$15,812.960
|
$14,000.000
|
$18,877.550
|
$18,877.550
|
|
|
ITS POLE (60 FT)(90 MPH)
|
EA
|
2.000
|
$26,000.000
|
$26,091.380
|
$23,100.000
|
$27,040.820
|
$27,040.820
|
|
|
ITS POLE MNT CAB (TY 1)(CONF 1)
|
EA
|
1.000
|
$5,000.000
|
$5,082.720
|
$4,500.000
|
$5,306.120
|
$5,306.120
|
|
|
ITS POLE MNT CAB (TY 1)(CONF 1)(REM)
|
EA
|
1.000
|
$4,000.000
|
$395.310
|
$350.000
|
$816.330
|
$816.330
|
|
|
ITS POLE MNT CAB (TY 2)(CONF 1)
|
EA
|
4.000
|
$5,100.000
|
$5,986.330
|
$5,300.000
|
$6,122.450
|
$6,122.450
|
|
|
MODIFY EXISTING ELECTRICAL SERVICE
|
EA
|
2.000
|
$4,500.000
|
$361.440
|
$320.000
|
$3,571.430
|
$3,571.430
|
|
|
REMOVE EXIST FIB OPT DMS SYS(TY-3)
|
EA
|
1.000
|
$8,700.000
|
$9,148.930
|
$8,100.000
|
$13,265.310
|
$13,265.310
|
|
|
RELOCATE EXIST FIB OPT DMS SYS(TY-3)
|
EA
|
1.000
|
$5,000.000
|
$8,245.290
|
$7,300.000
|
$13,265.310
|
$13,265.310
|
|
|
ETHERNET SWITCH (INSTALL ONLY)
|
EA
|
6.000
|
$575.000
|
$688.990
|
$610.000
|
$714.290
|
$714.290
|
|
|
TERMINAL SERVER (INSTALL ONLY)
|
EA
|
5.000
|
$600.000
|
$655.100
|
$580.000
|
$1,326.530
|
$1,326.530
|
|
|
RADAR COMMUNICATION CABLE
|
LF
|
1,817.000
|
$3.000
|
$4.290
|
$3.800
|
$3.570
|
$3.570
|
|
|
TMA (STATIONARY)
|
DAY
|
234.000
|
$300.000
|
$268.910
|
$427.590
|
$348.650
|
$348.650
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
44.000
|
$395.000
|
$741.330
|
$419.500
|
$934.500
|
$934.500
|
|
|
ITS GND BOX(PCAST) TY 1 (243636)W/APRN
|
EA
|
8.000
|
$5,500.000
|
$8,132.380
|
$7,200.000
|
$6,122.450
|
$6,122.450
|
|
|
ITS GND BOX(PCAST) TY 2 (366036)W/APRN
|
EA
|
7.000
|
$7,800.000
|
$13,779.870
|
$12,200.000
|
$8,673.470
|
$8,673.470
|
|
|
BLUETOOTH DETECTION SYSTEM (INSTALL)
|
EA
|
2.000
|
$4,500.000
|
$1,242.450
|
$1,100.000
|
$4,387.760
|
$4,387.760
|
|
|
ITS RVSD (DATA COLLECT ONLY) SYS
|
EA
|
5.000
|
$16,000.000
|
$20,669.810
|
$18,300.000
|
$6,122.450
|
$6,122.450
|
|
|
LED WRONG WAY DRIVER SYSTEM
|
EA
|
1.000
|
$8,300.000
|
$93,409.420
|
$82,700.000
|
$8,163.270
|
$8,163.270
|
|
|
SAN SWR STRUCTURES (RECONSTRUCT EX MH)
|
EA
|
1.000
|
$15,000.000
|
$54,509.540
|
$48,260.000
|
$21,894.380
|
$21,894.380
|
|
|
SAN SWR BYPASS PUMPING (LARGE DIA)
|
LS
|
1.000
|
$20,000.000
|
$91,630.470
|
$81,125.000
|
$91,497.080
|
$91,497.080
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
1,299.000
|
$25.000
|
$16.940
|
$15.000
|
$78.060
|
$78.060
|
|
|
DUCTILE IRON FITTINGS
|
TON
|
7.010
|
$13,500.000
|
$15,852.500
|
$14,035.000
|
$21,838.140
|
$21,838.140
|
|
|
HYDROSTATIC PRESSURE TEST
|
EA
|
3.000
|
$10,000.000
|
$6,381.660
|
$5,650.000
|
$7,345.160
|
$7,345.160
|
|
|
TEMPORARY BLOW-OFF(COMPLETE)(2")
|
EA
|
3.000
|
$4,000.000
|
$6,215.630
|
$5,503.000
|
$2,149.590
|
$2,149.590
|
|
|
FLOWABLE FILL BACKFILL
|
CY
|
29.000
|
$300.000
|
$311.740
|
$550.000
|
$167.430
|
$167.430
|
|
|
GATE VALVE & BOX (COMPLETE)(16")
|
EA
|
2.000
|
$25,000.000
|
$16,306.550
|
$14,437.000
|
$14,647.320
|
$14,647.320
|
|
|
FIRE HYDRANT ASSEMBLY
|
EA
|
3.000
|
$10,000.000
|
$12,710.240
|
$11,253.000
|
$11,017.910
|
$11,017.910
|
|
|
TIE-IN (COMPLETE)(12")
|
EA
|
1.000
|
$6,000.000
|
$12,861.590
|
$11,387.000
|
$16,259.080
|
$16,259.080
|
|
|
TIE-IN (COMPLETE)(16")
|
EA
|
2.000
|
$10,000.000
|
$17,092.680
|
$15,133.000
|
$20,646.390
|
$20,646.390
|
|
|
PIPE WATER MAIN (PVC) (12")
|
LF
|
13.000
|
$250.000
|
$297.060
|
$263.000
|
$217.490
|
$217.490
|
|
|
PIPE WATER MAIN (PVC) (16")
|
LF
|
64.000
|
$400.000
|
$459.700
|
$407.000
|
$207.330
|
$207.330
|
|
|
AIR RELEASE VALVE (COMPLETE)(2")
|
EA
|
1.000
|
$5,000.000
|
$24,712.270
|
$21,879.000
|
$71,326.520
|
$71,326.520
|
|
|
WTR (JACK, BORE OR TUNNEL) (42")
|
LF
|
295.000
|
$1,000.000
|
$1,096.750
|
$971.000
|
$1,072.990
|
$1,072.990
|
|
|
STEEL CASING (42") (BORE)
|
LF
|
295.000
|
$600.000
|
$480.030
|
$425.000
|
$592.150
|
$592.150
|
|
|
TEMPORARY BLOW-OFF (COMPLETE)(4 IN)
|
EA
|
1.000
|
$10,000.000
|
$19,205.970
|
$17,004.000
|
$18,923.090
|
$18,923.090
|
|
|
PIPE WATER MAIN (PVC) (24")
|
LF
|
1,157.000
|
$445.000
|
$454.060
|
$402.000
|
$290.560
|
$290.560
|
|
|
BUTTERFLY VALVE AND BOX (COMPL) (24")
|
EA
|
2.000
|
$35,000.000
|
$49,464.070
|
$43,793.000
|
$47,501.620
|
$47,501.620
|
|
|
TIE-IN (COMPLETE) (24")
|
EA
|
1.000
|
$12,500.000
|
$21,111.440
|
$18,691.000
|
$32,885.830
|
$32,885.830
|
|
|
CARRIER PIPE (OPEN CUT) (PVC) (24")
|
LF
|
65.000
|
$500.000
|
$446.150
|
$395.000
|
$330.080
|
$330.080
|
|
|
STEEL CASING (42") (OPEN CUT)
|
LF
|
65.000
|
$600.000
|
$579.440
|
$513.000
|
$535.240
|
$535.240
|
|
|
GROUT ABANDONMENT WATER MAIN (24")
|
LF
|
281.000
|
$150.000
|
$86.980
|
$77.000
|
$90.620
|
$90.620
|
|
|
WATER MAIN REMOVAL (LARGER THAN 16")
|
LF
|
348.000
|
$200.000
|
$83.590
|
$74.000
|
$67.930
|
$67.930
|
|
|
CARRIER PIPE (BORE)(PVC)(24")
|
LF
|
295.000
|
$500.000
|
$448.410
|
$397.000
|
$295.820
|
$295.820
|
|
Totals: |
$100,496,655.940
|
$84,474,579.271
|
$86,680,972.016
|
$95,600,000.001
|
$95,600,000.001
|