County: BEXAR Highway: SH 218 Date: 07/09/2024 (4 months ago) Engineer's Estimate: $542,865 Control Number: 0465-01-063
Project: F 2B24(211) District: SAN ANTONIO Time: 131 WORKING DAYS Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $542,865.00
RARE EARTH LANDSCAPE SOLUTIONS LLC   $430,569.00 1
-20.69% | -$112,296.00
E-Z BEL CONSTRUCTION, LLC   $478,986.00 2
-11.77% | -$63,879.00
11.24% | $48,417.00
DAN WILLIAMS COMPANY   $491,986.00 3
-9.37% | -$50,879.00
14.26% | $61,417.00
2.71% | $13,000.00
CROSS PLUS CONSTRUCTION, LLC   $494,063.00 4
-8.99% | -$48,802.00
14.75% | $63,494.00
0.42% | $2,077.00
DIAMOND R CONTRACTING, LLC   $532,331.00 5
-1.94% | -$10,534.00
23.63% | $101,762.00
7.75% | $38,268.00
ICOS MANAGEMENT, LLC   $557,579.00 6
2.71% | $14,714.00
29.5% | $127,010.00
4.74% | $25,248.00
STX CIVIL   $570,026.00 7
5% | $27,161.00
32.39% | $139,457.00
2.23% | $12,447.00
DEAN WORD COMPANY, LTD.   $624,766.13 8
15.09% | $81,901.13
45.1% | $194,197.13
9.60% | $54,740.13
TIGHT LINE CONSTRUCTION, LLC   $750,880.00 9
38.32% | $208,015.00
74.39% | $320,311.00
20.19% | $126,113.87
FNH CONSTRUCTION, LLC   $975,355.00 10
79.67% | $432,490.00
126.53% | $544,786.00
29.89% | $224,475.00
Subcontractor Percentage Amount
SOUTH TEXAS TRAFFIC ALLIANCE INC. 1.85% $7,965.53
Total: 1.85% $7,965.53

Bid Items

Items: 13, 0 filtered
BEXAR SH 218  |  SAN ANTONIO  |  0465-01-063  |  07/09/2024  |  $542,865  |  F 2B24(211)  |  CONSTRUCT PEDESTRIAN INFRASTRUCT  |  131 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate RARE EARTH LANDSCAPE SOLUTIONS LLC E-Z BEL CONSTRUCTION, LLC DAN WILLIAMS COMPANY CROSS PLUS CONSTRUCTION, LLC DIAMOND R CONTRACTING, LLC ICOS MANAGEMENT, LLC STX CIVIL DEAN WORD COMPANY, LTD. TIGHT LINE CONSTRUCTION, LLC FNH CONSTRUCTION, LLC
104 6021 REMOVING CONC (CURB) LF 17.000 $11.000 $25.000 $1.000 $50.000 $99.000 $600.000 $165.000 $8.000 $132.980 $85.000 $100.000
192 6015 LANDSCAPE EDGE LF 600.000 $25.000 $10.000 $10.000 $20.000 $23.000 $50.000 $55.000 $20.000 $34.800 $35.000 $25.000
400 6008 CUT & RESTORE ASPH PAVING SY 60.000 $130.000 $150.000 $204.000 $160.000 $199.000 $450.000 $550.000 $250.000 $302.600 $125.000 $200.000
500 6001 MOBILIZATION LS 1.000 $71,148.000 $43,000.000 $40,000.000 $49,000.000 $40,000.000 $55,000.000 $48,000.000 $40,000.000 $30,000.000 $50,000.000 $90,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 9.000 $7,500.000 $7,815.000 $1,500.000 $2,500.000 $5,678.000 $3,000.000 $1.000 $2,500.000 $10,203.670 $4,000.000 $8,500.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 500.000 $6.000 $0.100 $7.000 $6.500 $12.000 $1.000 $2.000 $7.750 $12.000 $10.000 $18.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 500.000 $2.000 $0.050 $1.000 $1.150 $11.000 $1.000 $1.000 $1.000 $1.750 $1.000 $9.000
528 6004 LANDSCAPE PAVERS SY 3,877.000 $85.000 $68.000 $92.000 $93.000 $77.000 $77.000 $55.000 $115.000 $102.560 $150.000 $185.000
529 6002 CONC CURB (TY II) LF 17.000 $55.000 $59.000 $25.000 $70.000 $99.000 $500.000 $330.000 $20.000 $285.320 $100.000 $55.000
531 6001 CONC SIDEWALKS (4") SY 285.000 $110.000 $111.000 $110.000 $86.000 $143.000 $60.000 $660.000 $80.000 $110.590 $125.000 $85.000
531 6035 CURB RAMPS SY 27.000 $500.000 $150.000 $450.000 $150.000 $99.000 $2,000.000 $660.000 $200.000 $631.370 $280.000 $650.000
644 6068 RELOCATE SM RD SN SUP&AM TY 10BWG EA 2.000 $650.000 $700.000 $780.000 $1,400.000 $199.000 $1.000 $6,700.000 $450.000 $1,314.830 $500.000 $2,500.000
6185 6005 TMA (MOBILE OPERATION) DAY 2.000 $300.000 $5.000 $530.000 $550.000 $10,000.000 $2,000.000 $550.000 $360.000 $545.540 $1,000.000 $850.000
Totals: $542,865.00 $430,569.00 $478,986.00 $491,986.00 $494,063.00 $532,331.00 $557,579.00 $570,026.00 $624,766.13 $750,880.00 $975,355.00