Show Job Controls
Bid Cobra

BEXAR IH 37 (0073-08-193)

Items: 18

County: BEXAR
Length: N/A
Highway: IH 37
District: SAN ANTONIO
Control Number: 0073-08-193
DBE Goal: N/A
Project: NH 1802(204)
Guaranty: N/A
Time: 45 WORKING DAYS
Engineer's Estimate: $98,053.60
Date: 06/05/2018 (8 years ago)
Contract Number: N/A
Type: LANDSCAPE PLANTING AND IRRIGATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$98,053.60
Over/Under Est: 9.88% $9,684.30
Over/Under Est: 12.12% $11,884.90
Amt Left: 2.04% $2,200.60
Over/Under Est: 16.47% $16,150.40
Amt Left: 6% $6,466.10
Delta: -3.88% -$4,265.50
Over/Under Est: 64.53% $63,277.40
Amt Left: 49.74% $53,593.10
Delta: -41.27% -$47,127.00
Over/Under Est: 121.4% $119,036.10
Amt Left: 101.5% $109,351.80
Delta: -34.56% -$55,758.70

Bid Items & Bid Tabulations

18 Total 0 of 18
BEXAR  |  IH 37  |  SAN ANTONIO  |  0073-08-193  |  06/05/2018  |  $98,053.60  |  NH 1802(204)  |  LANDSCAPE PLANTING AND IRRIGATION  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
NEW BRAUNFELS CONTRACTING, LLC
ENCINO LANDSCAPE, INC.
APEX LANDSCAPE & IRRIGATION, LLC
THOMAS 11 DEVELOPMENT LLC
REMOVING CONC (MEDIANS)
SY 347.000 $15.000 $42.975 $20.000 $30.000 $35.000 $25.000
EXCAVATION (SPECIAL)
CY 135.700 $18.000 $88.536 $25.000 $20.000 $35.000 $35.000
COMPOST MANUF TOPSOIL
CY 135.700 $30.000 $49.128 $45.000 $50.000 $45.000 $36.000
GENERAL USE COMPOST (4")
SY 290.000 $4.000 $13.914 $7.000 $5.000 $5.000 $35.000
IRRIGATION SYSTEM
LS 1.000 $30,000.000 $15,438.596 $40,000.000 $30,000.000 $45,000.000 $45,000.000
PLANT MATERIAL (1-GAL)
EA 552.000 $12.000 $17.321 $15.000 $10.000 $10.000 $50.000
PLANT MATERIAL (5-GAL)
EA 64.000 $30.000 $17.105 $40.000 $30.000 $30.000 $100.000
PLANT MATERIAL (30-GAL)
EA 10.000 $235.000 $263.158 $175.000 $300.000 $250.000 $500.000
PLANT MATERIAL (45-GAL)
EA 2.000 $365.000 $478.070 $350.000 $400.000 $375.000 $900.000
MULCH
SY 637.000 $3.000 $18.728 $11.000 $5.000 $5.000 $25.000
PLANT BED PREPARATION
SY 290.000 $3.000 $29.473 $25.000 $1.000 $5.000 $20.000
PLANT MAINTENANCE
MO 12.000 $1,200.000 $833.333 $1,000.000 $1,000.000 $3,000.000 $2,500.000
MOBILIZATION
LS 1.000 $6,300.000 $1,403.509 $1,000.000 $25,000.000 $15,000.000 $18,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $3,000.000 $362.573 $1,200.000 $3,000.000 $4,000.000 $2,000.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 90.000 $5.000 $14.620 $8.500 $10.000 $1.000 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 90.000 $2.000 $10.541 $1.000 $1.000 $1.000 $5.000
LOOSE AGGR FOR GROUNDCOVER (TYPE I)
CY 5.500 $80.000 $472.089 $85.000 $200.000 $250.000 $150.000
TMA (STATIONARY)
DAY 40.000 $250.000 $64.956 $150.000 $1.000 $300.000 $630.000
Totals: $98,053.600 $107,737.967 $109,938.500 $114,204.000 $161,331.000 $217,089.700