BEXAR IH 10 (0072-12-197)
Items: 57
County: BEXAR
Length: N/A
Highway: IH 10
District: SAN ANTONIO
Control Number: 0072-12-197
DBE Goal: N/A
Project: NH 2017(560)
Guaranty: N/A
Time: 59 WORKING DAYS
Engineer's Estimate: $1,429,099.25
Date: 02/02/2017 (9 years ago)
Contract Number: N/A
Type: OVERLAY & PAVEMENT MARKINGS ON EB FRONTAGE ROAD
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,429,099.25 | |||
| $1,177,187.95 |
-17.63%
-$251,911.30
|
|||
| $1,218,506.79 |
-14.74%
-$210,592.46
|
3.51%
$41,318.84
|
||
| $1,302,478.83 |
-8.86%
-$126,620.42
|
10.64%
$125,290.88
|
-6.89%
-$83,972.04
|
|
| $1,396,127.90 |
-2.31%
-$32,971.35
|
18.6%
$218,939.95
|
-7.19%
-$93,649.07
|
E
Engineer's Estimate
$1,429,099.25
1
Awarded
$1,177,187.95
Over/Under Est:
-17.63%
-$251,911.30
$1,218,506.79
Over/Under Est:
-14.74%
-$210,592.46
Amt Left:
3.51%
$41,318.84
$1,302,478.83
Over/Under Est:
-8.86%
-$126,620.42
Amt Left:
10.64%
$125,290.88
Delta:
-6.89%
-$83,972.04
$1,396,127.90
Over/Under Est:
-2.31%
-$32,971.35
Amt Left:
18.6%
$218,939.95
Delta:
-7.19%
-$93,649.07
Bid Items & Bid Tabulations
57
Total
0 of 57