Job Info for 0025-02-225

County: BEXAR Highway: IH 10 Date: 03/07/2023 (1 year ago) Engineer's Estimate: $2,246,524 Control Number: 0025-02-225
Project: STP 2023(502)HES District: SAN ANTONIO Time: 96 WORKING DAYS Type: HAZARD ELIMINATION & SAFETY
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10
Plans: Plans | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,246,523.56
D&G ENERGY CORPORATION   $1,631,615.00 1
-27.37% | -$614,908.56
THE LEVY COMPANY, INC.   $1,754,871.17 2
-21.89% | -$491,652.39
7.55% | $123,256.17
ELECNOR BELCO ELECTRIC, INC.   $1,799,235.00 3
-19.91% | -$447,288.56
10.27% | $167,620.00
2.53% | $44,363.83
VACA UNDERGROUND UTILITIES INC   $1,830,850.00 4
-18.5% | -$415,673.56
12.21% | $199,235.00
1.76% | $31,615.00
E-Z BEL CONSTRUCTION, LLC   $1,842,310.00 5
-17.99% | -$404,213.56
12.91% | $210,695.00
0.63% | $11,460.00
LIGHT IT UP ELECTRIC   $1,975,094.00 6
-12.08% | -$271,429.56
21.05% | $343,479.00
7.21% | $132,784.00
THIRD COAST SERVICES LLC   $2,097,985.00 7
-6.61% | -$148,538.56
28.58% | $466,370.00
6.22% | $122,891.00

Bid Items

Items: 12, 0 filtered
BEXAR IH 10  |  SAN ANTONIO  |  0025-02-225  |  03/07/2023  |  $2,246,524  |  STP 2023(502)HES  |  HAZARD ELIM & SAFETY  |  96 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate D&G ENERGY CORPORATION THE LEVY COMPANY, INC. ELECNOR BELCO ELECTRIC, INC. VACA UNDERGROUND UTILITIES INC E-Z BEL CONSTRUCTION, LLC LIGHT IT UP ELECTRIC THIRD COAST SERVICES LLC
432 6001 RIPRAP (CONC)(4 IN) CY 1.000 $477.950 $930.000 $502.520 $2,275.000 $1,200.000 $950.000 $4,600.000 $1,000.000
432 6006 RIPRAP (CONC)(CL B) CY 5.000 $477.950 $540.000 $502.500 $910.000 $800.000 $950.000 $1,140.000 $1,000.000
500 6001 MOBILIZATION LS 1.000 $204,229.410 $100,000.000 $65,307.570 $11,880.000 $100,000.000 $50,000.000 $20,000.000 $209,750.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $9,253.160 $2,500.000 $11,074.670 $3,900.000 $3,000.000 $7,500.000 $6,325.000 $8,000.000
618 6023 CONDT (PVC) (SCH 40) (2") LF 900.000 $14.660 $13.000 $13.430 $36.000 $20.000 $25.000 $25.300 $21.000
636 6001 ALUMINUM SIGNS (TY A) SF 24.000 $37.160 $25.000 $29.030 $45.000 $50.000 $65.000 $28.750 $40.000
644 6033 IN SM RD SN SUP&AM TYS80(1)SA(U) EA 20.000 $1,021.750 $1,325.000 $910.940 $1,500.000 $650.000 $1,000.000 $1,988.350 $900.000
644 6068 RELOCATE SM RD SN SUP&AM TY 10BWG EA 1.000 $526.250 $485.000 $776.480 $2,100.000 $650.000 $350.000 $1,150.000 $805.000
644 6078 REMOVE SM RD SN SUP&AM (SIGN ONLY) EA 18.000 $105.000 $50.000 $58.220 $225.000 $100.000 $150.000 $200.000 $275.000
687 6001 PED POLE ASSEMBLY EA 40.000 $2,233.570 $2,000.000 $2,696.340 $2,600.000 $2,600.000 $2,600.000 $1,926.250 $2,900.000
6185 6002 TMA (STATIONARY) DAY 60.000 $210.460 $180.000 $206.910 $225.000 $150.000 $250.000 $265.650 $265.000
6414 6001 WIRELESS WWD SYSTEM EA 20.000 $92,250.000 $69,100.000 $73,350.270 $78,500.000 $78,000.000 $78,775.000 $87,293.900 $82,936.000
Totals: $2,246,523.56 $1,631,615.00 $1,754,871.17 $1,799,235.00 $1,830,850.00 $1,842,310.00 $1,975,094.00 $2,097,985.00