County: BEXAR Highway: IH 10 Date: 08/07/2019 (5 years ago) Engineer's Estimate: $1,218,003 Control Number: 0025-02-223
Project: STP 1902(318) District: SAN ANTONIO Time: 125 WORKING DAYS Type: LANDSCAPE & SCENIC ENHANCEMENT

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,218,003.28
TIGHT LINE CONSTRUCTION, LLC   $1,049,982.00 1
-13.79% | -$168,021.28
APEX LANDSCAPE & IRRIGATION, LLC   $1,050,362.75 2
-13.76% | -$167,640.53
0.04% | $380.75
ENCINO LANDSCAPE, INC.   $1,073,043.55 3
-11.9% | -$144,959.73
2.2% | $23,061.55
2.16% | $22,680.80
YELLOWSTONE LANDSCAPE - CENTRAL, INC.   $1,362,036.65 4
11.83% | $144,033.37
29.72% | $312,054.65
26.93% | $288,993.10

Bid Items

Items: 17, 0 filtered
BEXAR IH 10  |  SAN ANTONIO  |  0025-02-223  |  08/07/2019  |  $1,218,003  |  STP 1902(318)  |  LANDSCAPE & SCENIC ENHAN  |  125 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate TIGHT LINE CONSTRUCTION, LLC APEX LANDSCAPE & IRRIGATION, LLC ENCINO LANDSCAPE, INC. YELLOWSTONE LANDSCAPE - CENTRAL, INC.
100 6014 PREPARING ROW (TREE)(20" TO 42" DIA) EA 12.000 $2,500.000 $1,250.000 $350.000 $1,000.000 $1,495.726
161 6012 GENERAL USE COMPOST CY 3,966.000 $35.000 $22.000 $16.500 $25.000 $21.642
170 6001 IRRIGATION SYSTEM LS 1.000 $96,000.000 $120,000.000 $106,500.000 $100,000.000 $99,635.791
192 6004 PLANT MATERIAL (5-GAL) EA 40.000 $30.000 $50.000 $30.000 $30.000 $14.957
192 6005 PLANT MATERIAL (15-GAL) EA 2,066.000 $124.000 $115.000 $130.000 $115.000 $115.836
192 6006 PLANT MATERIAL (30-GAL) EA 702.000 $220.000 $220.000 $225.000 $220.000 $216.719
192 6007 PLANT MATERIAL (45-GAL) EA 46.000 $370.000 $395.000 $360.000 $400.000 $427.350
192 6013 MULCH SY 35,698.000 $3.500 $3.000 $3.000 $3.000 $2.011
192 6016 PLANT BED PREPARATION SY 35,698.000 $3.000 $2.000 $1.250 $2.000 $0.407
192 6049 PLANT MATERIAL (MIN 4' TRNK HT) (PALM) EA 37.000 $300.000 $400.000 $300.000 $400.000 $953.162
193 6001 PLANT MAINTENANCE MO 36.000 $2,500.000 $1,000.000 $2,500.000 $1,500.000 $8,173.168
193 6007 IRRIGATION SYSTEM OPER AND MAINT MO 36.000 $1,500.000 $1,000.000 $1,000.000 $1,000.000 $3,659.092
500 6001 MOBILIZATION LS 1.000 $88,237.280 $125,000.000 $105,500.000 $120,000.000 $136,153.846
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 8.000 $3,000.000 $2,000.000 $4,000.000 $3,000.000 $1,346.667
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 2,295.000 $4.000 $3.000 $1.300 $10.000 $3.563
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 2,295.000 $1.000 $1.000 $0.250 $0.010 $0.332
6185 6002 TMA (STATIONARY) DAY 60.000 $225.000 $1.000 $1.000 $0.010 $724.957
Totals: $1,218,003.28 $1,049,982.00 $1,050,362.75 $1,073,043.55 $1,362,036.71