BEXAR US 90 (0024-07-063)
Items: 103
County: BEXAR
Length: N/A
Highway: US 90
District: SAN ANTONIO
Control Number: 0024-07-063
DBE Goal: N/A
Project: F 2021(778)
Guaranty: N/A
Time: 125 WORKING DAYS
Engineer's Estimate: $2,508,772.56
Date: 08/05/2021 (4 years ago)
Contract Number: N/A
Type: INTERSECTION IMPROVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (11)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,508,772.56 | |||
| $2,885,970.95 |
15.04%
$377,198.39
|
|||
| $2,907,080.22 |
15.88%
$398,307.66
|
0.73%
$21,109.27
|
||
| $3,055,086.65 |
21.78%
$546,314.09
|
5.86%
$169,115.70
|
-5.09%
-$148,006.43
|
|
| $3,077,905.71 |
22.69%
$569,133.15
|
6.65%
$191,934.76
|
-0.75%
-$22,819.06
|
|
| $3,196,979.94 |
27.43%
$688,207.38
|
10.78%
$311,008.99
|
-3.87%
-$119,074.23
|
|
| $3,232,754.63 |
28.86%
$723,982.07
|
12.02%
$346,783.68
|
-1.12%
-$35,774.69
|
|
| $3,269,110.65 |
30.31%
$760,338.09
|
13.28%
$383,139.70
|
-1.12%
-$36,356.02
|
|
| $3,301,369.35 |
31.59%
$792,596.79
|
14.39%
$415,398.40
|
-0.99%
-$32,258.70
|
|
| $3,446,931.10 |
37.4%
$938,158.54
|
19.44%
$560,960.15
|
-4.41%
-$145,561.75
|
|
| $3,616,426.79 |
44.15%
$1,107,654.23
|
25.31%
$730,455.84
|
-4.92%
-$169,495.69
|
|
| $3,695,633.84 |
47.31%
$1,186,861.28
|
28.06%
$809,662.89
|
-2.19%
-$79,207.05
|
E
Engineer's Estimate
$2,508,772.56
1
Awarded
$2,885,970.95
Over/Under Est:
15.04%
$377,198.39
$2,907,080.22
Over/Under Est:
15.88%
$398,307.66
Amt Left:
0.73%
$21,109.27
$3,055,086.65
Over/Under Est:
21.78%
$546,314.09
Amt Left:
5.86%
$169,115.70
Delta:
-5.09%
-$148,006.43
$3,077,905.71
Over/Under Est:
22.69%
$569,133.15
Amt Left:
6.65%
$191,934.76
Delta:
-0.75%
-$22,819.06
$3,196,979.94
Over/Under Est:
27.43%
$688,207.38
Amt Left:
10.78%
$311,008.99
Delta:
-3.87%
-$119,074.23
$3,232,754.63
Over/Under Est:
28.86%
$723,982.07
Amt Left:
12.02%
$346,783.68
Delta:
-1.12%
-$35,774.69
$3,269,110.65
Over/Under Est:
30.31%
$760,338.09
Amt Left:
13.28%
$383,139.70
Delta:
-1.12%
-$36,356.02
$3,301,369.35
Over/Under Est:
31.59%
$792,596.79
Amt Left:
14.39%
$415,398.40
Delta:
-0.99%
-$32,258.70
$3,446,931.10
Over/Under Est:
37.4%
$938,158.54
Amt Left:
19.44%
$560,960.15
Delta:
-4.41%
-$145,561.75
$3,616,426.79
Over/Under Est:
44.15%
$1,107,654.23
Amt Left:
25.31%
$730,455.84
Delta:
-4.92%
-$169,495.69
$3,695,633.84
Over/Under Est:
47.31%
$1,186,861.28
Amt Left:
28.06%
$809,662.89
Delta:
-2.19%
-$79,207.05