Job Info for 0017-09-111

County: BEXAR Highway: IH 35 Date: 04/06/2022 (2 years ago) Engineer's Estimate: $2,543,232 Control Number: 0017-09-111
Project: STP 2022(432)HES District: SAN ANTONIO Time: 176 WORKING DAYS Type: HAZARD ELIMINATION & SAFETY
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $2,543,232.04
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.   $2,720,941.84 1
6.99% | $177,709.80
E-Z BEL CONSTRUCTION, LLC   $2,837,695.95 2
11.58% | $294,463.91
4.29% | $116,754.11
3LW CIVIL LLC   $2,874,990.71 3
13.04% | $331,758.67
5.66% | $154,048.87
1.31% | $37,294.76
SCR CIVIL CONSTRUCTION, LLC   $2,877,867.55 4
13.16% | $334,635.51
5.77% | $156,925.71
0.10% | $2,876.84
DAN WILLIAMS COMPANY   $2,956,018.15 5
16.23% | $412,786.11
8.64% | $235,076.31
2.72% | $78,150.60
MICA CORPORATION   $3,224,516.67 6
26.79% | $681,284.63
18.51% | $503,574.83
9.08% | $268,498.52
ALTUS CONSTRUCTION LLC   $3,339,612.11 7
31.31% | $796,380.07
22.74% | $618,670.27
3.57% | $115,095.44
VECTOR UTILITIES LLC   $3,530,363.46 8
38.81% | $987,131.42
29.75% | $809,421.62
5.71% | $190,751.35
Subcontractor Percentage Amount
ROADWAY SPECIALTIES, INC. 32.03% $871,517.67
KHONSU ENTERPRISE LLC 8.81% $239,714.98
LONE STAR EROSION CONTROL 1.94% $52,786.27
BARRICADES UNLIMITED 0.79% $21,495.44
Total: 43.57% $1,185,514.36

Bid Items

Items: 31, 0 filtered
BEXAR IH 35  |  SAN ANTONIO  |  0017-09-111  |  04/06/2022  |  $2,543,232  |  STP 2022(432)HES  |  HAZARD ELIM & SAFETY  |  176 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. E-Z BEL CONSTRUCTION, LLC 3LW CIVIL LLC SCR CIVIL CONSTRUCTION, LLC DAN WILLIAMS COMPANY MICA CORPORATION ALTUS CONSTRUCTION LLC VECTOR UTILITIES LLC
132 6021 EMBANKMENT (VEHICLE)(ORD COMP)(TY C) CY 105.000 $19.990 $34.400 $40.000 $35.000 $15.000 $55.000 $52.500 $212.780 $202.020
150 6002 BLADING HR 19.000 $124.530 $169.430 $200.000 $300.000 $285.000 $120.000 $210.000 $656.540 $103.980
416 6029 DRILL SHAFT (RDWY ILL POLE) (30 IN) LF 1,004.000 $254.220 $190.000 $240.000 $199.000 $275.000 $300.000 $263.850 $256.050 $314.360
432 6001 RIPRAP (CONC)(4 IN) CY 1.400 $411.150 $624.300 $600.000 $1,000.000 $1,200.000 $1,500.000 $3,063.000 $865.030 $247.390
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 1,019.000 $438.290 $479.440 $480.000 $485.000 $580.000 $335.000 $427.900 $432.520 $647.020
500 6001 MOBILIZATION LS 1.000 $226,000.000 $206,756.830 $200,000.000 $310,000.000 $110,000.000 $290,000.000 $241,110.000 $328,267.990 $148,275.260
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 11.000 $7,300.000 $4,352.660 $5,000.000 $18,000.000 $8,200.000 $15,000.000 $17,975.000 $19,696.080 $3,207.710
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 15,543.000 $2.400 $4.590 $2.250 $1.000 $4.200 $2.500 $3.950 $2.570 $5.770
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 15,543.000 $0.570 $0.740 $0.600 $0.400 $0.450 $0.500 $0.420 $0.660 $2.310
543 6001 CABLE BARRIER SYSTEM (TL-3) LF 15,950.000 $12.870 $18.190 $17.000 $16.250 $14.050 $12.500 $15.060 $16.670 $16.340
543 6002 CABLE BARRIER SYSTEM (TL-4) LF 9,555.000 $9.740 $18.560 $17.000 $16.250 $14.120 $13.500 $15.400 $17.400 $17.450
543 6019 CABLE BARRIER TERMINAL SECTION (TL-3) EA 27.000 $2,694.310 $3,408.730 $3,600.000 $3,492.000 $3,000.000 $3,500.000 $3,059.000 $3,742.940 $3,178.220
543 6020 CABLE BARRIER TERMINAL SECTION (TL-4) EA 4.000 $2,261.920 $3,431.730 $3,600.000 $3,400.000 $3,150.000 $3,500.000 $3,080.000 $5,292.270 $4,178.950
610 6104 IN RD IL (U/P) (TY 1) (150W EQ) LED EA 2.000 $1,332.880 $1,172.600 $1,500.000 $1,600.000 $1,790.000 $1,250.000 $1,675.000 $2,100.920 $1,424.230
610 6216 IN RD IL (TY SA) 40T-10 (250W EQ) LED EA 63.000 $3,730.820 $3,716.650 $4,150.000 $4,125.000 $4,580.000 $4,500.000 $3,921.000 $5,383.600 $5,036.100
610 6288 IN RD IL (TY SA) 50T-10 (400W EQ) LED EA 17.000 $3,949.870 $4,322.950 $4,900.000 $4,700.000 $5,255.000 $5,500.000 $4,430.000 $6,171.440 $6,222.950
610 6289 IN RD IL (TY SA) 50T-10-10(400W EQ)LED EA 36.000 $4,141.990 $5,823.950 $5,975.000 $6,220.000 $6,925.000 $6,500.000 $5,464.000 $8,141.050 $7,127.530
618 6023 CONDT (PVC) (SCH 40) (2") LF 12,435.000 $11.440 $11.300 $13.000 $9.000 $10.050 $12.000 $19.670 $11.820 $16.040
618 6046 CONDT (PVC) (SCH 80) (2") LF 12,061.000 $13.440 $13.630 $16.000 $12.100 $13.400 $16.000 $22.450 $15.760 $21.170
618 6047 CONDT (PVC) (SCH 80) (2") (BORE) LF 1,932.000 $25.850 $18.920 $26.000 $21.500 $23.500 $41.000 $45.050 $27.570 $53.250
620 6003 ELEC CONDR (NO.12) BARE LF 50.000 $0.900 $3.030 $3.000 $1.150 $1.300 $1.750 $1.350 $1.510 $2.440
620 6004 ELEC CONDR (NO.12) INSULATED LF 100.000 $1.070 $3.210 $3.000 $1.150 $1.300 $1.750 $1.550 $1.510 $2.440
620 6007 ELEC CONDR (NO.8) BARE LF 27,209.000 $1.330 $1.290 $1.500 $1.200 $1.350 $1.450 $1.760 $1.580 $2.440
620 6008 ELEC CONDR (NO.8) INSULATED LF 55,658.000 $1.550 $1.390 $1.550 $1.220 $1.350 $1.450 $1.890 $1.580 $2.440
620 6009 ELEC CONDR (NO.6) BARE LF 158.000 $1.590 $2.370 $3.000 $1.650 $1.850 $1.000 $2.200 $2.170 $1.410
620 6010 ELEC CONDR (NO.6) INSULATED LF 316.000 $2.230 $2.420 $3.000 $1.650 $1.850 $1.000 $2.250 $2.170 $1.410
624 6002 GROUND BOX TY A (122311)W/APRON EA 35.000 $960.980 $948.850 $875.000 $966.000 $1,080.000 $1,200.000 $1,500.000 $1,267.110 $1,315.160
628 6011 ELC SRV TY A 120/240 060(NS)SS(E)TP(O) EA 5.000 $6,200.000 $5,989.500 $6,000.000 $5,500.000 $6,150.000 $8,500.000 $7,315.000 $7,221.900 $8,083.420
628 6056 ELC SRV TY A 240/480 060(SS)SS(E)TP(O) EA 5.000 $8,050.000 $6,443.750 $6,000.000 $5,000.000 $5,600.000 $8,500.000 $7,440.000 $7,221.900 $8,789.120
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 50.000 $84.630 $108.230 $80.000 $200.000 $115.000 $200.000 $119.050 $98.490 $513.230
6185 6002 TMA (STATIONARY) DAY 360.000 $174.420 $131.230 $175.000 $150.000 $275.000 $200.000 $303.850 $196.960 $259.470
Totals: $2,543,232.04 $2,720,941.84 $2,837,695.95 $2,874,990.71 $2,877,867.55 $2,956,018.15 $3,224,516.67 $3,339,612.11 $3,530,363.47