Job Info for 0017-09-105

County: BEXAR Highway: IH 35 Date: 07/09/2019 (5 years ago) Engineer's Estimate: $727,467 Control Number: 0017-09-105
Project: NH 1902(205) District: SAN ANTONIO Time: 100 WORKING DAYS Type: LANDSCAPE DEVELOPMENT

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $727,466.85
ENCINO LANDSCAPE, INC.   $641,593.00 1
-11.8% | -$85,873.85
TIGHT LINE CONSTRUCTION, LLC   $649,893.00 2
-10.66% | -$77,573.85
1.29% | $8,300.00
APEX LANDSCAPE & IRRIGATION, LLC   $725,332.05 3
-0.29% | -$2,134.80
13.05% | $83,739.05
11.61% | $75,439.05
YELLOWSTONE LANDSCAPE - CENTRAL, INC.   $839,940.37 4
15.46% | $112,473.52
30.91% | $198,347.37
15.80% | $114,608.32
CENTRAL NORTH CONSTRUCTION, LLC   $1,935,596.50 5
166.07% | $1,208,129.65
201.69% | $1,294,003.50
130.44% | $1,095,656.13

Bid Items

Items: 17, 0 filtered
BEXAR IH 35  |  SAN ANTONIO  |  0017-09-105  |  07/09/2019  |  $727,467  |  NH 1902(205)  |  LANDSCAPE DEVELOPMENT  |  100 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate ENCINO LANDSCAPE, INC. TIGHT LINE CONSTRUCTION, LLC APEX LANDSCAPE & IRRIGATION, LLC YELLOWSTONE LANDSCAPE - CENTRAL, INC. CENTRAL NORTH CONSTRUCTION, LLC
161 6012 GENERAL USE COMPOST CY 1,604.000 $35.000 $3.000 $22.000 $40.000 $27.344 $35.000
170 6001 IRRIGATION SYSTEM LS 1.000 $85,000.000 $100,000.000 $80,000.000 $90,000.000 $70,762.281 $325,000.000
192 6004 PLANT MATERIAL (5-GAL) EA 600.000 $25.000 $30.000 $30.000 $30.000 $19.883 $45.000
192 6005 PLANT MATERIAL (15-GAL) EA 1,335.000 $120.000 $125.000 $120.000 $130.000 $115.645 $150.000
192 6006 PLANT MATERIAL (30-GAL) EA 220.000 $250.000 $225.000 $225.000 $225.000 $215.311 $450.000
192 6007 PLANT MATERIAL (45-GAL) EA 87.000 $370.000 $400.000 $450.000 $350.000 $433.555 $750.000
192 6013 MULCH SY 14,431.000 $3.250 $3.000 $3.000 $3.300 $3.769 $6.500
192 6016 PLANT BED PREPARATION SY 14,431.000 $3.000 $2.000 $2.000 $2.250 $0.525 $5.000
192 6025 PLANT MATERIAL (45 GAL) (TREE) EA 6.000 $400.000 $400.000 $450.000 $360.000 $350.877 $5,000.000
192 6049 PLANT MATERIAL (MIN 4' TRNK HT) (PALM) EA 18.000 $300.000 $400.000 $425.000 $300.000 $925.926 $5,000.000
193 6001 PLANT MAINTENANCE MO 36.000 $2,490.000 $1,500.000 $1,000.000 $2,000.000 $4,711.415 $8,500.000
193 6007 IRRIGATION SYSTEM OPER AND MAINT MO 36.000 $1,500.000 $500.000 $1,000.000 $1,000.000 $2,589.292 $3,500.000
500 6001 MOBILIZATION LS 1.000 $52,553.100 $95,000.000 $100,000.000 $75,000.000 $84,561.404 $200,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 6.000 $3,000.000 $3,000.000 $2,000.000 $4,000.000 $1,315.789 $10,500.000
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 100.000 $4.000 $8.000 $10.000 $0.100 $4.489 $35.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 100.000 $1.000 $0.010 $2.000 $0.100 $2.439 $35.000
6185 6002 TMA (STATIONARY) DAY 50.000 $225.000 $1.000 $1.000 $100.000 $744.035 $3,500.000
Totals: $727,466.85 $641,593.00 $649,893.00 $725,332.05 $839,940.42 $1,935,596.50