Job Info for 0017-09-104

County: BEXAR Highway: IH 35 Date: 05/02/2018 (6 years ago) Engineer's Estimate: $386,094 Control Number: 0017-09-104
Project: NH 2018(801) District: SAN ANTONIO Time: 56 WORKING DAYS Type: LANDSCAPE PLANTING AND IRRIGATION

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $386,093.55
APEX LANDSCAPE & IRRIGATION, LLC   $482,084.04 1
24.86% | $95,990.49
ENCINO LANDSCAPE, INC.   $482,443.00 2
24.95% | $96,349.45
0.07% | $358.96
YELLOWSTONE LANDSCAPE - CENTRAL, INC.   $511,447.01 3
32.47% | $125,353.46
6.09% | $29,362.97
6.01% | $29,004.01

Bid Items

Items: 21, 0 filtered
BEXAR IH 35  |  SAN ANTONIO  |  0017-09-104  |  05/02/2018  |  $386,094  |  NH 2018(801)  |  LANDSCAPE PLANTING AND IRRIGATION  |  56 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate APEX LANDSCAPE & IRRIGATION, LLC ENCINO LANDSCAPE, INC. YELLOWSTONE LANDSCAPE - CENTRAL, INC.
110 6003 EXCAVATION (SPECIAL) CY 622.500 $25.000 $20.000 $15.000 $58.115
161 6012 GENERAL USE COMPOST CY 516.500 $30.000 $35.000 $30.000 $48.403
170 6001 IRRIGATION SYSTEM LS 1.000 $59,000.000 $75,000.000 $60,000.000 $55,625.000
192 6003 PLANT MATERIAL (3-GAL) EA 522.000 $20.000 $25.000 $60.000 $31.566
192 6004 PLANT MATERIAL (5-GAL) EA 3,071.000 $30.000 $30.000 $30.000 $19.129
192 6005 PLANT MATERIAL (15-GAL) EA 50.000 $125.000 $125.000 $100.000 $116.820
192 6013 MULCH SY 5,128.500 $3.000 $4.000 $4.000 $1.716
192 6016 PLANT BED PREPARATION SY 5,196.500 $1.500 $2.500 $3.000 $0.221
192 6071 PLANT MATERIAL (10-GAL) EA 33.000 $130.000 $50.000 $100.000 $101.117
193 6001 PLANT MAINTENANCE MO 12.000 $1,200.000 $2,500.000 $1,000.000 $2,382.568
193 6004 PLANT REPLACEMENT (3-GAL) EA 5.000 $20.000 $1.000 $30.000 $80.025
193 6005 PLANT REPLACEMENT (5-GAL) EA 5.000 $30.000 $1.000 $30.000 $123.367
193 6007 IRRIGATION SYSTEM OPER AND MAINT MO 12.000 $1,200.000 $1,000.000 $1,000.000 $1,596.857
193 6009 PLANT REPLACEMENT (15 GAL) EA 5.000 $125.000 $1.000 $100.000 $205.067
427 6002 CONCRETE PAINT FINISH SF 10,201.000 $0.800 $0.790 $1.000 $1.448
500 6001 MOBILIZATION LS 1.000 $25,000.000 $35,000.000 $52,000.000 $50,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 4.000 $2,160.000 $5,000.000 $3,000.000 $2,041.667
506 6040 BIODEG EROSN CONT LOGS (INSTL) (8") LF 50.000 $4.000 $1.000 $6.000 $12.337
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 50.000 $1.200 $1.000 $1.000 $2.835
1005 6001 LOOSE AGGR FOR GROUNDCOVER (TYPE I) CY 1,303.500 $60.000 $85.000 $100.000 $132.058
6185 6002 TMA (STATIONARY) DAY 56.000 $175.000 $250.000 $1.000 $83.333
Totals: $386,093.55 $482,084.04 $482,443.00 $511,447.10