BELL SH 195 (0836-02-073)

Items: 107

County: BELL
Length: N/A
Highway: SH 195
District: WACO
Control Number: 0836-02-073
DBE Goal: N/A
Project: STP 2019(835)MM
Guaranty: N/A
Time: 75 WORKING DAYS
Engineer's Estimate: $7,343,909.75
Date: 05/08/2019 (7 years ago)
Contract Number: N/A
Type: TRNARND UNDRPS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$7,343,909.75
$8,482,505.85
Over/Under Est: 15.5% $1,138,596.10
Over/Under Est: 18.88% $1,386,818.80
Amt Left: 2.93% $248,222.70
$9,029,880.62
Over/Under Est: 22.96% $1,685,970.87
Amt Left: 6.45% $547,374.77
Delta: -3.43% -$299,152.07
Over/Under Est: 23.89% $1,754,764.11
Amt Left: 7.26% $616,168.01
Delta: -0.76% -$68,793.24

Bid Items & Bid Tabulations

107 Total 0 of 107
BELL  |  SH 195  |  WACO  |  0836-02-073  |  05/08/2019  |  $7,343,909.75  |  STP 2019(835)MM  |  TRNARND UNDRPS  |  75 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TEXAS MATERIALS GROUP, INC.
BIG CREEK CONSTRUCTION, LTD.
AUSTIN MATERIALS, LLC
LONE STAR PAVING COMPANY
REMOVING CONC (RIPRAP)
SY 338.000 $25.000 $11.000 $16.000 $9.200 $9.000
REMOVING CONC (CURB AND GUTTER)
LF 841.000 $10.000 $11.000 $6.000 $9.200 $9.000
REMOVING STAB BASE AND ASPH PAV (2"-6")
CY 156.000 $15.000 $20.000 $15.000 $8.000 $58.000
REMOVING STAB BASE AND ASPH PAV (0-4")
SY 3,001.000 $15.000 $7.000 $7.000 $23.000 $5.250
EXCAVATION (ROADWAY)
CY 2,627.000 $15.000 $20.000 $12.500 $20.500 $21.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 44.000 $30.000 $55.000 $12.500 $56.000 $57.000
BACKFILL (TY A)
STA 150.000 $150.000 $76.000 $200.000 $255.000 $115.000
BLADING
STA 1.000 $100.000 $5,000.000 $1,000.000 $2,000.000 $160.000
FURNISHING AND PLACING TOPSOIL (4")
SY 550.000 $1.000 $5.000 $5.000 $10.000 $12.500
BLOCK SODDING
SY 4,500.000 $5.000 $5.500 $5.000 $3.550 $3.500
VEGETATIVE WATERING
MG 36.800 $12.000 $40.000 $15.000 $100.000 $100.000
D-GR HMA(SQ) TY-B PG64-22
TON 1,117.000 $100.000 $85.000 $100.000 $94.000 $90.000
TOM (ASPHALT) PG 76-22
TON 2,490.000 $100.000 $125.000 $110.000 $108.000 $120.000
TOM-C (AGGREGATE) SAC-A
TON 34,100.000 $93.000 $125.000 $110.000 $108.000 $120.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 14,160.000 $40.000 $45.000 $50.000 $38.000 $45.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 20,841.000 $25.000 $22.000 $35.000 $22.000 $22.500
CEM STABIL BKFL
CY 366.000 $150.000 $155.000 $125.000 $158.000 $160.000
CUT & RESTORING PAV
SY 13.000 $80.000 $80.000 $150.000 $82.000 $85.000
TRENCH EXCAVATION PROTECTION
LF 974.000 $10.000 $5.000 $5.000 $5.100 $5.250
SOIL NAIL ANCHORS
LF 1,250.000 $24.000 $30.840 $35.000 $25.000 $25.000
ROCK NAIL ANCHORS
LF 390.000 $35.000 $51.400 $40.000 $41.000 $40.000
RET WALL (SOIL NAIL)(ASHLAR FIN)
SF 1,981.000 $60.000 $81.060 $55.000 $77.000 $75.000
RIPRAP (CONC)(4 IN)
CY 113.000 $450.000 $459.550 $400.000 $435.000 $430.000
RIPRAP (CONC)(5 IN)
CY 1.500 $400.000 $865.030 $2,500.000 $815.000 $800.000
RIPRAP (CONC)(FLUME)
CY 16.000 $370.000 $713.650 $525.000 $675.000 $660.000
RIPRAP (MOW STRIP)(4 IN)
CY 735.000 $400.000 $454.140 $400.000 $430.000 $420.000
RC PIPE (CL III)(18 IN)
LF 748.000 $45.000 $80.000 $72.000 $82.000 $80.000
RC PIPE (CL III)(21 IN)
LF 8.000 $60.000 $180.000 $100.000 $185.000 $180.000
RC PIPE (CL III)(24 IN)
LF 118.000 $65.000 $100.000 $120.000 $102.000 $100.000
MANH (COMPL)(PRM)(48IN)
EA 2.000 $4,000.000 $3,000.000 $3,100.000 $3,100.000 $3,000.000
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 4.000 $3,200.000 $2,700.000 $3,200.000 $2,800.000 $2,700.000
INLET (COMPL)(PCO)(5FT)(NONE)
EA 3.000 $5,000.000 $4,400.000 $3,800.000 $4,500.000 $4,400.000
INLET (COMPL)(PCO)(5FT)(LEFT)
EA 2.000 $5,000.000 $5,500.000 $4,200.000 $5,600.000 $5,500.000
INLET (COMPL)(PCO)(5FT)(RIGHT)
EA 1.000 $5,000.000 $5,500.000 $4,200.000 $5,600.000 $5,500.000
INLET (COMPL)(PCU)(5FT)(NONE)
EA 6.000 $5,000.000 $4,500.000 $4,000.000 $4,600.000 $4,500.000
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
EA 2.000 $3,500.000 $3,500.000 $3,900.000 $3,600.000 $3,500.000
ADJUSTING INLET (CAP)
EA 3.000 $1,500.000 $1,700.000 $1,500.000 $1,750.000 $1,700.000
REMOV STR (INLET)
EA 6.000 $650.000 $1,300.000 $900.000 $1,325.000 $1,300.000
REMOV STR (PIPE)
LF 524.000 $11.500 $12.000 $20.000 $12.250 $12.000
MOBILIZATION
LS 1.000 $663,100.000 $289,510.000 $780,000.000 $826,000.000 $735,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $6,000.000 $2,000.000 $8,000.000 $100,000.000 $75,000.000
SANDBAGS FOR EROSION CONTROL (6")
LF 180.000 $8.000 $6.000 $5.000 $11.000 $11.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 371.000 $3.000 $3.500 $3.000 $3.890 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 371.000 $0.500 $1.250 $0.500 $1.780 $1.800
CONC CURB & GUTTER (TY II)
LF 1,707.000 $22.000 $23.790 $20.000 $22.500 $22.000
DRIVEWAYS (ACP)
SY 220.000 $40.000 $43.000 $35.000 $40.000 $60.000
CONC SIDEWALKS (5")
SY 228.000 $70.000 $59.470 $55.000 $56.000 $55.000
CURB RAMPS (TY 20)
EA 4.000 $1,600.000 $3,243.860 $2,500.000 $3,050.000 $3,000.000
MTL W-BEAM GD FEN (STEEL POST)
LF 6,100.000 $22.000 $21.490 $25.000 $22.000 $21.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 28.000 $1,700.000 $1,776.000 $2,300.000 $1,800.000 $1,800.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 21.000 $1,100.000 $1,124.000 $1,000.000 $1,150.000 $1,150.000
REMOVE METAL BEAM GUARD FENCE
LF 4,250.000 $2.000 $1.000 $2.500 $1.000 $1.000
REMOVE TERMINAL ANCHOR SECTION
EA 10.000 $200.000 $125.000 $200.000 $127.000 $125.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 4.000 $200.000 $100.000 $190.000 $102.000 $100.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 26.000 $200.000 $100.000 $225.000 $102.000 $100.000
CABLE BARRIER SYSTEM (TL-4)
LF 6,424.000 $10.000 $9.820 $11.000 $12.500 $10.000
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 4.000 $2,300.000 $2,142.000 $2,400.000 $2,200.000 $2,150.000
GUARDRAIL END TREATMENT (INSTALL)
EA 21.000 $2,700.000 $2,739.000 $2,600.000 $2,800.000 $2,800.000
GUARDRAIL END TREATMENT (REMOVE)
EA 16.000 $220.000 $125.000 $325.000 $127.000 $130.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 1.000 $200.000 $200.000 $200.000 $255.000 $255.000
CONDT (PVC) (SCH 40) (3")
LF 666.000 $15.000 $20.000 $22.000 $20.000 $21.000
CONDT (PVC) (SCH 80) (3")
LF 318.000 $16.000 $41.000 $45.000 $42.000 $42.000
ELEC CONDR (NO.8) BARE
LF 534.000 $1.300 $2.700 $3.000 $2.750 $2.700
ELEC CONDR (NO.8) INSULATED
LF 1,068.000 $1.500 $2.800 $3.000 $2.850 $2.900
GROUND BOX TY D (162922)
EA 4.000 $850.000 $2,700.000 $3,000.000 $2,750.000 $2,800.000
REMOVE GROUND BOX
EA 2.000 $280.000 $500.000 $600.000 $525.000 $510.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 2.000 $400.000 $602.000 $600.000 $540.000 $530.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 56.000 $25.000 $11.000 $21.000 $11.000 $11.500
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 83.000 $45.000 $14.250 $36.000 $14.250 $15.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 11,567.000 $0.600 $0.900 $1.000 $1.500 $1.500
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 1,440.000 $0.600 $1.000 $1.100 $1.800 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 24,861.000 $0.650 $0.650 $0.800 $0.900 $0.650
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 861.000 $5.000 $7.000 $5.700 $6.200 $7.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 33,980.000 $0.300 $0.500 $0.500 $0.380 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 4,810.000 $0.300 $0.340 $0.800 $0.380 $0.350
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 137,442.000 $0.600 $0.520 $0.750 $0.580 $0.550
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 133,360.000 $0.600 $0.520 $0.750 $0.590 $0.550
PREFAB PAV MRK TY C (W) (ARROW)
EA 80.000 $250.000 $180.000 $200.000 $215.000 $185.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 2.000 $350.000 $330.000 $300.000 $345.000 $340.000
PREFAB PAV MRK TY C (W) (TPL ARROW)
EA 1.000 $450.000 $500.000 $500.000 $400.000 $525.000
PREFAB PAV MRK TY C (W) (WORD)
EA 80.000 $250.000 $250.000 $250.000 $275.000 $260.000
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
EA 670.000 $40.000 $34.000 $35.000 $36.000 $35.000
REFL PAV MRKR TY I-C
EA 611.000 $3.000 $3.750 $4.500 $3.500 $3.750
REFL PAV MRKR TY II-A-A
EA 87.000 $3.000 $5.000 $4.500 $5.000 $5.250
REFL PAV MRKR TY II-C-R
EA 2,579.000 $3.000 $3.750 $4.500 $3.200 $3.750
ELIM EXT PAV MRK & MRKS (4")
LF 309,708.000 $0.300 $0.410 $0.550 $0.490 $0.420
ELIM EXT PAV MRK & MRKS (8")
LF 25,579.000 $1.000 $0.820 $0.600 $0.880 $0.850
ELIM EXT PAV MRK & MRKS (24")
LF 749.000 $3.000 $2.600 $3.250 $3.000 $2.700
ELIM EXT PAV MRK & MRKS (ARROW)
EA 15.000 $50.000 $40.000 $55.000 $45.000 $41.000
ELIM EXT PAV MRK & MRKS (DBL ARROW)
EA 3.000 $50.000 $80.000 $80.000 $70.000 $82.000
ELIM EXT PAV MRK & MRKS (WORD)
EA 15.000 $50.000 $60.000 $55.000 $60.000 $60.000
ELIM EXT PAV MRK & MRKS (36")(YLD TRI)
EA 721.000 $20.000 $12.000 $30.000 $7.000 $12.000
TRF SIG CBL (TY A)(12 AWG)(16 CONDR)
LF 1,208.000 $4.400 $5.000 $5.500 $5.150 $5.000
REMOVAL OF CONTROL CABINET(GRND MNT)
EA 1.000 $800.000 $900.000 $950.000 $925.000 $900.000
INSTALL OF CONTROL CABINET(GRND MNT)
EA 1.000 $2,200.000 $16,000.000 $17,000.000 $16,350.000 $16,500.000
FULL - WIDTH MOWING
CYC 1.000 $3,000.000 $12,055.640 $8,000.000 $10,250.000 $25,000.000
CLEANING / SWEEPING (SPOT)
MI 0.200 $725.000 $15,200.000 $5,000.000 $2,550.000 $1,500.000
MEMBRANE UNDERSEAL
GAL 79,824.000 $2.200 $4.000 $3.500 $6.450 $3.500
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 120.000 $200.000 $255.000 $75.000 $98.000 $150.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $9,000.000 $10,150.000 $10,000.000 $16,500.000 $15,000.000
VIVDS PROCESSOR SYSTEM
EA 1.000 $5,700.000 $8,000.000 $8,500.000 $8,200.000 $8,000.000
VIVDS CAMERA ASSEMBLY
EA 6.000 $1,900.000 $1,400.000 $1,500.000 $1,425.000 $1,400.000
VIVDS SET-UP SYSTEM
EA 1.000 $500.000 $370.000 $400.000 $375.000 $370.000
VIVDS COMMUNICATION CABLE (COAXIAL)
LF 1,660.000 $3.600 $4.000 $4.500 $4.050 $4.000
LONG CHANNEL MOUNT CURB SYS (INSTALL)
LF 210.000 $65.000 $76.500 $75.000 $78.000 $76.500
TMA (STATIONARY)
DAY 85.000 $150.000 $410.000 $200.000 $185.000 $825.000
TMA (MOBILE OPERATION)
HR 150.000 $45.000 $345.000 $75.000 $72.000 $310.000
Totals: $7,343,909.750 $8,482,505.855 $8,730,728.550 $9,029,880.620 $9,098,673.860