BELL IH 14 (0231-03-160)

Items: 16

County: BELL
Length: N/A
Highway: IH 14
District: WACO
Control Number: 0231-03-160
DBE Goal: 0.0%
Project: F 2B24(459)
Guaranty: N/A
Time: 45 WORKING DAYS
Engineer's Estimate: $1,995,966.38
Date: 08/01/2024 (1 year ago)
Contract Number: N/A
Type: REPLACE MAINLANE STRIPING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$1,995,966.38
$1,467,608.80
Over/Under Est: -26.47% -$528,357.58
Over/Under Est: -23.72% -$473,425.90
Amt Left: 3.74% $54,931.68
Over/Under Est: -16.18% -$322,991.13
Amt Left: 13.99% $205,366.45
Delta: -9.88% -$150,434.77
$1,796,468.35
Over/Under Est: -10% -$199,498.03
Amt Left: 22.41% $328,859.55
Delta: -7.38% -$123,493.10
$2,430,179.14
Over/Under Est: 21.75% $434,212.76
Amt Left: 65.59% $962,570.34
Delta: -35.28% -$633,710.79

Bid Items & Bid Tabulations

16 Total 0 of 16
BELL  |  IH 14  |  WACO  |  0231-03-160  |  08/01/2024  |  $1,995,966.38  |  F 2B24(459)  |  REPLACE MAINLANE STRIPING  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BATTERSON, LLP
TRAFFIC HIGHWAY MAINTENANCE, LLC
TRP INFRASTRUCTURE SERVICES, LLC
L&L COMPANY
STRIPE LINES, INC.
MOBILIZATION
LS 1.000 $180,000.000 $93,000.000 $333,000.000 $125,000.000 $1.000 $25,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $15,000.000 $2,500.000 $49,000.000 $10,000.000 $1.000 $15,000.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 47.000 $270.000 $200.000 $500.000 $225.000 $300.000 $285.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 9.000 $500.000 $425.000 $1,200.000 $495.000 $400.000 $475.000
PREFAB PAV MRK TY C (W) (NUMBER)
EA 120.000 $121.000 $200.000 $120.000 $215.000 $150.000 $165.000
PREFAB PAV MRK TY C (W) (WORD)
EA 45.000 $320.000 $270.000 $500.000 $275.000 $350.000 $300.000
REFL PAV MRKR TY II-C-R
EA 49,375.000 $5.000 $6.000 $2.000 $5.500 $5.000 $6.940
MULTIPOLYMER PAV MRK (W)(6")(SLD)
LF 448,282.000 $0.650 $0.580 $0.400 $0.700 $0.850 $1.150
MULTIPOLYMER PAV MRK (W)(6")(BRK)
LF 224,141.000 $0.750 $0.580 $0.600 $0.750 $0.850 $1.150
MULTIPOLYMER PAV MRK (W)(6")(DOT)
LF 1,382.000 $1.890 $1.000 $2.650 $1.500 $0.850 $1.770
MULTIPOLYMER PAV MRK (W)(8")(SLD)
LF 284,778.000 $2.250 $1.050 $0.410 $0.900 $1.800 $2.000
MULTIPOLYMER PAV MRK (W)(12")(SLD)
LF 6,525.000 $4.510 $4.000 $5.000 $4.000 $2.000 $6.250
MULTIPOLYMER PAV MRK (W)(12")(LNDP)
LF 4,842.000 $5.000 $4.000 $7.000 $2.000 $2.500 $6.250
MULTIPOLYMER PAV MRK (W)(24")(SLD)
LF 2,176.000 $6.300 $8.000 $15.000 $10.000 $3.000 $15.000
MULTIPOLYMER PAV MRK (Y)(6")(SLD)
LF 448,282.000 $0.650 $0.580 $0.400 $0.700 $0.850 $1.150
TMA (MOBILE OPERATION)
DAY 82.000 $200.000 $100.000 $1,950.000 $995.000 $1.000 $25.000
Totals: $1,995,966.380 $1,467,608.800 $1,522,540.480 $1,672,975.250 $1,796,468.350 $2,430,179.140