Job Info for 0231-03-160

County: BELL Highway: IH 14 Date: 08/01/2024 (3 months ago) Engineer's Estimate: $1,995,966 Control Number: 0231-03-160
Project: F 2B24(459) District: WACO Time: 45 WORKING DAYS Type: REPLACE MAINLANE STRIPING
Bidder's List
Informational:

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,995,966.38
BATTERSON, LLP   $1,467,608.80 1
-26.47% | -$528,357.58
TRAFFIC HIGHWAY MAINTENANCE, LLC   $1,522,540.48 2
-23.72% | -$473,425.90
3.74% | $54,931.68
TRP INFRASTRUCTURE SERVICES, LLC   $1,672,975.25 3
-16.18% | -$322,991.13
13.99% | $205,366.45
9.88% | $150,434.77
L&L COMPANY   $1,796,468.35 4
-10% | -$199,498.03
22.41% | $328,859.55
7.38% | $123,493.10
STRIPE LINES, INC.   $2,430,179.14 5
21.75% | $434,212.76
65.59% | $962,570.34
35.28% | $633,710.79

Bid Items

Items: 16, 0 filtered
BELL IH 14  |  WACO  |  0231-03-160  |  08/01/2024  |  $1,995,966  |  F 2B24(459)  |  REPLACE MAINLANE STRIPING  |  45 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate BATTERSON, LLP TRAFFIC HIGHWAY MAINTENANCE, LLC TRP INFRASTRUCTURE SERVICES, LLC L&L COMPANY STRIPE LINES, INC.
500 6001 MOBILIZATION LS 1.000 $180,000.000 $93,000.000 $333,000.000 $125,000.000 $1.000 $25,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 $15,000.000 $2,500.000 $49,000.000 $10,000.000 $1.000 $15,000.000
668 6077 PREFAB PAV MRK TY C (W) (ARROW) EA 47.000 $270.000 $200.000 $500.000 $225.000 $300.000 $285.000
668 6083 PREFAB PAV MRK TY C (W) (LNDP ARROW) EA 9.000 $500.000 $425.000 $1,200.000 $495.000 $400.000 $475.000
668 6084 PREFAB PAV MRK TY C (W) (NUMBER) EA 120.000 $121.000 $200.000 $120.000 $215.000 $150.000 $165.000
668 6085 PREFAB PAV MRK TY C (W) (WORD) EA 45.000 $320.000 $270.000 $500.000 $275.000 $350.000 $300.000
672 6010 REFL PAV MRKR TY II-C-R EA 49,375.000 $5.000 $6.000 $2.000 $5.500 $5.000 $6.940
6038 6004 MULTIPOLYMER PAV MRK (W)(6")(SLD) LF 448,282.000 $0.650 $0.580 $0.400 $0.700 $0.850 $1.150
6038 6005 MULTIPOLYMER PAV MRK (W)(6")(BRK) LF 224,141.000 $0.750 $0.580 $0.600 $0.750 $0.850 $1.150
6038 6006 MULTIPOLYMER PAV MRK (W)(6")(DOT) LF 1,382.000 $1.890 $1.000 $2.650 $1.500 $0.850 $1.770
6038 6007 MULTIPOLYMER PAV MRK (W)(8")(SLD) LF 284,778.000 $2.250 $1.050 $0.410 $0.900 $1.800 $2.000
6038 6011 MULTIPOLYMER PAV MRK (W)(12")(SLD) LF 6,525.000 $4.510 $4.000 $5.000 $4.000 $2.000 $6.250
6038 6012 MULTIPOLYMER PAV MRK (W)(12")(LNDP) LF 4,842.000 $5.000 $4.000 $7.000 $2.000 $2.500 $6.250
6038 6013 MULTIPOLYMER PAV MRK (W)(24")(SLD) LF 2,176.000 $6.300 $8.000 $15.000 $10.000 $3.000 $15.000
6038 6017 MULTIPOLYMER PAV MRK (Y)(6")(SLD) LF 448,282.000 $0.650 $0.580 $0.400 $0.700 $0.850 $1.150
6185 6005 TMA (MOBILE OPERATION) DAY 82.000 $200.000 $100.000 $1,950.000 $995.000 $1.000 $25.000
Totals: $1,995,966.38 $1,467,608.80 $1,522,540.48 $1,672,975.25 $1,796,468.35 $2,430,179.14