Job Info for 0814-01-036

County: BAYLOR Highway: FM 422 Date: 06/05/2024 (5 months ago) Engineer's Estimate: $4,131,342 Control Number: 0814-01-036
Project: F 2B24(123) District: WICHITA FALLS Time: 311 WORKING DAYS Type: SURFACING/ROADWAY RESTORATION
Bidder's List
Informational:
Email All | Notice | Questions
HCS
Pay Estimates: 1 | 2 | 3
Plans: Plans | Revision | Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $4,131,341.81
ZACK BURKETT CO.   $5,191,085.15 1
25.65% | $1,059,743.34
A. L. HELMCAMP, INC.   $5,271,226.70 2
27.59% | $1,139,884.89
1.54% | $80,141.55
TALBERT COMPANIES LLC   $6,035,511.71 3
46.09% | $1,904,169.90
16.27% | $844,426.56
14.50% | $764,285.01
DUININCK, INC.   $6,810,311.53 4
64.85% | $2,678,969.72
31.19% | $1,619,226.38
12.84% | $774,799.82
Subcontractor Percentage Amount
W. S. CONSTRUCTION COMPANY 11.15% $578,805.99
CONTRACTORS SERVICE, LTD. 3.04% $157,808.99
MURRAY CONSTRUCTION 0.69% $35,818.49
DUSTROL, INC. 0.53% $27,512.75
LANCO TURF & SEEDING, INC. 0.30% $15,573.26
Total: 15.71% $815,519.48

Bid Items

Items: 68, 0 filtered
BAYLOR FM 422  |  WICHITA FALLS  |  0814-01-036  |  06/05/2024  |  $4,131,342  |  F 2B24(123)  |  SURF/ROADWAY RESTOR  |  311 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate ZACK BURKETT CO. A. L. HELMCAMP, INC. TALBERT COMPANIES LLC DUININCK, INC.
104 6017 REMOVING CONC (DRIVEWAYS) SY 140.000 $20.000 $25.000 $70.000 $17.710 $27.500
110 6001 EXCAVATION (ROADWAY) CY 2,246.000 $20.000 $20.000 $90.000 $16.500 $10.000
132 6004 EMBANKMENT (FINAL)(DENS CONT)(TY B) CY 3,223.000 $33.000 $62.000 $70.000 $27.500 $76.500
134 6002 BACKFILL (TY B) STA 307.000 $280.000 $200.000 $430.000 $409.940 $130.000
164 6009 BROADCAST SEED (TEMP) (WARM) SY 16,997.000 $0.500 $0.100 $0.100 $0.190 $0.180
164 6011 BROADCAST SEED (TEMP) (COOL) SY 16,997.000 $0.500 $0.130 $0.100 $0.220 $0.200
164 6033 DRILL SEEDING (PERM) (RURAL) (SANDY) SY 33,994.000 $0.160 $0.130 $0.150 $0.190 $0.180
168 6001 VEGETATIVE WATERING MG 294.000 $30.000 $35.000 $40.000 $55.220 $34.500
275 6001 CEMENT TON 523.000 $250.000 $340.000 $320.000 $357.500 $320.000
275 6010 CEMENT TREAT (SUBGRADE) (8") SY 30,592.000 $3.500 $10.000 $6.500 $7.700 $14.000
310 6009 PRIME COAT (MC-30) GAL 7,649.000 $6.000 $6.550 $8.000 $12.960 $6.900
314 6013 EMULS ASPH (EROSN CONT)(CSS-1H) GAL 8,515.000 $4.950 $3.050 $5.500 $7.150 $4.700
351 6004 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 2,500.000 $65.500 $75.000 $90.000 $110.000 $115.000
354 6002 PLAN & TEXT ASPH CONC PAV(0" TO 2") SY 1,511.000 $4.160 $8.240 $9.000 $8.800 $24.500
400 6005 CEM STABIL BKFL CY 108.000 $180.000 $295.000 $260.000 $275.000 $310.000
400 6006 CUT & RESTORING PAV SY 138.000 $120.000 $53.100 $48.000 $313.500 $140.000
402 6001 TRENCH EXCAVATION PROTECTION LF 27.000 $10.000 $29.500 $26.000 $22.000 $31.000
403 6001 TEMPORARY SPL SHORING SF 124.000 $36.000 $53.100 $48.000 $110.000 $55.500
462 6051 CONC BOX CULV (5 FT X 3 FT)(EXTEND) LF 114.000 $700.000 $1,091.500 $980.000 $1,100.000 $1,100.000
464 6005 RC PIPE (CL III)(24 IN) LF 268.000 $150.000 $118.000 $110.000 $187.000 $125.000
464 6007 RC PIPE (CL III)(30 IN) LF 180.000 $200.000 $141.600 $125.000 $247.500 $150.000
464 6008 RC PIPE (CL III)(36 IN) LF 46.000 $250.000 $206.500 $185.000 $330.000 $215.000
466 6097 HEADWALL (CH - PW - 0) (DIA= 24 IN) EA 2.000 $6,000.000 $11,505.000 $800.000 $6,600.000 $12,000.000
466 6099 HEADWALL (CH - PW - 0) (DIA= 30 IN) EA 4.000 $6,975.000 $15,340.000 $14,000.000 $8,250.000 $16,000.000
466 6101 HEADWALL (CH - PW - 0) (DIA= 36 IN) EA 2.000 $8,916.000 $11,505.000 $10,500.000 $13,200.000 $12,000.000
466 6193 WINGWALL (PW - 2) (HW=4 FT) EA 3.000 $9,404.000 $14,750.000 $13,000.000 $11,000.000 $15,500.000
466 6194 WINGWALL (PW - 2) (HW=5 FT) EA 1.000 $12,667.000 $22,420.000 $20,000.000 $16,500.000 $23,500.000
467 6363 SET (TY II) (18 IN) (RCP) (6: 1) (P) EA 34.000 $1,320.000 $1,947.000 $1,800.000 $1,320.000 $2,000.000
467 6390 SET (TY II) (24 IN) (RCP) (4: 1) (C) EA 9.000 $2,000.000 $2,006.000 $1,800.000 $2,200.000 $2,100.000
467 6394 SET (TY II) (24 IN) (RCP) (6: 1) (C) EA 2.000 $2,200.000 $2,360.000 $2,200.000 $3,080.000 $2,500.000
467 6395 SET (TY II) (24 IN) (RCP) (6: 1) (P) EA 8.000 $2,650.000 $2,360.000 $2,200.000 $3,080.000 $2,500.000
467 6419 SET (TY II) (30 IN) (RCP) (4: 1) (C) EA 4.000 $2,590.000 $3,540.000 $3,200.000 $4,400.000 $3,700.000
467 6423 SET (TY II) (30 IN) (RCP) (6: 1) (P) EA 2.000 $3,500.000 $4,425.000 $4,000.000 $4,950.000 $4,600.000
496 6005 REMOV STR (WINGWALL) EA 4.000 $1,600.000 $590.000 $530.000 $2,200.000 $615.000
496 6007 REMOV STR (PIPE) LF 558.000 $15.000 $14.160 $13.000 $71.500 $15.000
500 6001 MOBILIZATION LS 1.000 $368,207.350 $490,000.000 $373,000.000 $500,000.000 $675,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 19.000 $6,000.000 $9,815.750 $5,000.000 $12,648.650 $20,000.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 975.000 $4.000 $4.500 $4.000 $4.170 $4.050
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 975.000 $0.750 $1.800 $1.600 $1.270 $1.250
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 560.000 $6.000 $6.200 $6.000 $5.060 $4.950
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 560.000 $1.500 $1.500 $1.400 $1.270 $1.250
530 6004 DRIVEWAYS (CONC) SY 140.000 $105.000 $141.600 $130.000 $275.000 $170.000
530 6005 DRIVEWAYS (ACP) SY 1,104.000 $54.000 $37.000 $93.000 $57.650 $94.000
530 6008 TURNOUTS (ACP) SY 308.000 $58.000 $37.000 $76.000 $56.720 $94.500
530 6016 DRIVEWAYS (BASE) SY 2,089.000 $25.000 $33.000 $30.000 $27.500 $57.000
533 6001 RUMBLE STRIPS (SHOULDER) LF 63,940.000 $0.210 $0.370 $0.320 $0.220 $0.090
533 6002 RUMBLE STRIPS (CENTERLINE) LF 31,970.000 $0.270 $0.370 $0.320 $0.330 $0.120
560 6005 MAILBOX INSTALL-D (TWG-POST) TY 2 EA 1.000 $374.000 $383.500 $240.000 $379.500 $285.000
560 6011 MAILBOX INSTALL-S (TWW-POST) TY 4 EA 13.000 $300.000 $354.000 $250.000 $324.500 $295.000
644 6004 IN SM RD SN SUP&AM TY10BWG(1)SA(T) EA 16.000 $700.000 $1,003.000 $850.000 $852.500 $985.000
644 6007 IN SM RD SN SUP&AM TY10BWG(1)SA(U) EA 2.000 $800.000 $1,032.500 $920.000 $1,094.500 $1,100.000
644 6033 IN SM RD SN SUP&AM TYS80(1)SA(U) EA 1.000 $945.000 $1,050.500 $1,000.000 $1,155.000 $1,200.000
644 6060 IN SM RD SN SUP&AM TYTWT(1)WS(P) EA 16.000 $475.000 $619.500 $600.000 $544.500 $675.000
644 6076 REMOVE SM RD SN SUP&AM EA 35.000 $118.220 $118.000 $110.000 $115.500 $125.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 36.000 $37.000 $41.300 $48.000 $17.050 $35.500
658 6100 INSTL OM ASSM (OM-2Z)(WFLX)GND(BI) EA 36.000 $104.000 $70.800 $68.000 $93.500 $80.000
662 6111 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 EA 4,569.000 $1.250 $1.200 $0.700 $2.040 $1.800
666 6309 RE PM W/RET REQ TY I (W)6"(SLD)(100MIL) LF 63,600.000 $0.730 $0.790 $0.700 $0.640 $0.710
666 6318 RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL) LF 34,600.000 $0.700 $0.900 $0.800 $0.660 $0.740
666 6321 RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL) LF 11,565.000 $0.730 $0.790 $0.700 $0.640 $0.710
3076 6001 D-GR HMA TY-B PG64-22 TON 6,731.000 $100.000 $123.000 $130.500 $154.000 $160.000
3076 6038 D-GR HMA TY-D PG64-22 (LEVEL-UP) TON 783.000 $125.000 $150.000 $210.000 $176.000 $250.000
3076 6046 D-GR HMA TY-D SAC-B PG70-28 TON 11,090.000 $115.000 $128.000 $135.000 $165.000 $175.000
3084 6001 BONDING COURSE GAL 7,882.000 $4.030 $5.650 $5.100 $7.700 $2.650
4122 6023 THERMO PIPE(18")(PP)(TY S)(TY II) LF 534.000 $28.000 $88.500 $79.000 $74.800 $92.500
4122 6024 THERMO PIPE(24")(PP)(TY S)(TY II) LF 154.000 $33.000 $106.200 $95.000 $170.500 $110.000
6185 6002 TMA (STATIONARY) DAY 283.000 $210.000 $267.000 $50.000 $218.680 $310.000
6185 6005 TMA (MOBILE OPERATION) DAY 8.000 $250.000 $1.000 $50.000 $290.540 $1,200.000
Totals: $4,131,341.81 $5,191,085.15 $5,271,226.70 $6,035,511.71 $6,810,311.53