Job Info for 6347-07-001

County: BASTROP Highway: FM2104 Date: 12/10/2019 (4 years ago) Engineer's Estimate: $241,332 Control Number: 6347-07-001
Project: BPM - 634707001 District: AUSTIN Time: 32 W Type: BRIDGE PREVENTATIVE MAINTENANCE

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $241,331.51
DAN WILLIAMS COMPANY   $277,914.00 1
15.16% | $36,582.49
FUQUA CONSTRUCTION CO., INC.   $338,937.57 2
40.44% | $97,606.06
21.96% | $61,023.57
3LW CIVIL LLC   $375,287.00 3
55.51% | $133,955.49
35.04% | $97,373.00
10.72% | $36,349.43
FNH CONSTRUCTION, LLC   $462,991.00 4
91.85% | $221,659.49
66.6% | $185,077.00
23.37% | $87,704.00

Bid Items

Items: 23, 0 filtered
BASTROP FM2104  |  AUSTIN  |  6347-07-001  |  12/10/2019  |  $241,332  |  BPM - 634707001  |  BRIDGE PREVENT MAINT  |  32 W
Item code Description Unit Quantity Engineer's Estimate DAN WILLIAMS COMPANY FUQUA CONSTRUCTION CO., INC. 3LW CIVIL LLC FNH CONSTRUCTION, LLC
100 6002 PREPARING ROW STA 3.000 $2,600.000 $8,000.000 $7,650.000 $20,000.000 $45,000.000
104 6009 REMOVING CONC (RIPRAP) SY 116.000 $50.000 $25.000 $51.140 $55.000 $50.000
110 6003 EXCAVATION (SPECIAL) CY 79.000 $34.000 $75.000 $68.000 $25.000 $50.000
160 6003 FURNISHING AND PLACING TOPSOIL (4") SY 3,822.000 $2.500 $1.250 $1.330 $6.000 $10.000
164 6035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY 3,822.000 $0.200 $0.250 $0.220 $1.000 $1.000
168 6001 VEGETATIVE WATERING MG 567.000 $35.000 $5.000 $20.400 $50.000 $30.000
169 6003 SOIL RETENTION BLANKETS (CL 1) (TY C) SY 592.000 $2.100 $1.750 $2.890 $3.000 $10.000
402 6001 TRENCH EXCAVATION PROTECTION LF 249.000 $15.000 $2.500 $5.610 $17.000 $10.000
432 6008 RIPRAP (CONC)(CL B)(RR8&RR9) CY 3.300 $775.000 $1,750.000 $850.000 $2,000.000 $650.000
432 6031 RIPRAP (STONE PROTECTION)(12 IN) CY 486.000 $155.000 $190.000 $260.000 $160.000 $150.000
432 6032 RIPRAP (STONE PROTECTION)(15 IN) CY 149.000 $160.000 $220.000 $260.000 $190.000 $175.000
432 6035 RIPRAP (STONE PROTECTION)(24 IN) CY 22.000 $250.000 $325.000 $238.000 $200.000 $250.000
432 6036 RIPRAP (STONE PROTECTION)(30 IN) CY 73.000 $175.000 $280.000 $238.000 $225.000 $450.000
500 6001 MOBILIZATION LS 1.000 $17,876.410 $25,000.000 $42,500.000 $50,000.000 $46,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 $4,000.000 $11,500.000 $4,059.920 $10,000.000 $8,500.000
506 6001 ROCK FILTER DAMS (INSTALL) (TY 1) LF 115.000 $45.000 $21.500 $42.500 $34.000 $30.000
506 6003 ROCK FILTER DAMS (INSTALL) (TY 3) LF 70.000 $55.000 $42.000 $85.000 $53.000 $30.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 185.000 $15.000 $18.000 $17.000 $12.000 $15.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 300.000 $35.000 $11.500 $11.900 $25.000 $40.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 300.000 $15.000 $9.000 $5.100 $10.000 $20.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 1,964.000 $3.000 $2.750 $5.100 $4.000 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 1,964.000 $3.000 $1.000 $1.700 $2.000 $2.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 68.000 $80.000 $90.000 $154.590 $150.000 $150.000
Totals: $241,331.51 $277,914.00 $338,937.57 $375,287.00 $462,991.00