Show Job Controls
Bid Cobra

BASTROP FM 969 (1186-02-020)

Items: 34

County: BASTROP
Length: N/A
Highway: FM 969
District: AUSTIN
Control Number: 1186-02-020
DBE Goal: N/A
Project: STP 2B20(027)
Guaranty: N/A
Time: 66 WORKING DAYS
Engineer's Estimate: $3,181,150.94
Date: 07/09/2020 (5 years ago)
Contract Number: N/A
Type: LEVEL-UP, REPAIR, OVERLAY & PVMNT MRK
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$3,181,150.94
$2,826,332.68
Over/Under Est: -11.15% -$354,818.26
Over/Under Est: -5.82% -$185,123.96
Amt Left: 6% $169,694.30
Over/Under Est: -5.3% -$168,653.41
Amt Left: 6.59% $186,164.85
Delta: -0.55% -$16,470.55
Over/Under Est: -3.35% -$106,659.17
Amt Left: 8.78% $248,159.09
Delta: -2.06% -$61,994.24
$3,796,176.61
Over/Under Est: 19.33% $615,025.67
Amt Left: 34.31% $969,843.93
Delta: -23.47% -$721,684.84

Bid Items & Bid Tabulations

34 Total 0 of 34
BASTROP  |  FM 969  |  AUSTIN  |  1186-02-020  |  07/09/2020  |  $3,181,150.94  |  STP 2B20(027)  |  LEVEL-UP, REPAIR, OVERLAY & PVMNT MR...  |  66 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
LONE STAR PAVING COMPANY
BIG CREEK CONSTRUCTION, LTD.
HUNTER INDUSTRIES, LTD.
ANGEL BROTHERS HOLDINGS CORP.
AUSTIN MATERIALS, LLC
BACKFILL (TY A)
STA 643.950 $125.000 $100.000 $90.000 $129.150 $50.000 $155.000
ASPH (TIER II)
GAL 67,951.000 $3.000 $2.500 $2.750 $3.210 $3.000 $3.900
AGGR(TY-PD GR-4 SAC-B)
CY 1,491.000 $90.000 $100.000 $100.000 $77.260 $75.000 $118.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 19,381.000 $35.000 $35.000 $40.000 $31.080 $35.000 $43.000
PLANE ASPH CONC PAV (1.5")
SY 29,549.000 $1.850 $1.250 $1.750 $1.620 $2.000 $1.750
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 306.000 $55.000 $37.000 $50.000 $34.000 $45.000 $37.000
MOBILIZATION
LS 1.000 $215,000.000 $108,000.000 $15,300.000 $254,054.620 $280,000.000 $302,400.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $3,500.000 $6,500.000 $2,300.000 $3,652.580 $4,000.000 $42,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 40.000 $5.000 $3.000 $10.000 $10.000 $4.000 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 40.000 $5.000 $0.500 $1.000 $10.000 $0.500 $1.350
RUMBLE STRIPS (CENTERLINE)
LF 59,517.000 $0.250 $0.170 $0.250 $0.200 $0.420 $0.280
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 289,778.000 $0.100 $0.060 $0.080 $0.140 $0.060 $0.090
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 48.000 $3.150 $4.150 $4.250 $4.000 $4.000 $4.000
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 16,527.000 $0.100 $0.100 $0.110 $0.140 $0.100 $0.090
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 208,722.000 $0.100 $0.100 $0.110 $0.140 $0.100 $0.090
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 140.000 $1.000 $0.830 $1.000 $1.270 $1.000 $1.200
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 7,267.000 $1.000 $0.750 $1.000 $1.270 $1.000 $1.200
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 18,604.000 $1.000 $0.590 $1.100 $2.000 $0.250 $1.300
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 60.000 $25.000 $15.600 $16.000 $7.000 $15.000 $15.000
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 7,345.000 $0.300 $0.290 $0.300 $0.310 $0.280 $0.300
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 92,765.000 $0.300 $0.280 $0.280 $0.310 $0.270 $0.300
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 197,874.000 $0.550 $0.600 $0.600 $0.590 $0.580 $0.600
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 6,710.000 $0.570 $0.620 $0.650 $0.590 $0.600 $0.600
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 34,922.000 $0.520 $0.600 $0.600 $0.590 $0.580 $0.600
REFL PAV MRKR TY I-C
EA 70.000 $3.600 $3.550 $3.750 $3.410 $3.500 $3.100
REFL PAV MRKR TY II-A-A
EA 2,739.000 $3.600 $3.000 $3.000 $3.410 $2.900 $3.100
ELIM EXT PAV MRK & MRKS (4")
LF 69,084.000 $0.350 $0.250 $0.250 $0.540 $0.230 $0.230
D-GR HMA TY-D PG64-22 (LEVEL-UP)
TON 800.000 $90.000 $76.000 $85.000 $75.840 $84.000 $77.000
D-GR HMA TY-D SAC-B PG76-22
TON 16,292.000 $80.000 $71.000 $77.000 $68.640 $78.000 $85.000
TACK COAT
GAL 776.000 $4.000 $2.650 $3.600 $2.960 $2.700 $4.500
BONDING COURSE
GAL 17,773.000 $2.750 $2.500 $3.100 $2.960 $2.700 $2.700
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 192.000 $85.000 $70.000 $75.000 $108.250 $25.000 $60.000
TMA (STATIONARY)
DAY 192.000 $200.000 $150.000 $200.000 $270.630 $25.000 $192.000
TMA (MOBILE OPERATION)
HR 48.000 $180.000 $85.000 $200.000 $108.250 $193.500 $96.000
Totals: $3,181,150.940 $2,826,332.680 $2,996,026.980 $3,012,497.532 $3,074,491.770 $3,796,176.610