BASTROP SH 71 (0265-03-054)
Items: 66
County: BASTROP
Length: 0.0000 MILES (0.4897 MILES)
Highway: SH 71
District: AUSTIN
Control Number: 0265-03-054
DBE Goal: 0.0%
Project: F 2026(388)
Guaranty: $15,000.00
Time: 93 WORKING DAYS
Engineer's Estimate: $745,820.25
Date: 07/02/2026 1:00 PM CDT (16 days ago) Changed
Contract Number: 7263028
Type: HIGHWAY IMPROVEMENT
Project ID: A00216234
Contract Type: FEDERAL
Project Description: U-TURN/TURNAROUND AT SH 21-WITH THE REMOVAL OF THE ONE CROSSOVERS FROM 0.49 MILES WEST OF SH 21 TO SH 21, REPLACED WITH A CABLE BARRIER
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DIANA SCHULZE
SHANE SWIMM
MAHENDRAN THIVAKARAN
YETNAYET BOGALE
BASTROP SH 71 (0265-03-054)
Project Name: N/A
Project: F 2026(388)
Engineer's Estimate: $745,820.25
Length: 0.0000 MILES (0.4897 MILES)
Project Class: INTERSECTION & OPERATIONAL IMPRV
Limits From: 0.49 MILES WEST OF SH 21
Limits To: SH 21
Project Description: U-TURN/TURNAROUND AT SH 21-WITH THE REMOVAL OF THE ONE CROSSOVERS FROM 0.49 MILES WEST OF SH 21 TO SH 21, REPLACED WITH A CABLE BARRIER
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$745,820.25 | |||
| $1,095,803.80 |
46.93%
$349,983.55
|
|||
| $1,222,711.90 |
63.94%
$476,891.65
|
11.58%
$126,908.10
|
||
| $1,265,101.35 |
69.63%
$519,281.10
|
15.45%
$169,297.55
|
-3.47%
-$42,389.45
|
|
| $1,324,346.75 |
77.57%
$578,526.50
|
20.86%
$228,542.95
|
-4.68%
-$59,245.40
|
|
| $1,451,193.81 |
94.58%
$705,373.56
|
32.43%
$355,390.01
|
-9.58%
-$126,847.06
|
E
Engineer's Estimate
$745,820.25
$1,095,803.80
Over/Under Est:
46.93%
$349,983.55
$1,222,711.90
Over/Under Est:
63.94%
$476,891.65
Amt Left:
11.58%
$126,908.10
$1,265,101.35
Over/Under Est:
69.63%
$519,281.10
Amt Left:
15.45%
$169,297.55
Delta:
-3.47%
-$42,389.45
$1,324,346.75
Over/Under Est:
77.57%
$578,526.50
Amt Left:
20.86%
$228,542.95
Delta:
-4.68%
-$59,245.40
$1,451,193.81
Over/Under Est:
94.58%
$705,373.56
Amt Left:
32.43%
$355,390.01
Delta:
-9.58%
-$126,847.06
Bid Items & Bid Tabulations
66
Total
0 of 66
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $3,500.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,500.00 |
| Total: | $10,000.00 |