Show Job Controls
Bid Cobra

BASTROP SH 71 (0265-03-054)

Items: 66

County: BASTROP
Length: 0.0000 MILES (0.4897 MILES)
Highway: SH 71
District: AUSTIN
Control Number: 0265-03-054
DBE Goal: 0.0%
Project: F 2026(388)
Guaranty: $15,000.00
Time: 93 WORKING DAYS
Engineer's Estimate: $745,820.25
Date: 07/02/2026 1:00 PM CDT (16 days ago) Changed
Contract Number: 7263028
Type: HIGHWAY IMPROVEMENT
Project ID: A00216234
Contract Type: FEDERAL
Project Description: U-TURN/TURNAROUND AT SH 21-WITH THE REMOVAL OF THE ONE CROSSOVERS FROM 0.49 MILES WEST OF SH 21 TO SH 21, REPLACED WITH A CABLE BARRIER
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DIANA SCHULZE
SHANE SWIMM
MAHENDRAN THIVAKARAN
YETNAYET BOGALE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$745,820.25
Over/Under Est: 46.93% $349,983.55
Over/Under Est: 63.94% $476,891.65
Amt Left: 11.58% $126,908.10
Over/Under Est: 69.63% $519,281.10
Amt Left: 15.45% $169,297.55
Delta: -3.47% -$42,389.45
Over/Under Est: 77.57% $578,526.50
Amt Left: 20.86% $228,542.95
Delta: -4.68% -$59,245.40
Over/Under Est: 94.58% $705,373.56
Amt Left: 32.43% $355,390.01
Delta: -9.58% -$126,847.06

Bid Items & Bid Tabulations

66 Total 0 of 66
BASTROP  |  SH 71  |  AUSTIN  |  0265-03-054  |  07/02/2026 1:00 PM CDT  |  $745,820.25  |  F 2026(388)  |  HWY IMPRV  |  93 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
E-Z BEL CONSTRUCTION, LLC
AARON CONCRETE CONTRACTORS, LLC
TEXAS MATERIALS GROUP, INC.
JOE BLAND CONSTRUCTION LLC
HUNTER INDUSTRIES, LTD.
PREPARING ROW
STA 10.000 $1,000.000 $3,000.000 $330.000 $750.000 $3,500.000 $7,500.000
REMOV CONC (RIPRAP)
SY 506.000 $15.000 $5.000 $17.000 $15.000 $25.000 $50.000
REMOV CONC (RETAINING WALLS)
SY 44.000 $65.000 $15.000 $66.000 $75.000 $100.000 $150.000
REMOV CONC (COPING)
LF 57.000 $100.000 $10.000 $36.000 $5.000 $85.000 $100.000
REMOVING STAB BASE & ASPH PAV(12"-27")
SY 1,024.000 $7.500 $15.000 $26.000 $58.000 $24.000 $18.800
EXCAV (ROADWAY)
CY 725.000 $13.000 $17.000 $34.000 $42.000 $60.000 $38.500
EMBANK (FNL)(OC)(TY B)
CY 58.000 $20.000 $40.000 $19.000 $43.000 $60.000 $38.500
EMBANK (FNL)(OC)(TY C1)
CY 321.000 $25.000 $50.000 $60.000 $102.000 $65.000 $55.200
FURN & PLACE TOPSOIL (4")
SY 4,840.000 $2.000 $7.000 $5.000 $7.000 $5.000 $4.600
HYDRO MULCH SEED (PERM_RURAL_SANDY)
SY 4,840.000 $0.500 $0.370 $1.000 $0.500 $0.500 $0.540
VEGETATIVE WATERING
TGL 8.000 $25.000 $150.000 $144.000 $350.000 $60.000 $77.000
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 735.000 $95.000 $110.500 $129.000 $205.000 $120.000 $143.000
D-GR HMA TY-D SAC-B PG 76-22 (EXEMPT)
TON 134.000 $190.000 $192.000 $224.000 $325.000 $210.000 $206.800
TOM-C PG76-22 SAC-B
TON 67.000 $120.000 $305.000 $357.000 $450.000 $335.000 $363.000
TEMPORARY SPL SHORING
SF 2,000.000 $22.000 $100.000 $145.000 $96.600 $105.000 $77.000
DRILL SHAFT (TRF SIG POLE) (30 IN)
LF 11.300 $400.000 $500.000 $453.000 $350.000 $390.000 $340.750
CL C CONC (RAIL FOUNDATION)
CY 19.000 $750.000 $600.000 $752.000 $794.000 $1,150.000 $800.000
RETAINING WALL (SPREAD FOOTING)
SF 1,905.000 $105.000 $152.000 $146.000 $139.000 $105.000 $230.000
RIPRAP (CONC) (CL B) (4 IN)
CY 19.000 $550.000 $975.000 $584.000 $500.000 $975.000 $540.750
RAIL (TY SSTR)
LF 106.000 $90.000 $151.000 $119.000 $119.000 $115.000 $200.000
RAIL (TY T80SS)
LF 112.000 $150.000 $151.000 $223.000 $222.000 $175.000 $300.000
REMOV STR (SET)
EA 2.000 $750.000 $400.000 $421.000 $1,994.330 $1,500.000 $500.000
REMOV STR (PIPE)
LF 67.000 $25.000 $12.000 $15.000 $182.070 $20.000 $30.000
MOBILIZATION
LS 1.000 $60,000.000 $90,000.000 $119,764.000 $100,000.000 $115,000.000 $144,339.390
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $4,000.000 $3,500.000 $1,937.000 $7,500.000 $1,050.000 $5,200.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $7,500.000 $7,550.000 $9,935.000 $8,250.000 $14,000.000 $7,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 155.000 $4.000 $4.500 $4.000 $4.000 $6.000 $3.790
TEMP SEDMT CONT FENCE (REMOVE)
LF 155.000 $1.000 $1.000 $1.000 $1.000 $1.000 $1.080
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 397.000 $5.750 $10.500 $5.000 $4.000 $12.000 $4.330
BIODEG EROSN CONT LOGS (REMOVE)
LF 397.000 $1.500 $1.500 $1.000 $1.000 $2.000 $1.080
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 700.000 $35.000 $25.000 $22.000 $24.000 $110.000 $50.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 1,340.000 $35.000 $20.000 $16.000 $16.000 $105.000 $40.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 20.000 $65.000 $25.000 $8.000 $8.000 $100.000 $40.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 700.000 $20.000 $15.000 $24.000 $24.000 $20.000 $30.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 1,340.000 $12.000 $10.000 $16.000 $16.000 $20.000 $20.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 20.000 $20.000 $15.000 $14.000 $14.000 $20.000 $20.000
CABLE BARRIER SYSTEM (INSTALL)(TL-4)
LF 280.000 $25.000 $41.000 $40.000 $34.000 $38.000 $36.770
CABLE BARRIER TERM SEC (INSTL)(TL-4)
EA 1.000 $3,000.000 $7,100.500 $6,166.000 $5,275.000 $7,000.000 $5,704.960
CABLE BARRIER TERMINAL SECTION (REMOVE)
EA 1.000 $450.000 $1,580.000 $526.000 $450.000 $200.000 $486.680
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,000.000 $1,475.000 $526.000 $450.000 $1,175.000 $486.680
CCA (INSTL)(N)(TL3)(WORK ZONE)
EA 2.000 $7,500.000 $8,575.000 $7,831.000 $6,700.000 $11,300.000 $7,246.120
CONDT (PVC) (SCH 80) (2")
LF 11.000 $40.000 $45.000 $45.000 $35.000 $20.000 $19.190
CONDT (PVC) (SCH 80) (3")
LF 22.000 $40.000 $50.000 $52.000 $40.000 $24.000 $21.480
CONDUIT (PREPARE)
LF 182.000 $20.000 $4.000 $5.000 $4.000 $12.000 $18.970
ELEC CONDR (NO.8) BARE
LF 33.000 $3.000 $4.000 $6.000 $5.000 $4.000 $3.030
GROUND BOX TY D (162922)W/APRON
EA 1.000 $2,000.000 $1,500.000 $3,106.000 $2,400.000 $2,950.000 $1,644.500
REMOVE GROUND BOX
EA 2.000 $500.000 $375.000 $324.000 $250.000 $1,100.000 $322.070
ALUMINUM SIGNS (TY G)
SF 14.000 $35.000 $85.000 $58.000 $30.000 $55.000 $54.080
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $1,000.000 $850.000 $1,379.000 $850.000 $990.000 $973.360
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
EA 2.000 $1,300.000 $950.000 $1,800.000 $950.000 $1,350.000 $1,270.770
REMOVE SM RD SN SUP&AM
EA 10.000 $150.000 $400.000 $84.000 $50.000 $60.000 $59.480
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 208.000 $3.000 $3.000 $3.000 $3.000 $3.000 $3.150
REFL PAV MRK TY I(W)(UTURN ARW)(100MIL)
EA 2.000 $300.000 $350.000 $403.000 $350.000 $390.000 $367.500
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 2.000 $250.000 $350.000 $392.000 $350.000 $375.000 $367.500
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 911.000 $2.000 $2.000 $1.000 $2.000 $1.250 $2.100
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 1,846.000 $2.000 $2.000 $1.000 $2.000 $1.250 $2.100
REFL PAV MRKR TY II-C-R
EA 15.000 $5.000 $8.000 $12.000 $8.000 $11.000 $8.400
ELIM EXT PM & MRKS (6")
LF 190.000 $2.000 $5.000 $1.000 $5.000 $1.250 $5.250
VEH SIG SEC (12")LED(GRN)
EA 2.000 $350.000 $435.000 $472.000 $365.000 $590.000 $379.900
VEH SIG SEC (12")LED(YEL)
EA 2.000 $350.000 $435.000 $472.000 $365.000 $590.000 $379.900
VEH SIG SEC (12")LED(RED)
EA 2.000 $350.000 $435.000 $472.000 $365.000 $590.000 $379.900
VEH SIG SEC(12")LED(YEL ARW)(LENS ONLY)
EA 1.000 $200.000 $435.000 $182.000 $141.000 $555.000 $148.880
BACKPLATE W/REF BRDR(3 SEC)(VENT)ALUM
EA 2.000 $250.000 $230.000 $259.000 $200.000 $375.000 $373.770
INS TRF SIG PL AM(S)1 ARM(32')LUM
EA 1.000 $12,000.000 $22,000.000 $25,883.000 $20,000.000 $25,000.000 $18,106.830
REMOVE TRF SIG PL
EA 1.000 $2,500.000 $1,950.000 $1,165.000 $900.000 $6,725.000 $1,217.520
BONDING COURSE
GAL 214.000 $5.000 $3.250 $4.000 $20.000 $3.500 $7.900
Totals: $745,820.250 $1,095,803.800 $1,222,711.900 $1,265,101.350 $1,324,346.750 $1,451,193.805
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $3,500.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,500.00
Total: $10,000.00