Job Info for 0913-20-093

County: AUSTIN Highway: CR Date: 05/05/2022 (2 years ago) Engineer's Estimate: $1,314,061 Control Number: 0913-20-093
Project: BR 2020(686) District: YOAKUM Time: 172 WORKING DAYS Type: BRIDGE REPLACEMENT
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12
Plans

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,314,061.00
FUQUA CONSTRUCTION CO., INC.   $1,258,243.82 1
-4.25% | -$55,817.18
MB WESTERN INDUSTRIAL CONTRACTING COMPANY   $1,556,463.54 2
18.45% | $242,402.54
23.7% | $298,219.72
SB CONTRACTORS LLC   $1,564,704.45 3
19.07% | $250,643.45
24.36% | $306,460.63
0.53% | $8,240.91
KNIFE RIVER CORPORATION - SOUTH   $1,685,524.80 4
28.27% | $371,463.80
33.96% | $427,280.98
7.72% | $120,820.35
EARTH BUILDERS, L.P.   $1,966,075.50 5
49.62% | $652,014.50
56.26% | $707,831.68
16.64% | $280,550.70
Subcontractor Percentage Amount
HEMPHILL WBE PILE DRIVING CO. 8.99% $113,116.12
TRAFFIC SIGNS & LINES, LLC 4.57% $57,501.74
CEN TEX HYDROSEED, INC. 1.82% $22,900.04
RAY"S CRANE SERVICE 0.54% $6,794.52
AREA WIDE PROTECTIVE, INC. 0.51% $6,417.04
Total: 16.43% $206,729.46

Bid Items

Items: 37, 0 filtered
AUSTIN CR  |  YOAKUM  |  0913-20-093  |  05/05/2022  |  $1,314,061  |  BR 2020(686)  |  BRIDGE REPL  |  172 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate FUQUA CONSTRUCTION CO., INC. MB WESTERN INDUSTRIAL CONTRACTING COMPANY SB CONTRACTORS LLC KNIFE RIVER CORPORATION - SOUTH EARTH BUILDERS, L.P.
100 6002 PREPARING ROW STA 8.880 $3,000.000 $3,000.000 $5,907.280 $5,500.000 $15,800.000 $20,000.000
110 6001 EXCAVATION (ROADWAY) CY 222.000 $20.000 $10.000 $29.500 $46.250 $17.000 $20.000
110 6002 EXCAVATION (CHANNEL) CY 683.000 $20.000 $8.000 $25.250 $17.630 $23.000 $20.000
132 6005 EMBANKMENT (FINAL)(ORD COMP)(TY C) CY 468.000 $22.000 $15.000 $75.350 $21.940 $37.350 $40.000
150 6002 BLADING HR 48.000 $100.000 $60.000 $206.000 $80.000 $120.000 $100.000
164 6003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY 2,317.000 $2.000 $3.000 $3.100 $2.770 $3.300 $3.000
164 6009 BROADCAST SEED (TEMP) (WARM) SY 581.000 $4.000 $2.000 $11.150 $10.120 $2.200 $1.000
164 6011 BROADCAST SEED (TEMP) (COOL) SY 581.000 $4.000 $2.000 $5.000 $10.120 $2.200 $1.000
168 6001 VEGETATIVE WATERING MG 19.600 $50.000 $8.380 $92.800 $70.000 $53.000 $100.000
247 6366 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) CY 428.000 $120.000 $100.000 $100.000 $187.320 $115.000 $100.000
400 6005 CEM STABIL BKFL CY 110.000 $115.000 $160.000 $125.000 $168.390 $180.000 $250.000
409 6002 PRESTR CONC PIL (18 IN SQ) LF 1,136.000 $155.000 $162.160 $140.650 $145.600 $197.000 $225.000
420 6013 CL C CONC (ABUT) CY 75.300 $1,200.000 $1,050.000 $1,012.000 $1,250.690 $1,180.000 $1,500.000
422 6005 REINF CONC SLAB (BOX BEAM) SF 3,402.000 $22.000 $20.000 $36.500 $40.250 $37.650 $30.000
422 6007 REINF CONC SLAB (SLAB BEAM) SF 1,300.000 $22.000 $20.000 $38.150 $51.810 $32.200 $25.000
422 6023 SHEAR KEY CY 17.200 $700.000 $300.000 $316.250 $728.050 $500.000 $1,500.000
425 6001 PRESTR CONC BOX BEAM (4B20) LF 516.000 $215.000 $253.550 $268.000 $276.860 $272.750 $315.000
425 6002 PRESTR CONC BOX BEAM (5B20) LF 258.000 $220.000 $253.550 $275.000 $277.090 $300.000 $315.000
425 6012 PRESTR CONC SLAB BEAM (5SB15) LF 247.500 $230.000 $246.800 $251.000 $306.630 $301.000 $315.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 788.000 $175.000 $140.000 $137.550 $158.280 $165.000 $230.000
432 6035 RIPRAP (STONE PROTECTION)(24 IN) CY 466.000 $185.000 $140.000 $164.000 $130.600 $162.000 $230.000
450 6006 RAIL (TY T223) LF 450.000 $120.000 $120.000 $106.000 $134.970 $131.000 $150.000
454 6004 ARMOR JOINT (SEALED) LF 132.000 $85.000 $90.000 $226.500 $232.150 $122.500 $150.000
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 3.000 $20,000.000 $20,000.000 $17,755.000 $17,000.000 $16,900.000 $30,000.000
500 6001 MOBILIZATION LS 1.000 $116,000.000 $144,000.000 $171,037.000 $150,000.000 $203,000.000 $200,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 12.000 $3,000.000 $510.900 $4,330.100 $2,500.000 $1,700.000 $4,000.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 2,276.000 $4.500 $4.500 $6.800 $6.090 $5.000 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 2,276.000 $1.000 $1.500 $1.120 $1.100 $1.650 $1.000
530 6016 DRIVEWAYS (BASE) SY 20.000 $50.000 $23.860 $65.000 $98.160 $200.000 $100.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 12.500 $22.000 $37.970 $92.800 $43.890 $45.000 $80.000
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 8.000 $2,000.000 $1,965.000 $3,715.000 $2,271.420 $2,160.000 $3,000.000
540 6007 MTL BEAM GD FEN TRANS (TL2) EA 4.000 $1,500.000 $1,095.000 $3,100.000 $1,265.760 $1,203.000 $2,500.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 1.000 $1,500.000 $1,490.000 $3,100.000 $1,722.360 $1,650.000 $2,750.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 11.000 $3,000.000 $3,159.000 $5,567.000 $3,651.620 $3,471.000 $4,250.000
552 6001 WIRE FENCE (TY A) LF 75.000 $15.000 $14.580 $61.900 $23.120 $16.000 $40.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 8.000 $32.000 $25.000 $105.150 $28.900 $27.000 $50.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 16.000 $25.000 $35.000 $154.650 $40.460 $40.000 $50.000
Totals: $1,314,061.00 $1,258,243.83 $1,556,463.55 $1,564,704.47 $1,685,524.80 $1,966,075.50