Job Info for 6342-37-001

County: ATASCOSA Highway: SH0016 Date: 05/07/2019 (5 years ago) Engineer's Estimate: $1,618,901 Control Number: 6342-37-001
Project: RMC - 634237001 District: SAN ANTONIO Time: 64 CALENDAR DAYS Type: GUARDRAIL REPAIR

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $1,618,901.25
K-BAR SERVICES, INC.   $1,471,267.82 1
-9.12% | -$147,633.43
RELMCO, INC.   $1,549,072.42 2
-4.31% | -$69,828.83
5.29% | $77,804.60
TALBRAN ENTERPRISES LLC   $1,552,744.50 3
-4.09% | -$66,156.75
5.54% | $81,476.68
0.24% | $3,672.08
VANN/ELLI, INC.   $2,444,497.25 4
51% | $825,596.00
66.15% | $973,229.43
57.43% | $891,752.75
3LW CIVIL LLC   $2,635,105.50 5
62.77% | $1,016,204.25
79.1% | $1,163,837.68
7.80% | $190,608.25

Bid Items

Items: 31, 0 filtered
ATASCOSA SH0016  |  SAN ANTONIO  |  6342-37-001  |  05/07/2019  |  $1,618,901  |  RMC - 634237001  |  GUARDRAIL REPAIR  |  64 CALENDAR DAYS
Item code Description Unit Quantity Engineer's Estimate K-BAR SERVICES, INC. RELMCO, INC. TALBRAN ENTERPRISES LLC VANN/ELLI, INC. 3LW CIVIL LLC
104 6028 REMOVING CONC (MISC) SY 10.000 $28.400 $20.000 $50.000 $100.000 $200.000 $100.000
104 6054 REMOVING CONCRETE(MOW STRIP) LF 3,920.000 $8.820 $5.000 $12.000 $9.000 $38.000 $30.000
132 6019 EMBANKMENT (VEHICLE)(ORD COMP)(TY B) CY 9.000 $85.000 $20.000 $100.000 $100.000 $2,000.000 $50.000
161 6017 COMPOST MANUF TOPSOIL (4") SY 25,837.000 $1.500 $4.500 $5.000 $3.500 $10.000 $7.000
164 6003 BROADCAST SEED (PERM) (RURAL) (CLAY) SY 25,837.000 $0.900 $1.300 $0.180 $0.500 $0.750 $3.000
168 6001 VEGETATIVE WATERING MG 402.000 $12.500 $50.000 $20.000 $25.000 $100.000 $160.000
169 6007 SOIL RETENTION BLANKETS (CL 2) (TY G) SY 25,837.000 $3.400 $3.000 $2.470 $4.000 $10.000 $8.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 987.000 $545.000 $450.000 $405.000 $475.000 $610.000 $700.000
450 6018 RAIL (TY T631) LF 450.000 $95.000 $100.000 $105.000 $110.000 $102.000 $200.000
500 6001 MOBILIZATION LS 1.000 $155,000.000 $56,587.220 $160,000.000 $200,000.000 $200,000.000 $250,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 $15,000.000 $6,000.000 $30,000.000 $4,000.000 $15,000.000 $25,000.000
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 1,900.000 $6.250 $4.500 $5.750 $7.000 $10.000 $5.910
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 1,900.000 $1.250 $0.500 $1.100 $4.000 $3.000 $1.760
510 6001 ONE-WAY TRAF CONT (FLAGGER CONT) HR 480.000 $150.000 $100.000 $85.000 $25.000 $95.000 $200.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 10,025.000 $22.000 $24.000 $21.000 $17.000 $24.000 $30.000
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 300.000 $30.000 $40.000 $62.000 $65.000 $75.000 $32.480
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 3.000 $1,850.000 $2,000.000 $1,720.000 $1,850.000 $3,000.000 $2,300.000
540 6010 MTL W-BEAM GD FEN ADJUSTMENT LF 1,500.000 $18.000 $9.000 $12.000 $15.000 $24.000 $18.000
540 6016 DOWNSTREAM ANCHOR TERMINAL SECTION EA 18.000 $1,200.000 $1,500.000 $1,075.000 $1,500.000 $1,200.000 $1,500.000
540 6018 MTL BM GD FEN TRANS (NON - SYM) EA 3.000 $800.000 $500.000 $900.000 $1,500.000 $1,500.000 $1,500.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 7,562.500 $2.500 $2.000 $2.150 $5.000 $3.000 $5.000
542 6002 REMOVE TERMINAL ANCHOR SECTION EA 65.000 $200.000 $300.000 $172.000 $200.000 $200.000 $350.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 56.000 $2,750.000 $3,000.000 $2,690.000 $2,200.000 $3,500.000 $3,500.000
544 6002 GUARDRAIL END TREATMENT (MOVE & RESET) EA 6.000 $1,418.000 $1,200.000 $1,650.000 $1,800.000 $2,500.000 $1,800.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 15.000 $250.000 $250.000 $270.000 $200.000 $200.000 $500.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 311.000 $29.000 $60.000 $25.000 $26.000 $42.000 $40.000
752 6009 TREE REMOVAL (30" - 36" DIA) EA 2.000 $600.000 $2,000.000 $1,500.000 $625.000 $5,000.000 $1,000.000
752 6012 TREE REMOVAL (48" - 60" DIA) EA 2.000 $1,000.000 $2,500.000 $2,000.000 $985.000 $15,000.000 $1,500.000
752 6022 TREE TRIMMING AND BRUSH REMOVAL LF 1,000.000 $20.000 $4.750 $15.000 $15.000 $15.000 $30.000
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 120.000 $125.000 $100.000 $200.000 $250.000 $300.000 $200.000
6185 6002 TMA (STATIONARY) DAY 120.000 $250.000 $200.000 $200.000 $350.000 $400.000 $400.000
Totals: $1,618,901.25 $1,471,267.82 $1,549,072.43 $1,552,744.50 $2,444,497.25 $2,635,105.50