Job Info for 0915-13-029

County: ATASCOSA Highway: CR Date: 05/07/2019 (5 years ago) Engineer's Estimate: $484,586 Control Number: 0915-13-029
Project: BR 2019(907) District: SAN ANTONIO Time: 102 WORKING DAYS Type: REPLACE BRIDGE AND APPROACHES

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $484,585.50
SB CONTRACTORS LLC   $619,853.50 1
27.91% | $135,268.00
TMES LLC   $636,892.27 2
31.43% | $152,306.77
2.75% | $17,038.77
ACME BRIDGE COMPANY, INC.   $726,751.69 3
49.97% | $242,166.19
17.25% | $106,898.19
14.11% | $89,859.42
TREVWAY, INC.   $736,359.15 4
51.96% | $251,773.65
18.8% | $116,505.65
1.32% | $9,607.46
FUQUA CONSTRUCTION CO., INC.   $813,672.40 5
67.91% | $329,086.90
31.27% | $193,818.90
10.50% | $77,313.25
DEAN WORD COMPANY, LTD.   $836,227.89 6
72.57% | $351,642.39
34.91% | $216,374.39
2.77% | $22,555.49
FNH CONSTRUCTION, LLC   $895,110.00 7
84.72% | $410,524.50
44.41% | $275,256.50
7.04% | $58,882.11
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.   $1,138,838.40 8
135.01% | $654,252.90
83.73% | $518,984.90
27.23% | $243,728.40

Bid Items

Items: 43, 0 filtered
ATASCOSA CR  |  SAN ANTONIO  |  0915-13-029  |  05/07/2019  |  $484,586  |  BR 2019(907)  |  REPLACE BRIDGE AND APPROACHES  |  102 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate SB CONTRACTORS LLC TMES LLC ACME BRIDGE COMPANY, INC. TREVWAY, INC. FUQUA CONSTRUCTION CO., INC. DEAN WORD COMPANY, LTD. FNH CONSTRUCTION, LLC SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
100 6002 PREPARING ROW STA 3.500 $4,000.000 $4,000.000 $2,000.000 $7,500.000 $1,274.550 $2,800.000 $4,032.300 $13,000.000 $1,702.230
105 6008 REMOVING STAB BASE AND ASPH PAV (6") SY 600.000 $2.500 $5.000 $6.000 $7.300 $12.390 $9.000 $20.280 $20.000 $13.760
110 6001 EXCAVATION (ROADWAY) CY 903.000 $10.000 $18.000 $8.000 $20.000 $6.590 $15.000 $30.904 $20.000 $14.760
132 6002 EMBANKMENT (FINAL)(DENS CONT)(TY A) CY 162.000 $15.000 $46.000 $15.000 $50.000 $96.790 $20.000 $99.568 $35.000 $88.680
161 6017 COMPOST MANUF TOPSOIL (4") SY 10.000 $1.500 $50.000 $169.050 $112.000 $200.000 $4.000 $229.880 $60.000 $172.130
164 6023 CELL FBR MLCH SEED(PERM)(RURAL)(CLAY) SY 10.000 $2.000 $2.000 $43.700 $112.000 $48.000 $1.000 $39.520 $100.000 $52.230
164 6029 CELL FBR MLCH SEED(TEMP)(WARM) SY 5.000 $2.000 $2.000 $222.000 $224.000 $252.630 $1.000 $200.720 $10.000 $233.150
164 6031 CELL FBR MLCH SEED(TEMP)(COOL) SY 5.000 $2.000 $2.000 $222.000 $224.000 $378.950 $1.000 $200.720 $10.000 $233.150
168 6001 VEGETATIVE WATERING MG 1.000 $50.000 $100.000 $92.000 $89.300 $2,525.000 $60.000 $275.000 $2,000.000 $121.480
169 6001 SOIL RETENTION BLANKETS (CL 1) (TY A) SY 10.000 $1.500 $50.000 $50.000 $33.600 $58.000 $4.000 $47.840 $10.000 $61.030
216 6001 PROOF ROLLING HR 56.000 $100.000 $55.000 $50.000 $72.200 $50.000 $97.000 $59.862 $150.000 $177.480
247 6475 FL BS (CIP)(TY D GR 1-2, OR 5)FINAL POS CY 168.000 $50.000 $110.000 $75.000 $102.000 $151.000 $82.000 $81.982 $80.000 $93.340
316 6224 AGGR(TY-PB GR-4 SAC-B) CY 12.000 $50.000 $350.000 $1,000.000 $721.000 $1,136.840 $600.000 $480.084 $350.000 $470.490
316 6466 ASPH (CHFRS-2P OR CRS-2P) GAL 630.000 $4.000 $12.000 $12.000 $22.200 $21.470 $24.000 $8.712 $10.000 $6.690
400 6005 CEM STABIL BKFL CY 22.000 $115.000 $145.000 $175.000 $229.000 $200.000 $250.000 $125.400 $350.000 $171.160
416 6002 DRILL SHAFT (24 IN) LF 360.000 $180.000 $210.000 $346.000 $345.000 $477.000 $367.000 $340.018 $270.000 $334.660
420 6013 CL C CONC (ABUT) CY 18.400 $850.000 $1,200.000 $750.000 $1,230.000 $798.000 $2,800.000 $1,610.762 $950.000 $1,298.760
422 6007 REINF CONC SLAB (SLAB BEAM) SF 1,300.000 $20.000 $26.000 $20.000 $24.100 $18.000 $22.000 $24.272 $18.000 $221.630
422 6015 APPROACH SLAB CY 38.500 $400.000 $500.000 $450.000 $695.000 $450.000 $679.000 $847.810 $950.000 $869.620
425 6012 PRESTR CONC SLAB BEAM (5SB15) LF 247.500 $175.000 $188.000 $214.940 $287.000 $240.000 $325.000 $253.739 $160.000 $223.210
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 18.000 $500.000 $425.000 $450.000 $821.000 $600.000 $350.000 $410.300 $650.000 $633.570
450 6006 RAIL (TY T223) LF 124.000 $80.000 $115.000 $100.000 $112.000 $119.470 $168.000 $151.800 $185.000 $174.090
459 6007 GABION MATTRESSES (GALV)(12 IN) SY 1,327.300 $60.000 $75.000 $95.250 $78.300 $82.110 $88.000 $103.733 $150.000 $91.180
459 6009 GABIONS (3' X 3')(GALV) CY 234.400 $215.000 $185.000 $347.000 $205.000 $221.000 $380.000 $383.061 $300.000 $332.040
496 6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) EA 1.000 $12,000.000 $15,000.000 $15,390.000 $20,000.000 $25,000.000 $30,000.000 $32,900.000 $50,000.000 $40,556.240
500 6001 MOBILIZATION LS 1.000 $40,000.000 $61,750.000 $42,000.000 $60,000.000 $70,000.000 $75,000.000 $83,500.904 $80,000.000 $174,324.250
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $4,000.000 $5,000.000 $2,100.000 $4,000.000 $1,260.000 $2,500.000 $5,081.569 $5,000.000 $1,101.590
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 224.000 $15.000 $15.000 $16.000 $15.700 $9.000 $17.000 $14.768 $30.000 $16.090
506 6024 CONSTRUCTION EXITS (REMOVE) SY 224.000 $6.000 $5.000 $5.000 $2.250 $5.000 $7.000 $4.784 $15.000 $5.530
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 600.000 $2.750 $4.000 $2.300 $2.500 $3.000 $1.000 $2.600 $4.000 $2.920
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 600.000 $0.750 $0.500 $0.600 $1.100 $1.300 $1.000 $0.520 $2.000 $0.720
540 6002 MTL W-BEAM GD FEN (STEEL POST) LF 100.000 $25.000 $52.000 $34.500 $32.000 $33.000 $26.000 $29.692 $35.000 $37.340
540 6007 MTL BEAM GD FEN TRANS (TL2) EA 4.000 $850.000 $1,100.000 $713.000 $980.000 $1,473.000 $2,600.000 $910.000 $1,850.000 $2,226.070
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $2,500.000 $2,900.000 $2,360.000 $3,030.000 $3,200.000 $3,000.000 $2,813.200 $2,850.000 $3,326.070
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 6.000 $600.000 $571.000 $700.000 $619.000 $700.000 $530.000 $575.110 $650.000 $561.880
644 6076 REMOVE SM RD SN SUP&AM EA 2.000 $85.000 $100.000 $125.000 $112.000 $200.000 $78.000 $104.000 $50.000 $178.630
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 6.000 $20.000 $18.000 $23.000 $17.800 $5.000 $25.000 $16.494 $100.000 $39.380
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 16.000 $20.000 $22.000 $45.000 $23.500 $11.370 $27.000 $21.819 $100.000 $34.020
666 6224 PAVEMENT SEALER 4" LF 700.000 $0.150 $2.000 $2.300 $2.050 $3.000 $4.000 $2.080 $10.000 $2.350
666 6315 RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) LF 700.000 $0.500 $4.000 $4.600 $3.650 $3.000 $4.000 $4.160 $10.000 $4.550
672 6009 REFL PAV MRKR TY II-A-A EA 10.000 $3.000 $30.000 $34.500 $22.400 $126.000 $8.000 $31.200 $15.000 $43.430
678 6001 PAV SURF PREP FOR MRK (4") LF 700.000 $0.500 $1.000 $1.150 $0.840 $3.750 $2.000 $1.040 $2.000 $1.250
6001 6002 PORTABLE CHANGEABLE MESSAGE SIGN EA 2.000 $8,000.000 $15,000.000 $2,090.000 $8,480.000 $8,500.000 $8,800.000 $5,500.000 $14,500.000 $16,552.130
Totals: $484,585.50 $619,853.50 $636,892.27 $726,751.69 $736,359.16 $813,672.40 $836,227.95 $895,110.00 $1,138,838.42