Job Info for 0613-02-063

County: ATASCOSA Highway: SH 16 Date: 05/02/2018 (6 years ago) Engineer's Estimate: $5,215,910 Control Number: 0613-02-063
Project: C 613-2-63 District: SAN ANTONIO Time: 252 WORKING DAYS Type: REPLACE EXISTING BRIDGE

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $5,215,909.88
HARPER BROTHERS CONSTRUCTION LLC   $5,704,330.28 1
9.36% | $488,420.40
DAN WILLIAMS COMPANY   $5,734,991.80 2
9.95% | $519,081.92
0.54% | $30,661.52
J3 COMPANY, LLC   $5,755,176.68 3
10.34% | $539,266.80
0.89% | $50,846.40
0.35% | $20,184.88
CAPITAL EXCAVATION COMPANY   $5,772,536.26 4
10.67% | $556,626.38
1.2% | $68,205.98
0.30% | $17,359.58
RELMCO, INC.   $5,846,460.94 5
12.09% | $630,551.06
2.49% | $142,130.66
1.28% | $73,924.68
SB CONTRACTORS LLC   $6,096,562.73 6
16.88% | $880,652.85
6.88% | $392,232.45
4.28% | $250,101.79
ANDERSON COLUMBIA CO., INC.   $6,959,677.67 7
33.43% | $1,743,767.79
22.01% | $1,255,347.39
14.16% | $863,114.94
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.   $7,095,943.04 8
36.04% | $1,880,033.16
24.4% | $1,391,612.76
1.96% | $136,265.37
JORDAN FOSTER CONSTRUCTION, LLC   $7,131,290.25 9
36.72% | $1,915,380.37
25.02% | $1,426,959.97
0.50% | $35,347.21
ANGEL BROTHERS HOLDINGS CORP.   $7,231,177.43 10
38.64% | $2,015,267.55
26.77% | $1,526,847.15
1.40% | $99,887.18
AUSTIN BRIDGE & ROAD SERVICES, LP   $7,495,802.44 11
43.71% | $2,279,892.56
31.41% | $1,791,472.16
3.66% | $264,625.01

Bid Items

Items: 96, 0 filtered
ATASCOSA SH 16  |  SAN ANTONIO  |  0613-02-063  |  05/02/2018  |  $5,215,910  |  C 613-2-63  |  REPLACE EXIST BRIDGE  |  252 WORKING DAYS
Item code Description Unit Quantity Engineer's Estimate HARPER BROTHERS CONSTRUCTION LLC DAN WILLIAMS COMPANY J3 COMPANY, LLC CAPITAL EXCAVATION COMPANY RELMCO, INC. SB CONTRACTORS LLC ANDERSON COLUMBIA CO., INC. SALINAS CONSTRUCTION TECHNOLOGIES, LTD. JORDAN FOSTER CONSTRUCTION, LLC ANGEL BROTHERS HOLDINGS CORP. AUSTIN BRIDGE & ROAD SERVICES, LP
100 6002 PREPARING ROW STA 25.200 $500.000 $11,300.000 $2,500.000 $4,000.000 $2,000.000 $1,600.000 $1,000.000 $1,720.000 $576.660 $2,500.000 $13,000.000 $2,540.000
104 6009 REMOVING CONC (RIPRAP) SY 1,206.000 $10.000 $2.000 $5.000 $10.000 $8.000 $8.510 $14.000 $10.000 $7.670 $5.000 $9.000 $11.000
106 6001 OBLITERATING ABANDONED ROAD STA 21.410 $1,368.000 $1,250.000 $1,150.000 $1,500.000 $1,000.000 $1,402.500 $1,000.000 $260.000 $4,397.250 $1,200.000 $900.000 $2,000.000
110 6001 EXCAVATION (ROADWAY) CY 11,216.000 $8.860 $9.000 $7.500 $8.000 $7.000 $5.940 $14.000 $9.000 $5.000 $6.000 $9.000 $9.000
110 6002 EXCAVATION (CHANNEL) CY 4,327.000 $13.100 $7.000 $7.500 $10.000 $6.000 $8.110 $5.000 $12.000 $5.520 $11.000 $12.000 $17.000
132 6003 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 13,369.000 $9.000 $18.000 $7.500 $5.000 $4.000 $9.240 $12.000 $19.000 $4.170 $7.000 $15.000 $30.000
160 6006 FURNISHING AND PLACING TOPSOIL (3") SY 29,501.000 $0.750 $0.600 $1.000 $1.000 $1.000 $0.460 $2.750 $0.320 $2.150 $2.500 $0.900 $2.000
161 6024 GENERAL USE COMPOST (2") SY 33,785.000 $1.500 $1.100 $1.100 $1.000 $1.000 $1.250 $1.200 $1.100 $3.190 $2.000 $1.200 $1.100
162 6004 MULCH SODDING SY 3,460.000 $4.000 $4.750 $4.800 $4.000 $4.750 $3.140 $7.000 $5.000 $6.770 $4.750 $4.000 $4.750
164 6005 BROADCAST SEED (PERM) (URBAN) (SANDY) SY 841.000 $0.500 $0.140 $0.150 $0.160 $0.140 $0.170 $1.140 $0.140 $0.200 $0.200 $0.160 $0.140
164 6013 STRAW/HAY MLCH SEED(PERM)(RURAL)(SANDY) SY 18,818.000 $0.260 $0.780 $0.800 $0.800 $0.780 $0.840 $0.900 $0.800 $0.530 $0.800 $0.800 $0.780
164 6033 DRILL SEEDING (PERM) (RURAL) (SANDY) SY 10,684.000 $0.200 $0.140 $0.150 $0.160 $0.140 $0.170 $0.200 $0.140 $0.210 $0.200 $0.160 $0.140
164 6071 BROADCAST SEED (TEMP)(WARM OR COOL) SY 33,785.000 $0.200 $0.120 $0.120 $0.120 $0.120 $0.130 $0.200 $0.120 $0.110 $0.150 $0.120 $0.120
166 6001 FERTILIZER AC 7.040 $145.000 $180.000 $180.000 $300.000 $180.000 $315.000 $350.000 $184.000 $498.260 $300.000 $300.000 $180.000
168 6001 VEGETATIVE WATERING MG 527.700 $12.000 $20.000 $8.000 $24.970 $5.000 $20.000 $30.000 $26.000 $38.630 $10.000 $18.000 $35.000
169 6002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY 4,512.000 $0.910 $0.820 $0.850 $1.200 $0.820 $1.260 $1.200 $0.850 $1.530 $1.200 $1.200 $0.820
169 6004 SOIL RETENTION BLANKETS (CL 1) (TY D) SY 6,171.000 $1.250 $0.820 $0.850 $1.200 $0.820 $1.260 $1.200 $0.850 $1.820 $1.200 $1.200 $0.820
169 6006 SOIL RETENTION BLANKETS (CL 2) (TY F) SY 841.000 $4.230 $1.750 $1.800 $1.650 $1.750 $1.730 $6.500 $2.000 $1.900 $1.700 $1.650 $1.750
247 6053 FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS) CY 2,214.000 $30.000 $45.000 $40.000 $42.920 $49.000 $52.420 $50.000 $44.000 $62.530 $59.000 $52.000 $45.000
275 6001 CEMENT TON 122.000 $130.000 $162.040 $136.000 $140.000 $130.000 $185.690 $143.000 $150.000 $161.640 $150.000 $180.000 $180.000
275 6376 CEMENT TREAT (NEW BASE) (7.5") SY 10,619.000 $2.000 $2.200 $1.850 $3.000 $1.500 $1.500 $4.000 $3.300 $2.730 $4.250 $2.200 $3.000
310 6009 PRIME COAT (MC-30) GAL 2,126.000 $3.870 $2.900 $2.900 $2.870 $3.000 $6.450 $4.000 $5.000 $3.800 $3.500 $5.300 $5.500
316 6409 AGGR (TY-B GR-4) CY 203.000 $38.000 $75.500 $80.000 $75.500 $79.000 $150.200 $76.000 $100.000 $129.830 $75.000 $120.000 $130.000
316 6410 ASPH(AC-15P,AC-20-5TR,AC-20XP,AC10-2TR) GAL 6,377.000 $2.500 $2.600 $2.750 $2.550 $2.750 $3.500 $3.000 $3.500 $3.700 $2.750 $3.500 $3.700
340 6242 D-GR HMA(SQ)TY-B OR D PG64-22(LVL-UP) TON 44.000 $85.340 $93.000 $95.000 $100.000 $97.000 $202.830 $100.000 $160.000 $245.730 $105.000 $140.000 $150.000
341 6008 D-GR HMA TY-B PG64-22 TON 3,429.000 $60.000 $55.000 $60.000 $55.000 $58.000 $77.230 $67.500 $78.000 $87.000 $69.000 $72.000 $74.000
344 6063 SUPERPAVE MIXTURES SP-C SAC-A PG76-22 TON 2,420.000 $75.000 $73.000 $75.000 $73.000 $77.000 $102.050 $81.000 $85.000 $102.930 $81.000 $90.000 $92.000
354 6045 PLANE ASPH CONC PAV (2") SY 10,863.000 $1.000 $2.500 $1.650 $2.500 $2.020 $4.350 $2.100 $2.000 $2.990 $3.000 $1.400 $2.000
400 6005 CEM STABIL BKFL CY 41.000 $100.000 $131.000 $145.000 $125.000 $140.000 $103.430 $140.000 $160.000 $113.740 $125.000 $175.000 $200.000
403 6001 TEMPORARY SPL SHORING SF 1,785.000 $12.000 $22.000 $8.000 $40.000 $10.000 $25.530 $22.000 $36.000 $22.430 $20.000 $25.000 $1.000
416 6001 DRILL SHAFT (18 IN) LF 720.000 $65.000 $47.000 $80.000 $60.000 $76.000 $54.600 $83.000 $46.000 $174.450 $48.500 $100.000 $60.000
416 6004 DRILL SHAFT (36 IN) LF 13,123.000 $125.000 $139.780 $145.000 $155.000 $161.000 $157.000 $129.000 $178.000 $171.190 $163.000 $151.000 $180.000
416 6006 DRILL SHAFT (48 IN) LF 720.000 $207.950 $235.000 $235.000 $250.000 $249.000 $365.750 $205.000 $275.000 $347.430 $295.000 $350.000 $275.000
420 6013 CL C CONC (ABUT) CY 106.000 $800.000 $650.000 $750.000 $750.000 $730.000 $712.470 $550.000 $866.000 $882.110 $780.000 $1,000.000 $1,310.000
420 6029 CL C CONC (CAP) CY 59.750 $900.000 $875.000 $850.000 $750.000 $725.000 $788.290 $850.000 $1,080.000 $1,027.910 $1,600.000 $1,000.000 $1,055.000
420 6037 CL C CONC (COLUMN) CY 16.000 $870.000 $920.000 $1,000.000 $750.000 $800.000 $1,166.370 $1,200.000 $1,150.000 $1,411.520 $1,300.000 $1,200.000 $1,465.000
422 6001 REINF CONC SLAB SF 16,920.000 $12.860 $18.000 $15.250 $15.000 $14.000 $13.740 $15.000 $19.000 $20.380 $19.500 $18.000 $18.000
422 6015 APPROACH SLAB CY 153.500 $400.000 $345.000 $385.000 $500.000 $485.000 $635.180 $315.000 $350.000 $541.930 $500.000 $520.000 $500.000
422 6023 SHEAR KEY CY 1.900 $281.410 $1,900.000 $650.000 $2,000.000 $1,702.820 $1,025.140 $400.000 $3,900.000 $2,770.040 $375.000 $1,200.000 $1,935.000
423 6007 RETAINING WALL (DRILL SHAFT) (FACIA) SF 10,173.000 $49.000 $24.850 $42.000 $40.000 $40.000 $24.230 $50.000 $51.000 $30.780 $69.000 $64.000 $50.000
425 6039 PRESTR CONC GIRDER (TX54) LF 2,150.000 $106.000 $215.500 $135.000 $126.000 $136.000 $153.770 $150.000 $150.000 $153.660 $133.500 $170.000 $168.000
432 6009 RIPRAP (CONC) (CL B) (4") CY 130.000 $320.000 $366.000 $350.000 $350.000 $370.000 $415.000 $325.000 $440.000 $557.560 $450.000 $440.000 $560.000
432 6010 RIPRAP (CONC)(CL B)(5 IN) CY 80.000 $340.000 $350.000 $350.000 $400.000 $375.000 $415.000 $300.000 $450.000 $523.610 $500.000 $440.000 $445.000
432 6033 RIPRAP (STONE PROTECTION)(18 IN) CY 880.000 $70.000 $160.000 $105.000 $90.000 $150.000 $93.740 $135.000 $110.000 $110.270 $165.000 $120.000 $210.000
432 6045 RIPRAP (MOW STRIP)(4 IN) CY 55.000 $400.000 $470.000 $425.000 $385.000 $470.000 $450.000 $485.000 $450.000 $550.460 $400.000 $460.000 $645.000
450 6038 RAIL (TY C412) LF 828.000 $160.000 $110.000 $115.000 $95.000 $135.000 $113.100 $130.000 $257.000 $80.400 $175.000 $170.000 $150.000
454 6002 SEALED EXPANSION JOINT (5 IN) (SEJ - A) LF 132.300 $113.520 $100.000 $105.000 $100.000 $104.030 $115.950 $95.000 $107.000 $239.670 $110.000 $90.000 $185.000
460 6002 CMP (GAL STL 18 IN) LF 38.000 $50.000 $42.000 $40.000 $40.000 $92.870 $55.260 $40.000 $77.000 $103.120 $70.000 $80.000 $60.000
467 6348 SET (TY II) (18 IN) (CMP) (6: 1) (P) EA 2.000 $1,100.000 $1,700.000 $550.000 $500.000 $1,059.170 $565.500 $900.000 $1,140.000 $465.590 $1,500.000 $1,300.000 $1,450.000
496 6010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) EA 1.000 $80,000.000 $40,500.000 $50,000.000 $85,000.000 $30,000.000 $37,500.000 $50,000.000 $66,000.000 $72,146.410 $124,250.000 $75,000.000 $79,000.000
496 6043 REMOV STR (SMALL FENCE) LF 955.000 $3.000 $4.000 $1.000 $5.000 $1.400 $0.830 $5.000 $3.000 $10.960 $3.000 $1.400 $6.000
500 6001 MOBILIZATION LS 1.000 $382,215.550 $57,000.000 $570,000.000 $375,003.000 $426,000.000 $365,000.000 $592,500.000 $520,000.000 $670,291.720 $625,000.000 $700,000.000 $740,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 16.000 $3,500.000 $2,000.000 $2,800.000 $3,500.000 $1,000.000 $1,204.690 $1,100.000 $2,120.000 $745.650 $12,500.000 $5,000.000 $2,100.000
506 6003 ROCK FILTER DAMS (INSTALL) (TY 3) LF 610.000 $35.000 $45.500 $46.000 $42.000 $45.500 $44.100 $48.000 $42.000 $84.300 $90.000 $42.000 $42.000
506 6004 ROCK FILTER DAMS (INSTALL) (TY 4) LF 234.000 $24.000 $28.500 $29.000 $28.900 $28.500 $30.350 $30.000 $30.000 $32.550 $42.000 $29.000 $29.000
506 6011 ROCK FILTER DAMS (REMOVE) LF 844.000 $6.000 $12.000 $12.000 $6.000 $12.000 $6.300 $12.000 $6.000 $18.560 $8.000 $6.000 $6.000
506 6020 CONSTRUCTION EXITS (INSTALL) (TY 1) SY 666.000 $13.370 $12.500 $13.000 $18.680 $12.500 $19.610 $15.000 $19.000 $14.940 $19.000 $19.000 $19.000
506 6024 CONSTRUCTION EXITS (REMOVE) SY 666.000 $4.000 $10.000 $10.000 $8.000 $10.000 $6.300 $5.000 $6.000 $6.360 $6.000 $6.000 $6.000
506 6030 BACKHOE WORK (EROSION & SEDMT CONT) HR 160.000 $50.000 $55.000 $35.000 $28.380 $59.400 $55.000 $55.000 $72.000 $185.570 $60.000 $75.000 $160.000
506 6034 CONSTRUCTION PERIMETER FENCE LF 1,105.000 $2.150 $6.000 $9.000 $2.250 $2.650 $2.360 $3.000 $2.300 $2.880 $4.000 $2.300 $2.250
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 3,666.000 $1.760 $2.250 $2.300 $2.250 $2.250 $2.360 $3.000 $2.300 $2.480 $2.250 $2.300 $2.250
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 3,666.000 $0.410 $0.750 $0.750 $0.250 $0.750 $0.260 $0.750 $0.260 $0.280 $0.250 $0.250 $0.250
506 6041 BIODEG EROSN CONT LOGS (INSTL) (12") LF 8,239.000 $3.500 $3.750 $3.800 $3.000 $3.750 $3.150 $4.000 $3.000 $6.000 $3.000 $3.000 $3.000
506 6043 BIODEG EROSN CONT LOGS (REMOVE) LF 8,239.000 $0.750 $0.750 $0.750 $1.000 $0.750 $1.050 $0.750 $1.000 $1.100 $1.100 $1.000 $1.000
508 6001 CONSTRUCTING DETOURS SY 468.000 $36.000 $24.000 $45.000 $55.000 $75.200 $52.830 $52.000 $56.000 $127.070 $55.000 $55.000 $75.000
510 6002 ONE-WAY TRAF CONT (PILOT CAR) HR 144.000 $63.500 $85.000 $75.000 $70.000 $109.620 $195.000 $100.000 $158.000 $90.060 $80.000 $86.000 $100.000
512 6067 PTB (FRN&INSTL)(F SHAPE)(TY 1) OR (STL) LF 3,600.000 $9.000 $35.000 $15.000 $15.000 $9.000 $9.750 $45.000 $43.000 $32.830 $33.000 $25.000 $12.000
512 6069 PTB (MOVE)(F SHAPE)(TY 1) OR (STL) LF 2,910.000 $5.000 $4.500 $3.000 $5.000 $5.000 $4.550 $8.000 $8.000 $7.990 $4.000 $8.000 $8.000
512 6071 PTB (REMOVE)(F SHAPE)(TY 1) OR (STL) LF 3,600.000 $8.000 $9.000 $8.000 $10.000 $9.000 $7.020 $10.000 $13.000 $6.680 $7.000 $13.000 $12.000
530 6015 DRIVEWAYS AND TURNOUTS (SURF TREAT) SY 617.400 $24.500 $14.000 $24.000 $40.000 $40.000 $25.800 $17.000 $35.000 $54.950 $25.000 $34.000 $45.000
540 6001 MTL W-BEAM GD FEN (TIM POST) LF 944.000 $19.540 $21.630 $22.000 $19.750 $22.750 $20.740 $22.750 $20.000 $22.850 $20.000 $22.000 $19.750
540 6006 MTL BEAM GD FEN TRANS (THRIE-BEAM) EA 4.000 $1,795.840 $1,616.000 $2,000.000 $1,245.000 $1,845.000 $1,307.250 $1,845.000 $1,780.000 $1,710.730 $1,250.000 $1,700.000 $1,245.000
542 6001 REMOVE METAL BEAM GUARD FENCE LF 651.000 $1.100 $2.000 $1.000 $1.000 $2.500 $1.050 $2.000 $1.000 $2.240 $1.000 $1.000 $1.000
542 6004 RM MTL BM GD FENCE TRANS (THRIE-BEAM) EA 4.000 $150.000 $198.000 $150.000 $100.000 $185.000 $105.000 $150.000 $102.000 $214.730 $100.000 $100.000 $100.000
544 6001 GUARDRAIL END TREATMENT (INSTALL) EA 4.000 $2,345.670 $2,522.200 $2,500.000 $2,496.000 $2,696.000 $2,620.800 $2,700.000 $2,540.000 $214.730 $2,500.000 $2,800.000 $2,496.000
544 6003 GUARDRAIL END TREATMENT (REMOVE) EA 4.000 $70.000 $276.000 $200.000 $125.000 $275.000 $131.250 $275.000 $125.000 $2,667.730 $125.000 $140.000 $125.000
545 6003 CRASH CUSH ATTEN (MOVE & RESET) EA 2.000 $758.290 $1,735.000 $500.000 $1,000.000 $2,750.000 $2,739.750 $2,750.000 $1,020.000 $1,842.970 $1,000.000 $1,000.000 $1,000.000
545 6005 CRASH CUSH ATTEN (REMOVE) EA 8.000 $208.520 $1,032.000 $400.000 $500.000 $1,000.000 $1,089.080 $1,000.000 $760.000 $1,091.870 $500.000 $500.000 $500.000
545 6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) EA 8.000 $7,066.250 $9,240.000 $6,000.000 $6,250.000 $9,500.000 $6,500.000 $10,000.000 $6,590.000 $9,754.370 $6,500.000 $6,500.000 $6,250.000
560 6001 MAILBOX INSTALL-S (TWG-POST) TY 1 EA 2.000 $130.000 $153.000 $200.000 $153.000 $153.000 $185.850 $153.000 $155.000 $179.770 $180.000 $160.000 $153.000
560 6002 MAILBOX INSTALL-D (TWG-POST) TY 1 EA 1.000 $180.000 $192.000 $255.000 $192.000 $192.000 $236.730 $192.000 $194.000 $234.130 $230.000 $200.000 $192.000
644 6001 IN SM RD SN SUP&AM TY10BWG(1)SA(P) EA 8.000 $400.000 $407.000 $480.000 $407.000 $407.000 $507.830 $407.000 $415.000 $450.570 $485.000 $420.000 $407.000
644 6076 REMOVE SM RD SN SUP&AM EA 6.000 $56.790 $75.000 $95.000 $75.000 $75.000 $105.000 $75.000 $76.000 $86.320 $100.000 $75.000 $75.000
658 6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) EA 6.000 $22.130 $16.000 $14.000 $16.000 $16.000 $14.180 $16.000 $16.000 $21.420 $13.500 $16.000 $16.000
658 6017 INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BR) EA 11.000 $16.000 $18.000 $14.000 $18.000 $18.000 $14.180 $18.000 $18.000 $21.880 $13.500 $18.000 $18.000
658 6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) EA 4.000 $18.660 $22.000 $17.000 $22.000 $22.000 $16.800 $22.000 $22.000 $29.930 $16.000 $22.000 $22.000
662 6077 WK ZN PAV MRK REMOV (W)4"(SLD W/MRKR) LF 19,060.000 $0.500 $0.570 $0.580 $0.570 $0.570 $0.600 $0.570 $0.600 $0.630 $0.600 $0.600 $0.570
662 6104 WK ZN PAV MRK REMOV (Y)4"(SLD W/MRKR) LF 22,880.000 $0.500 $0.570 $0.580 $0.570 $0.570 $0.600 $0.570 $0.600 $0.630 $0.600 $0.600 $0.570
666 6224 PAVEMENT SEALER 4" LF 22,184.000 $0.070 $0.120 $0.130 $0.120 $0.120 $0.130 $0.120 $0.120 $0.130 $0.150 $0.120 $0.120
666 6342 REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) LF 11,094.000 $0.800 $0.680 $0.690 $0.680 $0.680 $0.710 $0.680 $0.700 $0.750 $0.700 $0.700 $0.680
666 6345 REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL) LF 11,094.000 $0.800 $0.680 $0.690 $0.680 $0.680 $0.710 $0.680 $0.700 $0.750 $0.700 $0.700 $0.680
672 6009 REFL PAV MRKR TY II-A-A EA 109.000 $3.000 $5.000 $5.100 $5.000 $5.000 $5.250 $5.000 $5.100 $5.710 $5.000 $5.000 $5.000
677 6001 ELIM EXT PAV MRK & MRKS (4") LF 10,371.000 $0.590 $0.470 $0.500 $0.470 $0.470 $0.490 $0.470 $0.500 $0.520 $0.500 $0.500 $0.470
678 6001 PAV SURF PREP FOR MRK (4") LF 1,776.000 $0.150 $0.200 $0.210 $0.200 $0.200 $0.210 $0.200 $0.200 $0.230 $0.200 $0.200 $0.200
6001 6001 PORTABLE CHANGEABLE MESSAGE SIGN DAY 196.000 $60.000 $165.000 $80.000 $60.000 $38.270 $115.000 $100.000 $26.000 $262.570 $50.000 $75.000 $100.000
6185 6002 TMA (STATIONARY) DAY 28.000 $200.000 $380.000 $215.000 $165.000 $65.000 $252.870 $200.000 $190.000 $613.200 $160.000 $250.000 $320.000
Totals: $5,215,909.89 $5,704,330.28 $5,734,991.80 $5,755,176.69 $5,772,536.28 $5,846,460.96 $6,096,562.73 $6,959,677.67 $7,095,943.06 $7,131,290.25 $7,231,177.43 $7,495,802.44