Bid Cobra

ARCHER BU 82-F (0156-05-064)

Items: 32

County: ARCHER
Length: N/A
Highway: BU 82-F
District: WICHITA FALLS
Control Number: 0156-05-064
DBE Goal: N/A
Project: BR 2023(508)
Guaranty: N/A
Time: 85 WORKING DAYS
Engineer's Estimate: $1,600,522.25
Date: 03/07/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
ZACHARY HUSEN
ANTHONY BOUCHER
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$1,600,522.25
Over/Under Est: 11.6% $185,684.25
$2,113,524.00
Over/Under Est: 32.05% $513,001.75
Amt Left: 18.32% $327,317.50
Over/Under Est: 60.23% $963,942.96
Amt Left: 43.57% $778,258.71
Delta: -21.34% -$450,941.21

Bid Items & Bid Tabulations

32 Total 0 of 32
ARCHER  |  BU 82-F  |  WICHITA FALLS  |  0156-05-064  |  03/07/2023  |  $1,600,522.25  |  BR 2023(508)  |  BRIDGE REPL  |  85 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HODGES AND SON CONSTRUCTION COMPANY, INC.
EARTH BUILDERS, L.P.
INDUS ROAD & BRIDGE, INC.
PREPARING ROW
STA 4.100 $4,500.000 $12,000.000 $20,000.000 $15,000.000
EXCAVATION (ROADWAY AND CHANNEL)
CY 962.000 $25.000 $20.000 $35.000 $80.000
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 1,377.000 $1.000 $1.500 $2.000 $2.000
VEGETATIVE WATERING
MG 10.000 $75.000 $1.000 $150.000 $280.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 1,377.000 $1.500 $3.000 $3.000 $2.100
CEM STABIL BKFL
CY 387.000 $215.000 $240.000 $260.000 $360.000
CUT & RESTORING PAV
SY 528.000 $175.000 $85.000 $150.000 $175.000
TEMPORARY SPL SHORING
SF 2,412.000 $35.000 $35.000 $12.000 $80.000
RIPRAP (CONC)(4 IN)
CY 188.000 $475.000 $600.000 $750.000 $700.000
RIPRAP (CONC)(5 IN)
CY 57.000 $500.000 $600.000 $750.000 $800.000
RIPRAP (MOW STRIP)(4 IN)
CY 51.000 $525.000 $600.000 $600.000 $900.000
CONC BOX CULV (8 FT X 5 FT)
LF 216.000 $1,000.000 $1,400.000 $1,800.000 $1,000.000
CONC BOX CULV (10 FT X 5 FT)
LF 288.000 $1,500.000 $1,720.000 $2,000.000 $1,200.000
WINGWALL (FW - 0) (HW=6 FT)
EA 4.000 $25,000.000 $35,000.000 $25,000.000 $40,000.000
REMOV STR (WINGWALL)
EA 4.000 $2,000.000 $8,000.000 $10,000.000 $10,000.000
REMOV STR (BOX CULVERT)
LF 792.000 $150.000 $60.000 $180.000 $600.000
MOBILIZATION
LS 1.000 $113,974.750 $160,000.000 $200,000.000 $253,339.510
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $15,000.000 $9,000.000 $3,000.000 $15,000.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 380.000 $10.000 $8.000 $6.000 $9.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 380.000 $1.000 $1.000 $2.000 $2.000
DRIVEWAYS (BASE)
SY 290.000 $25.000 $20.000 $35.000 $170.000
MTL W-BEAM GD FEN (TIM POST)
LF 625.000 $25.000 $22.000 $30.000 $45.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $1,100.000 $1,300.000 $1,600.000 $2,000.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 175.000 $75.000 $85.000 $50.000 $100.000
REMOVE METAL BEAM GUARD FENCE
LF 775.000 $1.000 $1.000 $5.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $450.000 $500.000 $250.000 $350.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $2,850.000 $2,800.000 $3,500.000 $5,200.000
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000 $250.000 $250.000 $350.000 $300.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 11.000 $50.000 $30.000 $30.000 $60.000
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 4.000 $250.000 $500.000 $500.000 $500.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $7,500.000 $15,000.000 $15,000.000 $30,000.000
TMA (STATIONARY)
DAY 40.000 $350.000 $100.000 $250.000 $425.000
Totals: $1,600,522.250 $1,786,206.500 $2,113,524.000 $2,564,465.210