Show Job Controls
Bid Cobra

ARANSAS SH 35 (0180-04-120)

Items: 146

County: ARANSAS
Length: N/A
Highway: SH 35
District: CORPUS CHRISTI
Control Number: 0180-04-120
DBE Goal: N/A
Project: C 180-4-120
Guaranty: N/A
Time: 278 WORKING DAYS
Engineer's Estimate: $25,403,884.49
Date: 03/08/2023 (3 years ago)
Contract Number: N/A
Type: INTERCHANGE IMPROVEMENT (NEW OR UPDATE)
Mail/Deliver Bids To: N/A
ROBERT ISASSI
JOSE GALLEGOS
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$25,403,884.49
$22,334,443.85
Over/Under Est: -12.08% -$3,069,440.64
$28,970,082.16
Over/Under Est: 14.04% $3,566,197.67
Amt Left: 29.71% $6,635,638.31
$35,298,548.50
Over/Under Est: 38.95% $9,894,664.01
Amt Left: 58.05% $12,964,104.65
Delta: -21.84% -$6,328,466.34
Subcontractor Percentage Amount
FLOVERA CONSTRUCTION SERVICES, LLC 8.66% $1,973,209.84
M & D FOUNDATION DRILLING INDUSTRIES, INC. 3.50% $797,486.65
HIGHWAY BARRICADES AND SERVICES, LLC 1.43% $325,830.26
TRAF-TEX, INC. 1.36% $309,880.53
AARON CONCRETE CONTRACTORS, LLC 1.02% $232,410.40
DEPENDABLE FENCE 0.86% $195,953.86
ISLAND CONSTRUCTION, L.P. 0.64% $145,826.13
EPIC ENERGY SERVICES LLC 0.43% $97,976.93
K. L. DURHAM CONSTRUCTION, L.L.C. 0.34% $77,470.13
BROOKE PAVING AND CONSTRUCTION LLC 0.18% $41,013.60
DORAN STEEL, INC. 0.17% $38,735.07
TEXAS ICON CONSTRUCTION, LLC 0.17% $38,735.07
PRIMATE CONSTRUCTION, LP 0.06% $13,671.20
TORO BRAVO CONSTRUCTION, LLC 0.00% $0.00
Total: 18.82% $4,288,199.67

Bid Items & Bid Tabulations

146 Total 0 of 146
ARANSAS  |  SH 35  |  CORPUS CHRISTI  |  0180-04-120  |  03/08/2023  |  $25,403,884.49  |  C 180-4-120  |  INTERCHANGE IMPRV (NEW OR UPDATE)  |  278 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ANDERSON COLUMBIA CO., INC.
HUNTER INDUSTRIES, LTD.
BAY LTD.
PREPARING ROW
STA 72.000 $5,000.000 $2,000.000 $3,060.000 $6,500.000
REMOVE STAB BASE & ASPH PAV (13"-18")
SY 25,350.000 $10.000 $4.550 $9.400 $10.000
EXCAVATION (ROADWAY)
CY 36,198.000 $10.000 $6.300 $12.900 $17.250
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 134,292.000 $10.000 $24.000 $39.100 $16.000
EMBANKMENT (FINAL)(DC)(TY C)(RWAL FND)
CY 4,816.000 $25.000 $24.000 $86.500 $59.000
BACKFILL (TY A OR B)
STA 113.000 $200.000 $117.000 $134.500 $370.000
FURNISHING AND PLACING TOPSOIL (4")
SY 125,909.000 $1.000 $0.850 $1.510 $3.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 125,909.000 $0.150 $0.250 $0.250 $0.300
FERTILIZER
AC 29.000 $650.000 $266.000 $854.740 $1,000.000
VEGETATIVE WATERING
MG 2,299.000 $25.000 $35.000 $24.500 $39.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 23,323.000 $100.000 $85.000 $119.620 $145.000
CEMENT
TON 2,377.000 $150.000 $224.000 $253.000 $360.000
CEMENT TREAT (SUBGRADE) (8")
SY 71,680.000 $5.000 $4.350 $2.640 $6.000
PRIME COAT (MC-30)
GAL 13,694.000 $5.000 $4.450 $6.460 $5.000
ASPH (MULTI OPTION)
GAL 47,120.000 $5.000 $3.200 $4.260 $4.500
AGGR(TY-PB GR-3 OR TY-PB GR-3S)(SAC-B)
CY 1,117.000 $150.000 $177.000 $184.740 $225.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 3,543.000 $4.000 $5.250 $5.980 $5.000
CEM STABIL BKFL
CY 632.000 $150.000 $39.000 $181.820 $150.000
CUT & RESTORE ASPH PAVING
SY 237.000 $125.000 $191.000 $616.320 $120.000
FOUNDATON LOADTEST(D4945)(DRILLD SHAFT)
EA 1.000 $20,000.000 $33,900.000 $30,441.860 $39,000.000
DRILL SHAFT (36 IN)
LF 1,340.000 $400.000 $285.000 $285.390 $280.000
DRILL SHAFT (42 IN)
LF 2,052.000 $400.000 $351.000 $320.370 $450.000
DRILL SHAFT (SIGN MTS) (24 IN)
LF 130.000 $300.000 $60.000 $54.000 $95.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 192.000 $200.000 $220.000 $311.000 $375.000
CL C CONC (ABUT)
CY 81.000 $1,000.000 $1,430.000 $1,715.590 $1,475.000
CL C CONC (CAP)
CY 149.600 $1,000.000 $1,260.000 $1,529.770 $1,300.000
CL C CONC (COLUMN)
CY 106.400 $1,000.000 $1,420.000 $1,421.020 $1,400.000
REINF CONC SLAB
SF 37,813.000 $15.000 $27.000 $26.600 $42.000
APPROACH SLAB
CY 211.000 $500.000 $831.000 $900.770 $925.000
RETAINING WALL (MSE)
SF 51,058.000 $100.000 $49.000 $49.210 $155.000
PRESTR CONC GIRDER (TX46)
LF 4,474.800 $150.000 $193.000 $191.280 $246.000
RIPRAP (CONC)(4 IN)
CY 142.000 $500.000 $564.000 $946.210 $920.000
RIPRAP (CONC)(CL B)
CY 9.000 $700.000 $1,230.000 $1,235.260 $1,870.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 128.000 $500.000 $592.000 $740.880 $985.000
RIPRAP (CONC)(CL B)(5 IN)
CY 134.000 $600.000 $567.000 $658.220 $1,015.000
RIPRAP (MOW STRIP)(5 IN)
CY 183.000 $500.000 $631.000 $924.400 $943.000
RAIL (TY SSTR)
LF 3,974.000 $50.000 $69.000 $89.300 $130.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 260.000 $100.000 $216.000 $264.490 $260.000
CONC BOX CULV (4 FT X 3 FT)
LF 11.000 $500.000 $424.000 $431.550 $990.000
RC PIPE (CL III)(18 IN)
LF 257.000 $75.000 $96.000 $87.420 $150.000
RC PIPE (CL III)(24 IN)
LF 493.200 $90.000 $113.000 $107.060 $155.000
RC PIPE (CL III)(30 IN)
LF 3,440.500 $150.000 $121.000 $136.720 $180.000
RC PIPE (CL III)(36 IN)
LF 471.000 $200.000 $200.000 $185.170 $250.000
RC PIPE (CL III)(48 IN)
LF 230.000 $200.000 $252.000 $279.740 $350.000
INLET (COMPL)(PSL)(RC)(5FTX5FT)
EA 15.000 $5,000.000 $6,430.000 $8,246.970 $12,000.000
INLET (COMPL)(PSL)(RC)(8FTX8FT)
EA 2.000 $15,000.000 $11,500.000 $17,741.890 $22,650.000
INLET (COMPL)(PSL)(FG)(6FTX6FT-4FTX4FT)
EA 3.000 $7,000.000 $7,930.000 $13,378.330 $14,500.000
INLET (COMPL)(TY MSE1)
EA 10.000 $3,000.000 $6,210.000 $9,419.570 $7,500.000
SET (TY I)(S= 4 FT)(HW= 5 FT)(6:1) (P)
EA 1.000 $10,000.000 $13,000.000 $20,383.460 $21,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (C)
EA 2.000 $1,000.000 $2,030.000 $2,042.880 $3,800.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 4.000 $2,000.000 $2,030.000 $2,042.880 $3,800.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 1.000 $2,500.000 $2,260.000 $2,384.120 $6,800.000
SET (TY II) (30 IN) (RCP) (6: 1) (C)
EA 7.000 $3,000.000 $2,740.000 $3,907.850 $7,400.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 8.000 $5,000.000 $3,220.000 $4,419.900 $7,500.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 6.000 $5,000.000 $3,070.000 $7,620.240 $8,300.000
SET (TY II) (36 IN) (RCP) (6: 1) (C)
EA 6.000 $5,000.000 $3,350.000 $8,215.120 $9,400.000
REMOV STR (MANHOLE)
EA 5.000 $500.000 $931.000 $1,102.500 $4,300.000
REMOV STR (SET)
EA 24.000 $1,000.000 $466.000 $630.000 $1,100.000
REMOV STR (PIPE)
LF 1,861.000 $30.000 $24.000 $23.100 $65.000
MOBILIZATION
LS 1.000 $1,681,799.190 $1,242,000.000 $2,625,573.650 $740,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $10,000.000 $5,500.000 $4,107.640 $29,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $20.000 $30.000 $58.890 $110.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $10.000 $6.850 $16.110 $40.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 520.000 $2.000 $4.600 $9.190 $15.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 520.000 $1.000 $2.100 $2.480 $4.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 120.000 $5.000 $9.800 $9.080 $31.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 120.000 $1.000 $5.000 $3.100 $9.000
CONSTRUCTING DETOURS
SY 3,420.000 $200.000 $110.000 $108.500 $195.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 7,860.000 $40.000 $43.000 $31.870 $17.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 11,600.000 $10.000 $9.950 $9.250 $15.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 7,860.000 $10.000 $16.000 $13.470 $16.000
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 2,400.000 $75.000 $102.000 $142.600 $229.000
CONC CURB & GUTTER (TY II)
LF 1,379.000 $25.000 $26.000 $38.810 $50.000
INTERSECTIONS (ACP)
SY 1,297.000 $50.000 $33.000 $43.800 $100.000
DRIVEWAYS (ACP)
SY 2,246.000 $50.000 $37.000 $43.800 $98.000
RUMBLE STRIPS (SHOULDER)
LF 49,408.000 $0.150 $0.400 $0.280 $0.750
CRASH CUSH ATTEN (MOVE & RESET)
EA 9.000 $1,500.000 $1,110.000 $1,000.000 $4,700.000
CRASH CUSH ATTEN (REMOVE)
EA 9.000 $2,000.000 $970.000 $875.000 $690.000
CRASH CUSH ATTEN (INSTL)(L)(N)(70)
EA 4.000 $25,000.000 $28,300.000 $25,500.000 $49,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 9.000 $9,000.000 $9,590.000 $8,650.000 $12,600.000
REMOVE RD IL ASM (TRANS-BASE)
EA 12.000 $520.000 $459.000 $775.000 $1,060.000
IN RD IL (U/P) (TY 1) (150W EQ) LED
EA 4.000 $2,000.000 $1,060.000 $1,312.000 $1,800.000
IN RD IL (U/P) (TY 2) (150W EQ) LED
EA 4.000 $1,150.000 $1,090.000 $1,333.000 $1,850.000
IN RD IL (TY SA) 40T-8 (250W EQ) LED
EA 24.000 $4,000.000 $4,390.000 $4,519.000 $6,200.000
CONDT (PVC) (SCH 40) (2")
LF 4,090.000 $12.000 $13.000 $14.000 $19.250
CONDT (PVC) (SCH 80) (2") (BORE)
LF 1,200.000 $25.000 $24.000 $22.320 $31.000
CONDT (PVC) (SCH 80) (3")
LF 10.000 $50.000 $41.000 $31.000 $43.000
CONDT (RM) (1")
LF 180.000 $30.000 $19.000 $32.000 $44.000
ELEC CONDR (NO.12) INSULATED
LF 540.000 $2.000 $1.250 $1.900 $2.750
ELEC CONDR (NO.8) INSULATED
LF 16,825.000 $2.000 $1.850 $2.200 $3.000
GROUND BOX TY A (122311)W/APRON
EA 11.000 $1,000.000 $903.000 $1,246.000 $1,750.000
REMOVE ELECTRICAL SERVICES
EA 2.000 $1,200.000 $1,180.000 $517.000 $710.000
ELC SRV TY A 240/480 060(SS)SS(E)GC(O)
EA 2.000 $10,000.000 $9,690.000 $8,745.000 $12,000.000
ELC SRV TY A 240/480 060(SS)SS(E)GC(U)
EA 1.000 $6,500.000 $11,500.000 $6,788.000 $9,300.000
ALUMINUM SIGNS (TY G)
SF 877.000 $30.000 $31.000 $28.000 $39.000
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 5.000 $1,000.000 $859.000 $775.000 $1,060.000
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 10.000 $1,000.000 $998.000 $900.000 $1,235.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 60.000 $1,000.000 $832.000 $750.000 $1,030.000
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 3.000 $1,000.000 $1,050.000 $950.000 $1,300.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 3.000 $1,000.000 $1,610.000 $1,450.000 $1,985.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 6.000 $1,000.000 $1,360.000 $1,225.000 $1,675.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 4.000 $2,500.000 $2,160.000 $1,950.000 $3,200.000
REMOVE SM RD SN SUP&AM
EA 50.000 $100.000 $83.000 $75.000 $103.000
INSTALL LRSS (STRUCT STEEL)
LB 5,372.000 $7.000 $6.100 $5.500 $10.000
REMOVE LRSA
EA 2.000 $1,000.000 $1,390.000 $1,250.000 $710.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 41.000 $20.000 $17.000 $15.000 $21.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 18.000 $20.000 $17.000 $15.000 $21.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
EA 22.000 $20.000 $116.000 $105.000 $145.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 13.000 $20.000 $116.000 $105.000 $145.000
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 3,577.000 $1.000 $0.850 $0.750 $1.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 11,985.000 $1.000 $0.700 $0.650 $1.000
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 3,355.000 $2.000 $1.900 $1.700 $2.050
WK ZN PAV MRK REMOV (W)12"(SLD)
LF 900.000 $5.000 $2.550 $2.300 $3.250
WK ZN PAV MRK REMOV (W)(ARROW)
EA 5.000 $200.000 $166.000 $150.000 $210.000
WK ZN PAV MRK REMOV (W)(WORD)
EA 3.000 $250.000 $305.000 $275.000 $375.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 15,224.000 $1.000 $0.700 $0.650 $1.000
REFL PAV MRK TY I (W)8"(DOT)(090MIL)
LF 243.000 $1.000 $0.900 $0.800 $1.250
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 6,194.000 $1.000 $0.900 $0.800 $1.250
REFL PAV MRK TY I (W)12"(SLD)(090MIL)
LF 1,059.000 $4.000 $3.100 $2.800 $4.000
REFL PAV MRK TY I (Y)12"(SLD)(090MIL)
LF 97.000 $4.000 $6.650 $6.000 $9.000
RE PM W/RET REQ TY I (W)6"(BRK)(090MIL)
LF 5,907.000 $0.500 $0.700 $0.620 $1.000
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 29,551.000 $0.500 $0.700 $0.620 $1.000
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 31,011.000 $0.250 $0.700 $0.620 $1.000
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 152.000 $15.000 $12.000 $11.000 $15.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 16.000 $250.000 $166.000 $150.000 $205.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 4.000 $400.000 $360.000 $325.000 $445.000
PREFAB PAV MRK TY C (W) (UTURN ARROW)
EA 4.000 $350.000 $388.000 $350.000 $480.000
PREFAB PAV MRK TY C (W) (WORD)
EA 18.000 $250.000 $305.000 $275.000 $375.000
PREFAB PAV MRK TY C (W) (18")(YLD TRI)
EA 18.000 $25.000 $13.000 $12.000 $17.000
REFL PAV MRKR TY II-A-A
EA 60.000 $4.000 $5.550 $5.000 $7.000
REFL PAV MRKR TY II-C-R
EA 666.000 $4.000 $4.250 $3.850 $6.000
ELIM EXT PAV MRK & MRKS (4")
LF 17,748.000 $0.250 $0.400 $0.350 $5.000
ELIM EXT PAV MRK & MRKS (8")
LF 800.000 $0.500 $1.100 $1.000 $9.000
REMOVAL OF SIGNAL POLE ASSM
EA 2.000 $600.000 $823.000 $517.000 $710.000
INSTL TIED CONCRETE EROSN CONTROL MATS
SF 33,086.000 $10.000 $8.650 $15.280 $6.000
D-GR HMA TY-B SAC-B PG64-22
TON 14,580.000 $150.000 $101.000 $125.400 $150.000
D-GR HMA TY-D SAC-B PG70-22
TON 13,145.000 $150.000 $117.000 $138.600 $180.000
TACK COAT
GAL 5,242.000 $5.000 $3.800 $4.210 $6.000
TIP TESTING(DRILL SHAFT)
EA 5.000 $5,000.000 $5,550.000 $5,444.990 $8,400.000
GEOGRID BASE REINFORCEMENT (TY II)
SY 69,889.000 $5.000 $1.250 $1.820 $2.000
REMOVE CONDUCTOR
LF 7,750.000 $1.000 $0.900 $0.660 $1.000
REMOVE GROUND BOX
EA 6.000 $350.000 $282.000 $259.000 $350.000
REMOVE FOUNDATION
EA 14.000 $400.000 $590.000 $750.000 $720.000
INSTALL FUSED DISCONNECT
EA 2.000 $800.000 $1,070.000 $991.000 $1,200.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 278.000 $100.000 $72.000 $127.210 $215.000
TMA (STATIONARY)
DAY 278.000 $150.000 $194.000 $254.410 $1,500.000
Totals: $25,403,884.490 $22,334,443.850 $28,970,082.176 $35,298,548.500