County: ANGELINA Highway: US0059 Date: 11/01/2023 (1 year ago) Engineer's Estimate: $727,945 Control Number: 6456-17-001
Project: BPM - 645617001 District: LUFKIN Time: 60 W Type: BRIDGE PREVENTATIVE MAINTENANCE
HCS
Pay Estimates: 1 | 2 | 3 | 4 | 5 | 6
Proposal

Bidders

Name Total Amount Place Over/Under Est Amt Left From Low Bid Delta Between Bidders
Engineer's Estimate $727,945.00
GARRET SHIELDS INFRASTRUCTURE   $583,220.00 1
-19.88% | -$144,725.00
ICOS MANAGEMENT, LLC   $665,912.00 2
-8.52% | -$62,033.00
14.18% | $82,692.00
STRUCTURAL INTEGRITY GROUP LLC   $671,959.00 3
-7.69% | -$55,986.00
15.22% | $88,739.00
0.91% | $6,047.00
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC   $676,508.00 4
-7.07% | -$51,437.00
16% | $93,288.00
0.68% | $4,549.00
THK CONSTRUCTION LLC   $717,320.00 5
-1.46% | -$10,625.00
22.99% | $134,100.00
6.03% | $40,812.00
AAD CONTRACTING INC.   $785,550.00 6
7.91% | $57,605.00
34.69% | $202,330.00
9.51% | $68,230.00
Subcontractor Percentage Amount
4-HORN TRAFFIC & BARRICADE, LLC 0.00% $0.00
FARR FOUNDATION, INC. 0.00% $0.00
STRIPING TECHNOLOGY, L.P. 0.00% $0.00
Total: 0.00% $0.00

Bid Items

Items: 17, 0 filtered
ANGELINA US0059  |  LUFKIN  |  6456-17-001  |  11/01/2023  |  $727,945  |  BPM - 645617001  |  BRIDGE PREVENT MAINT  |  60 W
Item code Description Unit Quantity Engineer's Estimate GARRET SHIELDS INFRASTRUCTURE ICOS MANAGEMENT, LLC STRUCTURAL INTEGRITY GROUP LLC AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC THK CONSTRUCTION LLC AAD CONTRACTING INC.
132 6019 EMBANKMENT (VEHICLE)(ORD COMP)(TY B) CY 58.000 $50.000 $100.000 $220.000 $150.000 $50.000 $40.000 $50.000
158 6003 SPEC EXCAV WORK (HYD EXCAVATOR) HR 26.000 $150.000 $120.000 $880.000 $260.000 $200.000 $150.000 $100.000
361 6051 FULL-DPTH REP(BR APPROACH SLAB)(9"-13") SY 48.000 $855.000 $1,000.000 $1,870.000 $1,100.000 $500.000 $250.000 $250.000
401 6001 FLOWABLE BACKFILL CY 51.000 $400.000 $600.000 $385.000 $530.000 $550.000 $800.000 $240.000
429 6003 CONC STR REPAIR(DECK REP(PART DEPTH)) SF 158.000 $250.000 $220.000 $330.000 $130.000 $300.000 $250.000 $200.000
429 6007 CONC STR REPAIR (VERTICAL & OVERHEAD) SF 330.000 $188.000 $200.000 $275.000 $215.000 $725.000 $150.000 $190.000
432 6027 RIPRAP (STONE COMMON)(DRY)(24 IN) CY 214.000 $200.000 $200.000 $275.000 $345.000 $230.000 $225.000 $250.000
438 6005 CLEANING AND SEALING JOINTS LF 1,616.000 $55.000 $40.000 $55.000 $44.000 $61.000 $75.000 $85.000
480 6002 CLEAN EXIST CULVERTS CY 335.000 $211.000 $100.000 $110.000 $175.000 $200.000 $50.000 $100.000
500 6001 MOBILIZATION LS 1.000 $67,000.000 $70,000.000 $33,000.000 $55,000.000 $72,000.000 $80,000.000 $75,000.000
502 6001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 7.000 $5,000.000 $5,000.000 $1.000 $9,000.000 $1.000 $10,000.000 $7,000.000
506 6038 TEMP SEDMT CONT FENCE (INSTALL) LF 500.000 $10.000 $1.000 $2.000 $1.000 $4.000 $10.000 $4.000
506 6039 TEMP SEDMT CONT FENCE (REMOVE) LF 500.000 $5.000 $1.000 $1.000 $1.000 $1.000 $5.000 $1.000
752 6005 TREE REMOVAL (4" - 12" DIA) EA 1.000 $20,000.000 $500.000 $3,300.000 $3,000.000 $3,000.000 $5,000.000 $300.000
780 6010 CNC CRACK REPAIR (DISCRETE)(SURF SEAL) LF 2,310.000 $80.000 $50.000 $44.000 $27.000 $9.500 $70.000 $85.000
6185 6002 TMA (STATIONARY) DAY 60.000 $400.000 $300.000 $1.000 $250.000 $1.000 $400.000 $150.000
7000 6002 REML & DISPL DRIFTWOOD & DEBRIS LS 7.000 $2,500.000 $2,000.000 $7,700.000 $11,750.000 $2,200.000 $5,000.000 $15,000.000
Totals: $727,945.00 $583,220.00 $665,912.00 $671,959.00 $676,508.00 $717,320.00 $785,550.00